[go: up one dir, main page]

CN101319580A - A construction method for constructing water storage facilities using soil solidification materials - Google Patents

A construction method for constructing water storage facilities using soil solidification materials Download PDF

Info

Publication number
CN101319580A
CN101319580A CNA2008101502546A CN200810150254A CN101319580A CN 101319580 A CN101319580 A CN 101319580A CN A2008101502546 A CNA2008101502546 A CN A2008101502546A CN 200810150254 A CN200810150254 A CN 200810150254A CN 101319580 A CN101319580 A CN 101319580A
Authority
CN
China
Prior art keywords
cellar
soil
water
layer
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2008101502546A
Other languages
Chinese (zh)
Other versions
CN100567685C (en
Inventor
高建恩
樊恒辉
孙胜利
王广周
杨世伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Institute Of Soil And Water Conservation Ministry Of Water Resources Chinese Academy Of Sciences
NATIONAL CENTER FOR EFFICIENT IRRIGATION ENGINEERING AND TECHNOLOGY RESEARCH-YANGLING
Northwest A&F University
Original Assignee
Institute Of Soil And Water Conservation Ministry Of Water Resources Chinese Academy Of Sciences
NATIONAL CENTER FOR EFFICIENT IRRIGATION ENGINEERING AND TECHNOLOGY RESEARCH-YANGLING
Northwest A&F University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Institute Of Soil And Water Conservation Ministry Of Water Resources Chinese Academy Of Sciences, NATIONAL CENTER FOR EFFICIENT IRRIGATION ENGINEERING AND TECHNOLOGY RESEARCH-YANGLING, Northwest A&F University filed Critical Institute Of Soil And Water Conservation Ministry Of Water Resources Chinese Academy Of Sciences
Priority to CNB2008101502546A priority Critical patent/CN100567685C/en
Publication of CN101319580A publication Critical patent/CN101319580A/en
Application granted granted Critical
Publication of CN100567685C publication Critical patent/CN100567685C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Processing Of Solid Wastes (AREA)
  • Curing Cements, Concrete, And Artificial Stone (AREA)

Abstract

本发明公开了一种利用土壤固化材料修建蓄水设施的施工方法,采用土壤固化剂和黄土、水制成干性混合料,然后在模板支护条件下将混合料夯实,形成水窖,该方法制备的水窖具有较高的强度和防渗性能,能够满足水窖对防渗和耐久性需求,且水质较好;干性施工工艺施工较为方便,施工成本低。本发明对推动水资源缺乏地区尤其是干旱半干旱地区的雨水集蓄利用技术发展具有重要的实用价值。

Figure 200810150254

The invention discloses a construction method for building a water storage facility using soil solidification materials, wherein a soil solidifier, loess and water are used to make a dry mixture, and then the mixture is compacted under the condition of formwork support to form a water cellar. The water cellar prepared by the method has high strength and anti-seepage performance, can meet the anti-seepage and durability requirements of the water cellar, and has good water quality; the dry construction process is relatively convenient and has low construction cost. The invention has important practical value for promoting the development of rainwater collection and utilization technology in areas with water shortage, especially in arid and semi-arid areas.

Figure 200810150254

Description

一种利用土壤固化材料修建蓄水设施的施工方法 A construction method for constructing water storage facilities using soil solidification materials

技术领域 technical field

本发明属旱区农业生活、生产与生态环境建设节水、蓄水及保水技术领域,主要涉及修建蓄水设施的材料与工艺,特别是一种利用土壤固化材料修建蓄水设施的方法,该方法适用于农村的蓄水设施,如水窖、水窑、水池、鱼塘、塘坝等防渗处理。The invention belongs to the technical field of water saving, water storage and water conservation in agricultural life, production and ecological environment construction in arid areas, and mainly relates to materials and techniques for building water storage facilities, especially a method for building water storage facilities using soil solidification materials. The method is suitable for anti-seepage treatment of water storage facilities in rural areas, such as water cellars, water kilns, pools, fish ponds, and ponds and dams.

