[go: up one dir, main page]

CN100567659C - The basic structure of the tower - Google Patents

The basic structure of the tower Download PDF

Info

Publication number
CN100567659C
CN100567659C CNB200580029551XA CN200580029551A CN100567659C CN 100567659 C CN100567659 C CN 100567659C CN B200580029551X A CNB200580029551X A CN B200580029551XA CN 200580029551 A CN200580029551 A CN 200580029551A CN 100567659 C CN100567659 C CN 100567659C
Authority
CN
China
Prior art keywords
iron tower
foundation
concrete
steel pipe
piles
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB200580029551XA
Other languages
Chinese (zh)
Other versions
CN101010465A (en
Inventor
田边成
松尾敏
吉本正浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyo Electric Power Co Holdings Inc
Original Assignee
Tokyo Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Electric Power Co Inc filed Critical Tokyo Electric Power Co Inc
Publication of CN101010465A publication Critical patent/CN101010465A/en
Application granted granted Critical
Publication of CN100567659C publication Critical patent/CN100567659C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)

Abstract

本发明提供一种铁塔的基础构造,在将口径相对较小的多根桩体设置在地基中的基础构造形式中,通过使基础的小规模化成为可能,能够缩短施工时间,降低挖掘量、减少混凝土浇筑量等。将打入地基中的多根桩体(1、1…)与铁塔的主桩柱(2)通过混凝土结构体(3)接合的铁塔的基础构造中,所述混凝土结构体(3)是将混凝土(6)浇筑入在内壁面沿上下方向具有多段沿着周方向固定设置的抗剪凸缘(4、4…)的钢管(5)内而制成的结构体,在所述混凝土结构体(3)的下部侧接合打入所述地基中的多根桩体(1、1…)的顶部,并且,在所述铁塔主桩柱(2)的下部外面上设有多段支承板(7、7…),设有该支承板(7、7…)的主桩柱部分(K)埋设在所述混凝土结构体(3)中。

Figure 200580029551

The present invention provides a foundation structure of an iron tower. In a foundation structure form in which a plurality of piles with a relatively small diameter are arranged in a foundation, the construction time can be shortened and the amount of excavation can be reduced by making the foundation small-scale. Reduce the amount of concrete pouring, etc. In the foundation structure of the iron tower, the multiple piles (1, 1...) driven into the foundation and the main piles (2) of the iron tower are joined by a concrete structure (3), the concrete structure (3) is A structure made by pouring concrete (6) into a steel pipe (5) with multiple sections of shear flanges (4, 4...) fixed along the circumferential direction on the inner wall along the vertical direction, the concrete structure The lower side of (3) joins the tops of a plurality of piles (1, 1...) driven into the foundation, and a multi-section support plate (7) is provided on the outer surface of the lower part of the main pile (2) of the iron tower , 7...), the main pile part (K) provided with the support plate (7, 7...) is embedded in the concrete structure (3).

Figure 200580029551

Description

铁塔的基础构造 The basic structure of the tower

技术领域 technical field

本发明涉及一种通过混凝土结构体将打入地基中的多个桩体和铁塔的主桩柱接合的铁塔的基础构造。The present invention relates to a foundation structure of an iron tower in which a plurality of piles driven into a foundation are joined to main piles of the iron tower through a concrete structure.

背景技术 Background technique

作为支撑上述铁塔主桩柱的基础构造,在支撑层相对较深的情况下,如图6所示,在地基中打入多个口径相对较小的桩体50、50…后,利用钢筋混凝土制成连接这些桩体50、50…顶部的基脚(footing)51,将该基脚51与铁塔的主桩柱52连接的方式是普遍使用的(参照下述专利文献1等)。As the basic structure supporting the main piles of the above-mentioned iron tower, when the supporting layer is relatively deep, as shown in Figure 6, after driving a plurality of piles 50, 50... with relatively small diameters into the foundation, use reinforced concrete It is common practice to form a footing 51 connecting the tops of these pile bodies 50, 50..., and to connect this footing 51 to the main pile 52 of the iron tower (see Patent Document 1, etc. below).

并且,对于上述基脚51和主桩柱52的固定构造,大致区分的话,存在螺栓固定方式、锚部件固定方式、支承板固定方式等方式。螺栓固定方式如图6所示,是利用多根地脚螺栓54、54…固定设在主桩柱52底面上的基板53的方式,上述锚部件固定方式如图7(A)~(C)所示,是通过焊接等将安装板56固定设置在埋设在基脚51上的主桩柱的下部周面上,将隔着该安装板56左右成对的角钢57、57螺栓接合的构造在周围设置多处的固定方式,上述支承板固定方式如图8所示,利用在埋设于基脚51中的主桩柱52的底面和/或外面向外方突出设置的环状等的支承板58、58…进行固定的方式。In addition, the fixing structure of the footing 51 and the main pile 52 can be roughly classified into a bolt fixing method, an anchor member fixing method, a support plate fixing method, and the like. As shown in Figure 6, the bolt fixing method is to utilize a plurality of anchor bolts 54, 54... to fix the base plate 53 on the bottom surface of the main pile 52. The above-mentioned anchor component fixing method is shown in Figure 7 (A)-(C). As shown, the installation plate 56 is fixedly installed on the lower peripheral surface of the main pile buried on the footing 51 by welding or the like, and the left and right paired angle steels 57, 57 are bolted to each other through the installation plate 56. Multiple fixing methods are arranged around, and the above-mentioned supporting plate fixing method is shown in FIG. 58, 58... The way to fix.

另一方面,基脚和桩顶部的接合方式采用如下所述方式:如图9(A)所示,利用在没入基脚51内的桩顶部的外面向外方突出设置的环状等支承板59、59…进行固定的支承板接合方式;或者如图9(B)所示,设置横贯桩顶部和基脚51的多根钢筋60、60…并进行接合的钢筋接合方式等。On the other hand, the joint method of the footing and the top of the pile is as follows: As shown in FIG. 59, 59... to fix the supporting plate joining method; or as shown in Fig. 9(B), a plurality of steel bars 60, 60... which traverse the top of the pile and the footing 51 are set and joined.

另一方面,为了实现基础构造的简化,在下述专利文件2(参照图10)中,提出了一种铁塔基础构造,将下端具有比桩体直径大的挖掘叶片的旋转压入钢管桩70、70…沿倾斜方向压入设置于地底,旋转压入钢管桩70、70…的上端连接固定在铁塔脚部71的下端部而构成,在地底沿倾斜方向设置的旋转压入钢管桩70和向上方延伸的铁塔脚部71呈直线状。On the other hand, in order to realize the simplification of the foundation structure, in the following patent document 2 (see FIG. 10 ), a steel tower foundation structure is proposed. , 70 ... are pressed into the ground along the inclined direction, and the upper ends of the rotary press-in steel pipe piles 70, 70 ... are connected and fixed to the lower end of the iron tower foot 71. 70 and the iron tower foot 71 extending upwards are linear.

专利文件1:特开平9-3882号公报Patent Document 1: JP-9-3882 Gazette

专利文件2:特开2003-166254号公报Patent Document 2: JP-A-2003-166254 Gazette

在上述供电铁塔的基础中,如图11所示,与铁塔自重、电线自重的影响相比,更强烈地受到电线的放线张力、台风或季风等风负荷的影响。其结果是,与其他因素所产生的全部压缩负荷相比,翻转力矩变大,因此下风侧的铁塔脚部上作用有压缩负荷,而在上风侧的铁塔脚部上作用有大约相当于压缩负荷(压入力)的70%的拉拔负荷(拉拔力)。并且,由于上述压入力和拉拔力产生的力偶,作用有弯曲力矩,并且作用有水平力。As shown in Fig. 11, the foundation of the above-mentioned power supply tower is more strongly affected by the pay-out tension of the wire and wind load such as typhoon or monsoon than the influence of the tower's own weight and the wire's own weight. As a result, the overturning moment becomes large compared to the total compressive load due to other factors, so that a compressive load acts on the tower foot on the leeward side, and approximately the same compressive load acts on the tower foot on the windward side. 70% of the pull-out load (pull-out force) of the (press-fit force). And, due to the force couple generated by the above-mentioned pressing force and pulling force, a bending moment acts and a horizontal force acts.