背景技术 Background technique

我国是一个干旱缺水国家,人均水资源占有量2200m3,仅为世界人均占有量的1/4,现仍有2.5亿人饮水困难,约占全国总人口的20%,其中部分人口位于劣质苦咸水地区,利用水窖收集的雨水是重要水源;我国旱地面积约11亿亩,占我国耕地面积的60%左右,无灌溉设施与水源条件,只能依靠天然降水资源维持作物生长。实现旱作农田作物高产、稳产的根本措施是如何有效的提高天然降水资源的利用率和利用效率。实践证明,集雨补充灌溉农业是实现上述目标的有效途径。不仅如此,我国由于受季风气候影响,降雨过分集中,且时空分布不均,使得降雨与作物需水时间不同步,导致常年干旱和季节性干旱严重。理论和实践证明,雨水集蓄利用技术是解决水资源缺乏地区尤其是干旱半干旱地区人们生产生活用水的有效途径。蓄水设施如水窖是该技术体系的重要内容,也是其关键技术之一。目前,修建水窖材料多采用红胶泥、水泥砂浆、混凝土或塑料布等。红胶泥具有良好的防渗性能和较好的水质,但是材料难以获得,而且施工工艺极为烦琐,目前基本不采用;水泥砂浆和混凝土材料具有良好的耐久性和防渗性能,目前多采用,但是由于砂石等原材料的缺乏等原因使得成本较为昂贵,且水质不断受到质疑;膜料防渗效果较好,但是耐久性较差。这些材料的缺点极大地限制了雨水集蓄利用技术的发展与利用。因此,寻求一种经济、高效、环保,且便于施工的新型蓄水设施材料及其施工工艺一直是亟待解决的问题。China is a dry and water-scarce country, with a per capita water resource of 2200m 3 , which is only 1/4 of the world's per capita share. There are still 250 million people who have difficulty drinking water, accounting for about 20% of the total population of the country, and some of them are located in low-quality In brackish water areas, the rainwater collected by water cellars is an important water source; China's dry land area is about 1.1 billion mu, accounting for about 60% of China's cultivated land area, without irrigation facilities and water sources, and can only rely on natural precipitation resources to maintain crop growth. The fundamental measure to achieve high and stable yield of dryland crops is how to effectively improve the utilization rate and utilization efficiency of natural precipitation resources. Practice has proved that rain harvesting supplementary irrigation agriculture is an effective way to achieve the above goals. Not only that, due to the influence of the monsoon climate in my country, the rainfall is too concentrated and unevenly distributed in time and space, which makes the rainfall and crop water demand time out of sync, resulting in severe perennial drought and seasonal drought. Theory and practice have proved that rainwater storage and utilization technology is an effective way to solve the problem of water shortage areas, especially in arid and semi-arid areas. Water storage facilities such as water cellars are an important part of this technical system and one of its key technologies. At present, red clay, cement mortar, concrete or plastic sheets are mostly used as materials for building water cellars. Red cement has good anti-seepage performance and good water quality, but the material is difficult to obtain, and the construction process is extremely cumbersome, so it is basically not used at present; cement mortar and concrete materials have good durability and anti-seepage performance, and are currently mostly used, but Due to the lack of raw materials such as sand and gravel, the cost is relatively expensive, and the water quality is constantly questioned; the anti-seepage effect of the membrane material is good, but the durability is poor. The shortcomings of these materials have greatly limited the development and utilization of rainwater storage and utilization technologies. Therefore, seeking an economical, efficient, environmentally friendly, and easy-to-construct new water storage facility material and its construction technology has always been an urgent problem to be solved.

发明内容 Contents of the invention

本发明的目的是提供一种利用土壤固化材料修建蓄水设施的施工方法,该方法采用土壤固化材料,利用固化土干性施工技术,通过固化土代替水泥等材料防渗,达到防渗蓄水的目的。The purpose of the present invention is to provide a construction method for building water storage facilities using soil solidification materials. The method adopts soil solidification materials, utilizes solidified soil dry construction technology, and replaces materials such as cement with solidified soil for anti-seepage, so as to achieve anti-seepage water storage the goal of.