因此,在支撑铁塔脚部的基础(基脚)处,如图12所示,如果在主桩柱52和基脚51的固定部上,基脚过浅,则会产生以主桩柱52的基部为中心的锥状的剪切裂纹61,导致固定部的破坏。并且,如图13所示,在桩体50过于靠近基脚51的外边缘时,可能从固定部到外侧产生割裂裂纹状的剪切裂纹62、62…,产生固定部的破坏。并且,基脚过薄时,如该图所示,会有有时产生以桩体50为中心的锥状的剪切裂纹61等问题。Therefore, at the foundation (footing) supporting the foot of the iron tower, as shown in FIG. The cone-shaped shear crack 61 centered on the base leads to destruction of the fixed part. Moreover, as shown in FIG. 13 , when the pile body 50 is too close to the outer edge of the footing 51 , shear cracks 62 , 62 . In addition, when the footing is too thin, as shown in the figure, there may be problems such as a tapered shear crack 61 centered on the pile body 50 .

因此,如果设计对于这些压入力、拉拔力、弯曲力矩以及水平力具有充分耐力且不会产生裂纹的基脚51,基脚的规模变得大型化,并且也会与基脚规模增大相应地产生挖掘量变多、且混凝土浇筑量变多等问题,施工需要较多时间和劳力。Therefore, if the footing 51 is designed to have sufficient resistance to these pressing force, pulling force, bending moment, and horizontal force without causing cracks, the scale of the footing will become larger, and the scale of the footing will also increase accordingly. The amount of excavation increased and the amount of concrete poured increased, and the construction required a lot of time and labor.

另一方面,在上述专利文件2所述的基础构造的情况下,由于没有基脚,因此消除了上述问题,但是为了将大口径的钢管桩70打入地基中,需要大型重机械,特别是存在无法或难以在山岳地带的铁塔基础的构建中采用该技术等问题。On the other hand, in the case of the foundation structure described in the above-mentioned Patent Document 2, since there is no footing, the above-mentioned problem is eliminated, but in order to drive the steel pipe pile 70 with a large diameter into the foundation, a large heavy machine is required, especially It is impossible or difficult to adopt this technology in the construction of iron tower foundations in mountainous areas.

发明内容 Contents of the invention

因此,本发明的主要课题是提供一种铁塔的基础构造,在地基中设置多个口径相对较小的桩体,可使基础小规模化,由此能够实现缩短施工时间、减少挖掘量,并减少混凝土的浇筑量等。Therefore, the main subject of the present invention is to provide a foundation structure of an iron tower. A plurality of piles with relatively small diameters are arranged in the foundation, which can make the foundation small-scale, thereby shortening the construction time, reducing the amount of excavation, and Reduce the amount of concrete poured, etc.

为了解决上述问题,技术方案1的本发明提供一种铁塔的基础构造,通过混凝土结构体将打入地基中的多根桩体与铁塔的主桩柱接合,其特征在于,上述混凝土结构体是将混凝土浇筑入在内壁面沿上下方向具有多段沿圆周方向固定设置的抗剪凸缘的钢管内而制成的结构体,在上述混凝土结构体的下部侧接合打入上述地基中的多根桩体的顶部,且在上述铁塔主桩柱的下部设有固定部件,设有上述固定部件的主桩柱部分埋设在上述混凝土结构体中。In order to solve the above problems, the present invention of technical scheme 1 provides a basic structure of an iron tower, and a plurality of piles driven into the foundation are connected with the main piles of the iron tower through a concrete structure, wherein the above-mentioned concrete structure is A structure made by pouring concrete into a steel pipe with a plurality of segments of shear flanges fixed in the circumferential direction on the inner wall surface, and a plurality of piles driven into the foundation are joined to the lower side of the concrete structure The top of the body, and the lower part of the main pile of the iron tower is provided with a fixing part, and the main pile with the fixing part is partially buried in the above-mentioned concrete structure.

在上述技术方案1所述的本发明中,作为接合首先打入地基中的多根桩体和铁塔的主桩柱的混凝土结构体,是通过将混凝土浇筑入在内壁面沿上下方向具有多段沿圆周方向固定设置的抗剪凸缘的钢管内而制成的结构体。In the present invention described in the above-mentioned technical solution 1, as a concrete structure that joins a plurality of piles driven into the foundation first and the main pile of the iron tower, the concrete structure is poured into the inner wall surface to have a plurality of sections along the vertical direction. A structure made in a steel pipe with shear flanges fixed in the circumferential direction.

以往,铁塔主桩柱的固定部的设计,通过根据混凝土的容许拉伸应力、容许剪切应力的固定耐力进行加强,在由安全性的检测预测出固定耐力不充分时,为了进一步提高固定耐力,进行根据经验规则的加强,因而有时进行了过度加强。本申请人鉴于上述状况,对于有效的基础设计以及加强进行了锐意讨论,其结果如特开2000-345571号公报中公开所示,连续的应力作用于主桩柱时,在混凝土上产生水平的裂纹或垂直的裂纹(割裂裂纹)。并且发现,在支承固定方式时,较大受到上述割裂裂纹产生所导致的影响,在该割裂裂纹产生时,即使其中一条裂痕达到基础表面也会产生破坏。另外,本申请人根据十几个模型实验和数值解析得到了如下见解:利用钢管对与割裂裂纹垂直的方向即主桩柱的周方向进行加强,提高混凝土的约束,抑制割裂破坏,可以极大地提高固定耐力。In the past, the design of the fixing part of the main pile of the iron tower was strengthened by the fixing endurance based on the allowable tensile stress and the allowable shear stress of the concrete. , perform reinforcement according to empirical rules, and thus sometimes overreinforce. In view of the above situation, the present applicant has intensively discussed effective foundation design and reinforcement, and as a result, as disclosed in JP-A-2000-345571, when continuous stress acts on the main pile, horizontal stresses are generated on the concrete. Cracks or vertical cracks (slit cracks). Furthermore, it was found that, in the case of the support fixing method, the above-mentioned split cracks are greatly affected, and when the split cracks are generated, even if one of the cracks reaches the surface of the foundation, damage occurs. In addition, the applicant obtained the following insights based on more than a dozen model experiments and numerical analysis: using steel pipes to strengthen the direction perpendicular to the split crack, that is, the circumferential direction of the main pile, can improve the restraint of concrete and suppress split damage, which can greatly improve the Improves stationary stamina.

因此,如果能尽量抑制割裂裂纹,出于可以提高固定耐力、缩小接合部(基础部分)的考虑,作为上述构造的混凝土结构体,是在其下部侧接合打入上述地基中的多根桩体的顶部,且在上述铁塔主桩柱的下部设有固定部件,设有上述固定部件的主桩柱部分埋设在上述混凝土结构体中的基础结构。Therefore, if splitting cracks can be suppressed as much as possible, in order to improve the fixing resistance and reduce the joint part (foundation part), as the concrete structure of the above structure, a plurality of piles driven into the above foundation are joined at the lower side. The top of the tower, and the lower part of the main pile of the iron tower is provided with a fixed part, and the main pile with the fixed part is partially embedded in the foundation structure of the concrete structure.

其结果是,钢管从外部(周围)约束浇筑的混凝土,可以防止割裂裂纹,大幅度提高混凝土结构体的固定耐力,并且,桩体能够靠近配置在钢管内的内壁面附近,因此能够大幅度减小混凝土结构体的规模。并且,通过减小混凝土结构体的规模,能够缩短施工时间、降低挖掘量、减少混凝土的浇筑量等。As a result, the steel pipe constrains the poured concrete from the outside (surroundings), prevents splitting cracks, and greatly improves the fixation resistance of the concrete structure. In addition, the pile body can be placed close to the inner wall surface of the steel pipe, so it can be greatly reduced. The scale of small concrete structures. Furthermore, by reducing the scale of the concrete structure, it is possible to shorten the construction time, reduce the amount of excavation, reduce the amount of pouring concrete, and the like.

并且,通过形成由上述钢管和混凝土构成混凝土结构体,能够容易地设置多根桩体,并且容易吸收主桩和副桩的施工误差。Furthermore, by forming the concrete structure made of the above-mentioned steel pipes and concrete, it is possible to easily install a plurality of pile bodies, and it is easy to absorb construction errors of the main pile and the auxiliary pile.