为了实现上述任务,本发明采取以下的技术解决方案:In order to achieve the above tasks, the present invention takes the following technical solutions:

一种利用土壤固化材料修建蓄水设施的施工方法,其特征在于,该方法采用土壤固化剂和黄土、水制成干性混合料,然后在模板支护条件下将混合料夯实,形成水窖(蓄水设施),其特征在于,至少包括以下步骤:A construction method for constructing water storage facilities using soil-solidifying materials, characterized in that the method uses a soil-solidifying agent, loess, and water to make a dry mixture, and then tamps the mixture under the condition of formwork support to form a water cellar (Water storage facility), is characterized in that, at least comprises the following steps:

1)将水窖按要求开挖成型,并将水窖的内表面处理成毛面;1) Excavate and form the water cellar as required, and treat the inner surface of the water cellar to a rough surface;

2)将窖底地基进行翻夯,翻夯后的干密度不小于1.8g/cm3,窖底厚度为20cm~25cm,并使窖底地基平整;2) Compact the foundation of the cellar bottom, the dry density after compaction is not less than 1.8g/cm 3 , the thickness of the cellar bottom is 20cm-25cm, and the foundation of the cellar bottom is leveled;

3)按水窖用料重量的1.2倍准备土料,土料粉碎后过10mm土壤筛,并检测土料的含水率,保持土料的含水率为(1.15wop+2)%,其中wop表示最优含水量;3) Prepare the soil material according to 1.2 times the weight of the material used in the water cellar. After the soil material is crushed, pass through a 10mm soil sieve, and check the moisture content of the soil material to keep the moisture content of the soil material (1.15w op +2)%, where w op represents the optimal water content;

4)在土料中加入土壤固化剂,土壤固化剂与土料的重量比为1∶10,然后搅拌均匀,得到固化土混合料;4) adding a soil curing agent to the soil material, the weight ratio of the soil curing agent to the soil material is 1:10, and then stirring evenly to obtain a solidified soil mixture;

5)将固化土混合料按照松铺系数1.2~1.3摊铺窖底,然后将摊铺后的固化土混合料夯实,夯实密度不小于1.8g/cm3,固化窖底厚度不小于30cm;5) Spread the solidified soil mixture on the bottom of the cellar according to the loose paving coefficient of 1.2 to 1.3, and then tamp the solidified soil mixture after paving, the compacted density is not less than 1.8g/cm 3 , and the thickness of the solidified cellar bottom is not less than 30cm;

6)窖底制成后,按照水窖形状用模板和脚手架制作窖壁防渗层支护,使窖壁厚度不小于10cm;6) After the bottom of the cellar is made, formwork and scaffolding are used to support the impermeable layer of the cellar wall according to the shape of the cellar, so that the thickness of the cellar wall is not less than 10cm;

7)将固化土混合料层层填入模板内,分层制作窖壁,每层防渗层厚度不超过20cm,并进行夯实,夯实密度不小于1.7g/cm3,夯实过程中,层与层之间表面进行拉毛处理;7) Fill the solidified soil mixture into the formwork layer by layer, and make the cellar wall layer by layer. The thickness of each layer of anti-seepage layer is not more than 20cm, and it is tamped. The tamping density is not less than 1.7g/cm 3 . The surface between the layers is brushed;

8)水窖制作结束12h~18h后,先对窖底和窖壁洒水养护2d,以保持窖底和窖壁的表面湿润,待固化土形成一定强度后,按水窖容积注入0.02倍~0.04倍体积的水,封闭水窖口部,继续养护10d即可。8) 12 to 18 hours after the completion of the water cellar, first sprinkle water on the bottom and wall of the cellar for 2 days to keep the surface of the bottom and wall moist. After the solidified soil forms a certain strength, inject 0.02 to 0.04 Double the volume of water, close the mouth of the water cellar, and continue to maintain for 10 days.

采用本发明的方法修建的水窖,结合粘土水窖与混凝土水窖的优点,渗透系数<10-8cm/s,使用寿命可达15~20年,与混凝土水窖基本相同,而且对环境无污染,其建造成本仅为混凝土水窖建造成本的三分之一,且水质优于混凝土水窖;具有较高的强度和防渗性能,能够满足水窖对防渗和耐久性的需求;施工较为简便,降低了施工成本。特别适用于广大黄土高原和其它无砂石料地区,对推动旱区集雨补灌农业的发展具有重要的实际意义。The water cellar built by the method of the present invention combines the advantages of the clay water cellar and the concrete water cellar, the permeability coefficient is less than 10 -8 cm/s, and the service life can reach 15-20 years, which is basically the same as that of the concrete water cellar, and it is environmentally friendly. No pollution, its construction cost is only one-third of the construction cost of concrete water cellars, and the water quality is better than that of concrete water cellars; it has high strength and anti-seepage performance, which can meet the needs of water cellars for anti-seepage and durability; The construction is relatively simple and the construction cost is reduced. It is especially suitable for the vast Loess Plateau and other areas without sand and gravel, and has important practical significance for promoting the development of rain harvesting and supplementary irrigation agriculture in arid areas.