作为技术方案2的本发明,提供一种根据技术方案1所述的铁塔的基础构造,上述多根桩体是口径为400φmm以下或者口径为上述钢管直径的1/6以下的小口径桩。作为桩体,希望设置多根、优选4~6根与大口径桩体相比口径为400φmm以下或者口径为上述钢管直径的1/6以下的小口径桩。特别在山岳地带,由于无法进入大型重机械,因而优选利用小型挖孔机械在地基内设置需要根数的小口径桩。作为小口径桩,详细如后文所述,可以是就地灌注桩或钢管桩等。The present invention as claim 2 provides a foundation structure of an iron tower according to claim 1, wherein the plurality of piles are small-diameter piles with a diameter of 400φmm or less or 1/6 or less of the steel pipe diameter. As the pile body, it is desirable to install a plurality of, preferably 4 to 6, small-diameter piles with a diameter of 400mm or less compared with the large-diameter pile body, or with a diameter of 1/6 or less of the above-mentioned steel pipe diameter. Especially in mountainous areas, since large heavy machinery cannot be used, it is preferable to install the required number of small-diameter piles in the foundation using a small-sized hole-digging machine. The small-diameter piles may be in-situ cast-in-place piles or steel pipe piles, as will be described later in detail.

作为技术方案3的本发明,提供一种根据技术方案1或2所述的铁塔的基础构造,上述抗剪凸缘以上述铁塔主桩柱的支承板配置部位为边界,分别设在其上部侧和下部侧。The present invention according to claim 3 provides the steel tower foundation structure according to claim 1 or 2, wherein the shear flanges are respectively provided on the upper side of the steel tower main pile with the supporting plate arrangement part as a boundary. and lower side.

在上述技术方案3所述的本发明中,上述抗剪凸缘以上述铁塔主桩柱的埋设部的支承板配置部位为边界,分别设在其上部侧和下部侧。作用于混凝土结构体的来自主桩柱的负荷有时会因为风负荷或地震负荷的方向而包含压入力和拉拔力二者,因此对于该负荷二者,为了使上述抗剪凸缘有效起作用,优选以支承板配置部位为边界,分别设在其上部侧和下部侧。In the present invention described in claim 3 above, the shear flanges are respectively provided on the upper side and the lower side of the support plate arrangement portion of the embedded portion of the tower main pile as a boundary. The load from the main pile acting on the concrete structure sometimes includes both the indentation force and the pull-out force due to the direction of the wind load or earthquake load, so for both of the loads, in order for the above-mentioned shear flange to function effectively , are preferably provided on the upper side and the lower side of the support plate arrangement portion as a boundary, respectively.

技术方案4涉及的本发明提供一种根据技术方案1至3中任一项所述的铁塔的基础构造,上述混凝土结构体的大部分埋设在地基中。The present invention according to Claim 4 provides the foundation structure of the iron tower according to any one of Claims 1 to 3, wherein most of the concrete structure is buried in a foundation.

上述混凝土结构体也可以以放置在地上的方式进行筑造,但为了抑制基础的位移等,优选与基脚同样地埋设在地下,在能够通过土压阻力抑制位移的状态下进行筑造。The above-mentioned concrete structure can also be built by placing it on the ground, but in order to suppress the displacement of the foundation, it is preferable to bury it underground like the footing, and build it in a state where the displacement can be suppressed by the earth pressure resistance.

技术方案5涉及的本发明提供一种根据技术方案1至4中任一项所述的铁塔的基础构造,设上述铁塔主桩柱的直径为φ,上述铁塔主桩柱的支承板的配置区间长度为L,上述钢管的内径为D时,满足如下条件:L/φ=2~5,且D/φ=2~10。The present invention related to technical scheme 5 provides a kind of basic structure according to any one of technical scheme 1 to 4 iron tower, suppose the diameter of above-mentioned iron tower main pile column is φ, the configuration interval of the supporting plate of above-mentioned iron tower main pile column When the length is L and the inner diameter of the steel pipe is D, the following conditions are satisfied: L/φ=2-5, and D/φ=2-10.

技术方案6涉及的本发明提供一种根据技术方案1至5中任一项所述的铁塔的基础构造,具有从上述混凝土结构体的钢管周壁部朝斜下方向打入的坡桩。The present invention according to claim 6 provides the foundation structure of an iron tower according to any one of claims 1 to 5, including slope piles driven obliquely downward from the steel pipe peripheral wall portion of the concrete structure.

在上述技术方案6涉及的本发明中,具有从上述混凝土结构体的钢管周壁部朝斜下方向打入的坡桩。通过设置坡桩,尤其能够大幅度提高拉拔耐力。In the present invention according to Claim 6 above, slope piles are provided which are driven obliquely downward from the steel pipe peripheral wall portion of the concrete structure. In particular, by providing slope piles, the pull-out endurance can be significantly improved.

技术方案7涉及的本发明提供一种根据技术方案1至5中任一项所述的铁塔的基础构造,具有连接上述相邻铁塔主桩柱的混凝土结构体之间的连接梁。The present invention related to technical solution 7 provides a foundation structure of an iron tower according to any one of technical solutions 1 to 5, which has a connecting beam connecting the concrete structures of the main piles of adjacent iron towers.

在上述技术方案7涉及的本发明中,设有结合相邻铁塔主桩柱的混凝土结构体之间的连接梁。通过利用连接梁连接混凝土结构体,能够大幅度抑制基础的位移。In the present invention according to the above-mentioned technical solution 7, there is provided a connecting beam between the concrete structures connecting the main piles of adjacent iron towers. By connecting the concrete structure with the connecting beam, the displacement of the foundation can be significantly suppressed.

在技术方案8涉及的本发明中,提供一种根据技术方案1至5中任一项所述的铁塔的基础构造,上述铁塔主桩柱的根数为2~4根。替代较大的钢管柱,可以用于具有2至4根桁架结构的支柱的上部构造,在小规模的铁塔的情况下,可以在一个上述钢管中固定全部4根主桩柱。In the present invention according to Claim 8, there is provided the foundation structure of an iron tower according to any one of Claims 1 to 5, wherein the number of main piles of the iron tower is 2 to 4. Instead of larger steel tube columns, superstructures with 2 to 4 truss-structured columns can be used, and in the case of small-scale iron towers, all 4 main columns can be fixed in one said steel tube.

发明效果Invention effect

如上所详述,根据本发明,在将口径相对较小的多根桩体设置在地基中的基础构造形式中,作为混凝土结构体,采用将混凝土浇筑入在内壁面沿上下方向具有多段沿圆周方向固定设置的抗剪凸缘的钢管内而制成的结构体,因此能够极大地提高固定耐力,使基础部分小规模化。其结果,能够缩短施工时间,降低挖掘量、减少混凝土浇筑量等。As described in detail above, according to the present invention, in the form of foundation structure in which a plurality of piles with relatively small diameters are installed in the foundation, as a concrete structure, concrete is poured into the inner wall surface and has a plurality of sections along the circumference along the upper and lower directions. The structure is made in the steel pipe with the shear flange fixed in the direction, so the fixing resistance can be greatly improved, and the base part can be reduced in size. As a result, the construction time can be shortened, the amount of excavation can be reduced, the amount of concrete pouring can be reduced, and the like.

附图说明 Description of drawings

图1表示第一实施例的铁塔的基础构造,(A)是纵向截面图,(B)是横向截面图。Fig. 1 shows the basic structure of the steel tower of the first embodiment, (A) is a longitudinal sectional view, (B) is a transverse sectional view.

图2表示第二实施例的铁塔的基础构造,(A)是纵向截面图,(B)是右侧视图,(C)是横向截面图。Fig. 2 shows the basic structure of the iron tower of the second embodiment, (A) is a longitudinal sectional view, (B) is a right side view, and (C) is a transverse sectional view.

图3是表示表示第三实施例的铁塔的基础构造的纵向截面图。Fig. 3 is a longitudinal sectional view showing a basic structure of a steel tower according to a third embodiment.

图4是表示主桩柱2的变形例的纵向截面图。FIG. 4 is a longitudinal sectional view showing a modified example of the main pile 2 .

图5是抗剪凸缘4的方式例的图(A)~(C)。FIG. 5 is diagrams (A) to (C) of form examples of the shear flange 4 .