附图说明 Description of drawings

图1是土壤固化材料修建水窖示意图;其中,(a)是主视图,图(b)是(a)图的A处局部放大图;Fig. 1 is a schematic diagram of building a water cellar with soil solidification materials; wherein, (a) is a front view, and figure (b) is a partial enlarged view of A place of (a) figure;

图2是施工流程示意图;Figure 2 is a schematic diagram of the construction process;

图3是实施例的具体施工示意图。Fig. 3 is the concrete construction schematic diagram of embodiment.

以下结合附图和发明人给出的具体实施例对本发明作进一步的详细描述。The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments given by the inventor.

具体实施方式 Detailed ways

本发明是利用发明人拥有的土壤固化材料专利技术修建蓄水设施的施工方法,其施工的原材料包括土壤固化材料、土壤、水等,主要设备为搅拌机、摸板、脚手架、铁锨、泥刀、瓦刀、石夯等。The present invention is a construction method for constructing water storage facilities using the patented technology of soil solidification materials owned by the inventor. The raw materials for construction include soil solidification materials, soil, water, etc., and the main equipment is a mixer, template, scaffolding, shovel, trowel, Tile knife, stone rammer, etc.

以下是发明人给出的实施例:Below are the embodiments given by the inventor:

参见附图,按照图1给出的水窖在地面以下开挖水窖1,制作进水管1与沉淀池相连接。图1(b)是图1(a)图的侧壁A处局部施工放大图样。Referring to accompanying drawing, according to the water cellar that Fig. 1 provides, excavate water cellar 1 below ground, make water inlet pipe 1 and be connected with sedimentation tank. Fig. 1(b) is an enlarged partial construction drawing at side wall A of Fig. 1(a).

本实施例所采用的土壤固化剂是申请人发明的MBER土壤固化剂(中国专利,专利号:zL 200410073273.5),土料采用杨凌黄土。The soil curing agent used in this embodiment is the MBER soil curing agent invented by the applicant (Chinese patent, patent number: zL 200410073273.5), and the soil material adopts Yangling loess.

按需求根据相关规范设计水窖2;按照图3的施工示意图进行:Design the water cellar 2 according to the relevant specifications according to the requirements; proceed according to the construction schematic diagram in Figure 3:

1)施工放样:按照净尺寸以及开挖尺寸进行施工放样,应布设中线、边线,在桩上应设标记,进行高程测量,标出水窖2的设计高度;1) Construction stakeout: carry out construction stakeout according to net size and excavation size, centerline and sideline should be laid out, marks should be set on piles, elevation measurement should be carried out, and the design height of water cellar 2 should be marked;

2)开挖并翻夯窖底:将水窖开挖出来,并将水窖内表面处理成毛面。将窖底地基进行翻夯,翻夯后的干密度不小于1.8g/cm3,窖底厚度为20cm~25cm,并使窖底地基平整;2) Excavate and ram the bottom of the cellar: Excavate the cellar and treat the inner surface of the cellar to a rough surface. The foundation of the cellar bottom shall be compacted, the dry density after compaction shall not be less than 1.8g/cm 3 , the thickness of the cellar bottom shall be 20cm-25cm, and the foundation of the cellar bottom shall be leveled;

3)混合料准备:3) Mixture preparation:

粉碎土块:按设计用料1.2倍重量将土块进行粉碎,过10mm土壤筛;Crush soil clods: crush the soil clods according to 1.2 times the weight of the designed material, and pass through a 10mm soil sieve;

洒水闷料:检测土中的含水率,宜在(1.15wop+2)%左右,其中,wop表示最优含水量,当不能满足要求时,应对土采取洒水或晾干处理措施。Sprinkle water: check the moisture content in the soil, it should be around (1.15w op +2)%, where w op represents the optimal moisture content, if the requirements cannot be met, the soil should be watered or dried.

拌和混合料:计算土壤固化剂材料的用量,按固化剂与土重量1∶10用量,将土壤固化剂加入土中进行搅拌,使其均匀并使其含水量达到设计要求;Mixing and mixing: calculate the amount of soil curing agent material, according to the amount of curing agent and soil weight 1:10, add soil curing agent to the soil and stir to make it uniform and make the water content meet the design requirements;

4)将固化土混合料按照1.2~1.3的松铺系数进摊铺形成窖底地基5,将窖底地基5进行翻夯到设计厚度(不小于30cm),固化窖底地基5的干密度不应小于1.8g/cm3,并使其较为平整。4) Spread the solidified soil mixture according to the loose paving coefficient of 1.2 to 1.3 to form the pit bottom foundation 5, and tamp the pit bottom foundation 5 to the design thickness (not less than 30cm), and the dry density of the solidified pit bottom foundation 5 is not less than 30 cm. It should be less than 1.8g/cm 3 and make it relatively flat.

5)窖壁支护:采用模板和脚手架按不小于10cm窖壁厚度进行支护。5) Cellar wall support: formwork and scaffolding are used to support the cellar wall with a thickness of not less than 10cm.

6)夯实窖壁:将固化土混合料填入水窖模板内,按照每层不大于20cm的厚度进行夯实,层与层之间需要拉毛处理;6) Ramping the cellar wall: fill the solidified soil mixture into the water cellar formwork, and tamp it according to the thickness of each layer not greater than 20cm, and roughening is required between layers;

7)养护:砌筑结束12~18h后及时养护,经常保持表面湿润。洒水养护2d后,在蓄水设施中注入设计蓄水容积的(0.02~0.04)倍体积水,密封蓄水设施口,继续养护10d即可。7) Maintenance: timely maintenance 12-18 hours after the completion of masonry, and always keep the surface moist. After 2 days of watering maintenance, inject (0.02-0.04) times the designed water storage volume into the water storage facility, seal the water storage facility opening, and continue curing for 10 days.

8)养护期间,在水窖顶部上方覆混凝土盖板,混凝土盖板缝之间采用水泥砂浆进行粘合处理,防止上层杂质落入水窖中。8) During the maintenance period, cover the top of the water cellar with a concrete cover plate, and use cement mortar to bond the joints between the concrete cover plates to prevent the upper layer of impurities from falling into the water cellar.

9)在混凝土盖板上覆盖约35cm的土层,要求密实。9) Cover about 35cm of soil layer on the concrete cover plate, which is required to be dense.

10)水窖的扶手及水管最好在施工工程中进行安装到位。10) The handrails and water pipes of the water cellar are best installed in place during the construction project.

申请人对上述实施例制作的水窖进行了力学指标和抗渗系数的测试,结果表明,固化后的土体7d无侧限抗压强度在1.72Mpa~278Mpa之间,渗透系数在n×10-7~n×10-8cm/s之间,属于相对不透水层。说明土壤经过固化剂处理后,具有良好的防渗效果和强度,能够满足修建水窖等蓄水设施的要求。The applicant tested the mechanical index and anti-seepage coefficient of the water cellar made in the above embodiment, and the results showed that the 7d unconfined compressive strength of the solidified soil was between 1.72Mpa and 278Mpa, and the permeability coefficient was between n×10 Between -7 and n×10 -8 cm/s, it belongs to the relatively impermeable layer. It shows that after the soil is treated with the curing agent, it has good anti-seepage effect and strength, which can meet the requirements of building water storage facilities such as water cellars.

当然,也可以采用市售常规的高性能土壤固化材料,按照上述实施例的步骤,同样也能够满足修建水窖等蓄水设施的要求。Of course, commercially available conventional high-performance soil stabilization materials can also be used. According to the steps of the above-mentioned embodiments, the requirements for building water storage facilities such as water cellars can also be met.

Claims (2)