图6表示现有的铁塔的基础构造,(A)是纵向截面图,(B)是横向截面图。Fig. 6 shows the basic structure of a conventional iron tower, (A) is a longitudinal sectional view, and (B) is a transverse sectional view.

图7是表示主桩柱52的锚部件固定方式,(A)是基脚纵向截面图,(B)是锚部件的俯视图,(C)是锚部件的侧视图。Fig. 7 shows the anchor member fixing method of the main pile 52, (A) is a longitudinal sectional view of the footing, (B) is a top view of the anchor member, and (C) is a side view of the anchor member.

图8表示主桩柱52的支承板固定方式,(A)是纵向截面图,(B)是横向截面图。Fig. 8 shows the supporting plate fixing method of the main pile 52, (A) is a longitudinal sectional view, and (B) is a transverse sectional view.

图9(A)是表示桩体50的支承板固定方式的图,(B)是表示钢筋固定方式的图。Fig.9 (A) is a figure which shows the support plate fixing form of the pile body 50, (B) is a figure which shows the reinforcing bar fixing form.

图10是表示现有例中简易的铁塔的基础结构的侧视图。Fig. 10 is a side view showing a basic structure of a simple iron tower in a conventional example.

图11是风负荷对铁塔基础产生的外力作用的状态图。Fig. 11 is a state diagram of the external force generated by the wind load on the iron tower foundation.

图12是表示基脚的破坏方式(其一)的图。Fig. 12 is a diagram showing a destruction method (Part 1) of the footing.

图13是表示基脚的破坏方式(其二)的图。Fig. 13 is a diagram showing a destruction method (Part 2) of the footing.

标号说明Label description

1桩体1 pile

2主桩柱2 main piles

3混凝土结构体3 concrete structures

4、4a~4c抗剪凸缘4. 4a~4c shear flange

5钢管5 steel pipes

6混凝土6 concrete

7支承板7 support plate

8、11固定筋8, 11 fixed rib

10坡桩10 slope piles

12连接梁12 connection beam

具体实施方式 Detailed ways

以下参照附图对本发明的实施方式进行详细说明。Embodiments of the present invention will be described in detail below with reference to the drawings.

[第一实施例][first embodiment]

如图1所示,本发明的铁塔基础构造,将打入地基中的多根桩体1、1…与铁塔的主桩柱2通过混凝土结构体3接合时,作为上述混凝土结构体3,采用向在内壁面沿上下方向具有多段沿着周方向固定设置的抗剪凸缘4、4…的钢管5内浇筑入混凝土6而制成的结构体,在上述混凝土结构体3的下部侧接合打入上述地基中的多根桩体1、1…的顶部,并且,在上述铁塔主桩柱2的下部外面上设有多段支承板7、7…,设有上述支承板7、7…的主桩柱部分K埋设在上述混凝土结构体3中。As shown in Fig. 1, the iron tower foundation structure of the present invention, when the many pile bodies 1, 1 ... that are driven into the foundation and the main pile column 2 of the iron tower are joined by the concrete structure body 3, as the above-mentioned concrete structure body 3, adopt A structure made by pouring concrete 6 into a steel pipe 5 having a plurality of shear flanges 4, 4 ... fixedly arranged along the circumferential direction on the inner wall surface in the vertical direction, and the lower part of the concrete structure 3 is jointed and drilled. Into the top of the multiple piles 1, 1... in the above foundation, and, on the outer surface of the lower part of the main pile column 2 of the above-mentioned iron tower, multi-section support plates 7, 7... are provided, and the main parts of the above-mentioned support plates 7, 7... are provided. The pile part K is embedded in the concrete structure 3 mentioned above.

在下文中进行更具体的叙述。More specific descriptions are given below.