1.一种利用土壤固化材料修建蓄水窖的施工方法,其特征在于,至少包括以下步骤:1. A construction method utilizing soil solidification material to build a water storage cellar, is characterized in that, at least comprises the following steps: 1)将水窖按要求开挖成型,并将水窖的内表面处理成毛面;1) Excavate and form the water cellar as required, and treat the inner surface of the water cellar to a rough surface; 2)将窖底地基进行翻夯,翻夯后的干密度不小于1.8g/cm3,窖底厚度为20cm~25cm,并使窖底地基平整;2) Compact the foundation of the cellar bottom, the dry density after compaction is not less than 1.8g/cm 3 , the thickness of the cellar bottom is 20cm-25cm, and the foundation of the cellar bottom is leveled; 3)按水窖用料重量的1.2倍准备土料,土料粉碎后过10mm土壤筛,并检测的土料的含水率,保持土料的含水率为(1.15wop+2)%,其中wop表示最优含水量;3) Prepare the soil material according to 1.2 times the weight of the material used in the water cellar, pass the 10mm soil sieve after the soil material is crushed, and check the moisture content of the soil material to keep the moisture content of the soil material (1.15w op +2)%. w op represents the optimal water content; 4)在土料中加入土壤固化剂,土壤固化剂与土料的重量比为1∶10,然后搅拌均匀,得到固化土混合料;4) adding a soil curing agent to the soil material, the weight ratio of the soil curing agent to the soil material is 1:10, and then stirring evenly to obtain a solidified soil mixture; 5)将固化土混合料按照松铺系数1.2~1.3摊铺窖底,摊铺后的将固化土混合料夯实,使窖底部厚度不小于30cm;5) Spread the solidified soil mixture on the bottom of the pit according to the loose paving coefficient of 1.2 to 1.3, and tamp the solidified soil mixture after paving, so that the thickness of the bottom of the pit is not less than 30cm; 6)窖底制成后,按照水窖形状用模板和脚手架制作窖壁防渗层支护,使窖壁厚度不小于10cm;6) After the bottom of the cellar is made, formwork and scaffolding are used to support the impermeable layer of the cellar wall according to the shape of the cellar, so that the thickness of the cellar wall is not less than 10cm; 7)将固化土混合料层层填入模板内,分层制作窖壁,每层防渗层厚度不超过20cm,并进行夯实,夯实密度不小于1.7g/cm3,夯实过程中,层与层之间表面进行拉毛处理;7) Fill the solidified soil mixture into the formwork layer by layer, and make the cellar wall layer by layer. The thickness of each layer of anti-seepage layer is not more than 20cm, and it is tamped. The tamping density is not less than 1.7g/cm 3 . The surface between the layers is brushed; 8)水窖制作结束12h~18h后,先对窖底和窖壁洒水养护2d,以保持窖底和窖壁的表面湿润,待固化土形成一定的强度后,按水窖容积注入0.02倍~0.04倍体积的水,封闭水窖口部,继续养护10d即可。8) 12 to 18 hours after the completion of the water cellar, first sprinkle water on the bottom and wall of the cellar for 2 days to keep the surface of the bottom and wall of the cellar moist. After the solidified soil has formed a certain strength, inject 0.02~ 0.04 times the volume of water, close the mouth of the water cellar, and continue to maintain for 10 days. 2.如权利要求1所述的方法,其特征在于,所述的土壤固化剂是MBER土壤固化剂或常规的高性能的土壤固化材料。2. The method according to claim 1, characterized in that, said soil solidifying agent is MBER soil stabilizing agent or conventional high-performance soil stabilizing material.
CNB2008101502546A 2008-07-04 2008-07-04 A construction method for constructing water storage facilities using soil solidification materials Expired - Fee Related CN100567685C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2008101502546A CN100567685C (en) 2008-07-04 2008-07-04 A construction method for constructing water storage facilities using soil solidification materials

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2008101502546A CN100567685C (en) 2008-07-04 2008-07-04 A construction method for constructing water storage facilities using soil solidification materials

Publications (2)

Publication Number Publication Date
CN101319580A true CN101319580A (en) 2008-12-10
CN100567685C CN100567685C (en) 2009-12-09

Family

ID=40179817

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2008101502546A Expired - Fee Related CN100567685C (en) 2008-07-04 2008-07-04 A construction method for constructing water storage facilities using soil solidification materials

Country Status (1)

Country Link
CN (1) CN100567685C (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101575850B (en) * 2009-06-08 2011-05-11 西北农林科技大学 Construction and maintenance method for buliding rainwater-collecting engineering collector face using soil solidifying agent
CN102094542A (en) * 2010-12-24 2011-06-15 江苏河海新能源有限公司 Method for manufacturing energy storage underground water tank and support member for energy storage underground water tank
CN103541573A (en) * 2013-08-13 2014-01-29 刘安华 Air mold pouring polymerization concrete air inflation detection type small water cellar, construction method of small water cellar, application of small water cellar in biogas digester construction and inflatable model special for small water cellar
CN105660264A (en) * 2015-12-25 2016-06-15 易威 Fiber foundation bed used for plant fixation and production technology thereof
CN106592565A (en) * 2016-11-01 2017-04-26 西北农林科技大学 Dam fixing and protecting construction method using soil stabilizer in land reclamation project
CN109565987A (en) * 2019-01-16 2019-04-05 安徽工程大学 A kind of chiltern alkaline land soil prosthetic device and its restorative procedure

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101575850B (en) * 2009-06-08 2011-05-11 西北农林科技大学 Construction and maintenance method for buliding rainwater-collecting engineering collector face using soil solidifying agent
CN102094542A (en) * 2010-12-24 2011-06-15 江苏河海新能源有限公司 Method for manufacturing energy storage underground water tank and support member for energy storage underground water tank
CN102094542B (en) * 2010-12-24 2013-02-06 江苏河海新能源有限公司 Method for manufacturing energy storage underground water tank and support member for energy storage underground water tank
CN103541573A (en) * 2013-08-13 2014-01-29 刘安华 Air mold pouring polymerization concrete air inflation detection type small water cellar, construction method of small water cellar, application of small water cellar in biogas digester construction and inflatable model special for small water cellar
CN103541573B (en) * 2013-08-13 2015-09-09 刘安华 A kind of gas mould builds the little water cellar of high-performance polymerization concrete inflation inspection formula, construction method, application and special inflating mold
CN105660264A (en) * 2015-12-25 2016-06-15 易威 Fiber foundation bed used for plant fixation and production technology thereof
CN106592565A (en) * 2016-11-01 2017-04-26 西北农林科技大学 Dam fixing and protecting construction method using soil stabilizer in land reclamation project
CN106592565B (en) * 2016-11-01 2019-06-04 西北农林科技大学 A kind of construction method of soil stabilization agent for dyke and sill construction in land remediation engineering
CN109565987A (en) * 2019-01-16 2019-04-05 安徽工程大学 A kind of chiltern alkaline land soil prosthetic device and its restorative procedure
CN109565987B (en) * 2019-01-16 2021-08-27 安徽工程大学 Sandy saline-alkali soil remediation device and remediation method thereof

Also Published As

Publication number Publication date
CN100567685C (en) 2009-12-09

Similar Documents

Publication Publication Date Title
CN104264692B (en) A kind of side slope ecological renovation method
CN109736291B (en) A biocement reinforced roadbed on underconsolidated silt blowing foundation and a construction method thereof
CN101446082B (en) Construction method of building anti-permeability channel using soil curing agent
CN101575850B (en) Construction and maintenance method for buliding rainwater-collecting engineering collector face using soil solidifying agent
CN105272071A (en) Sponge concrete brick and application thereof
CN103821155B (en) Prefabricating and using method of planting growing building block for ecologically repairing exposed slope
CN111424689A (en) Protection method for improving soil slope resistance to rainwater erosion by adopting phosphogypsum and microorganisms
CN101319580A (en) A construction method for constructing water storage facilities using soil solidification materials
CN107034767A (en) A kind of full pervious concrete pavement structure of regeneration aggregate and its construction method
CN208857626U (en) A permeable and water storage pavement structure
CN103570310A (en) Revetment member of vegetation type porous concrete and preparation method thereof
CN103553471A (en) Method for manufacturing water permeable brick from waste concrete, and pavement method of water permeable brick
CN108059476A (en) A kind of permeable concrete and preparation method thereof
CN101302749A (en) Construction method of building water storage facilities using soil solidified materials
CN111472320A (en) A method for ecological transformation of black and odorous river channels using construction waste recycled materials and silt
CN105104062A (en) Construction method of multi-functional city sponge green space
CN204898694U (en) Living concrete member is planted to prefabricated chain formula
CN204803703U (en) Concrete road surface water collect structures permeates water
CN212896172U (en) River course slope protection and canal bottom structure for ecological reconstruction of black and odorous river course
CN109555135A (en) A kind of non-sintered haydite concrete of dredging silt plants raw building block and roadbed slope ecological protection construction method
CN201670764U (en) A vegetative concrete block capable of purifying water
CN107129208A (en) A kind of bioactivity, porous gap coarse aggregate ecological revetment matrix engineering material
CN110066159A (en) A kind of purified water type greening brick and preparation method thereof applied to ecological slope protection
CN207348029U (en) Environmental open drain based on straw resource utilization
CN206828912U (en) A kind of full pervious concrete pavement structure of regeneration aggregate

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20091209

Termination date: 20100704