作为上述混凝土结构体3,优选使用例如直径为1000~5000mm左右,厚度约为20~30mm左右的厚壁钢管。作为固定设置在内壁面上的抗剪凸缘4、4…,只要是能够在与浇筑的混凝土6间切实地防滑的突起形状,就可以是任意截面形状。例如,如图5(A)所示,可以通过焊接沿着钢管5的内壁面固定设置钢筋/钢棒4a,也可以如图5(B)所示,利用角钢4b,或者图5(C)所示,利用扁钢4c等。As the concrete structure 3, for example, a thick-walled steel pipe having a diameter of about 1000 to 5000 mm and a thickness of about 20 to 30 mm is preferably used. The shear flanges 4, 4..., which are fixedly arranged on the inner wall surface, may have any cross-sectional shape as long as they are in the shape of protrusions that can reliably prevent slipping between the poured concrete 6. For example, as shown in Figure 5(A), the steel bar/steel bar 4a can be fixedly installed along the inner wall of the steel pipe 5 by welding, or as shown in Figure 5(B), using angle steel 4b, or as shown in Figure 5(C) Shown, utilize flat steel 4c etc.

另外,在图示的例子中,作为上述钢管5使用钢制的圆形管,也可以使用角管或多角管等钢制管。并且,上述混凝土结构体3可以以放置在地上的方式筑造,但为了利用土压阻力降低位移量,优选以大部分埋设在地基中的状态进行筑造。In addition, in the illustrated example, a steel circular pipe is used as the above-mentioned steel pipe 5 , but steel pipes such as angular pipes and polygonal pipes may be used. In addition, the above-mentioned concrete structure 3 may be constructed by placing it on the ground, but it is preferable to construct it with most of it buried in the foundation in order to reduce displacement by earth pressure resistance.

如上所述,在上述主桩柱2上由于风负荷等的方向,作用有压入力或拉拔力二者,因此为了能够应对压入力和拉拔力二者,上述抗剪凸缘4优选以上述铁塔主桩柱2的支承板配置部位K为边界,分别设置在其上部侧和下部侧。实际上优选在上述钢管5的上下方向上以大致均等的间隔配置。As described above, since both the pressing force and the pulling force act on the main pile 2 due to the direction of the wind load, etc., in order to be able to cope with both the pressing force and the pulling force, the above-mentioned shear flange 4 is preferably The above-mentioned supporting plate arrangement part K of the iron tower main pile 2 is a boundary, and is respectively arranged on the upper side and the lower side thereof. Actually, it is preferable to arrange the steel pipes 5 at substantially equal intervals in the vertical direction.

上述主桩柱2在其下部外面设有多段、在图示例中为3段的支承板7、7…,以该支承板配置部位K位于上述混凝土结构体3的大致中央的方式埋设在混凝土结构体3中。上述主桩柱2的截面尺寸没有特别限定,但大致为300~3000mm左右。作为上述支承板7,采用将环状板通过焊接等固定设置在上述主桩柱2周围的结构,但支承板7的平面形状也可以是多角形状等。并且,在本实施例中,作为上述主桩柱2的固定方式采用了支承板方式,但也可以采用图7所示的锚部件固定方式。The above-mentioned main pile 2 is provided with a plurality of stages, three stages of support plates 7, 7... in the illustrated example, and is embedded in the concrete structure so that the support plate arrangement position K is located in the approximate center of the above-mentioned concrete structure 3. Body 3. Although the cross-sectional dimension of the main pile 2 is not particularly limited, it is approximately 300 to 3000 mm. As the support plate 7, a ring-shaped plate is fixedly installed around the main pile 2 by welding or the like, but the planar shape of the support plate 7 may be a polygonal shape or the like. In addition, in the present embodiment, the support plate method is adopted as the fixing method of the above-mentioned main pile 2, but the anchor member fixing method shown in FIG. 7 may also be used.

并且,在图示例中,作为铁塔主桩柱2表示了钢管柱的例子,但是作为主桩柱2,例如也可以是三角钢,并且,也可以如图4所示,使主桩柱2的数量为2至4根,将利用多个斜杆2a、2a…连接而成的组合柱2’等作为对象。And, in the illustrated example, the example of the steel pipe column has been shown as the main pile 2 of the iron tower, but as the main pile 2, for example, also can be triangular steel, and, also can make the main pile 2 as shown in Figure 4 The number is 2 to 4, and the combined columns 2' and the like connected by a plurality of diagonal rods 2a, 2a... are targeted.

作为上述桩体1,不拘桩体种类,可以是钢管桩、就地灌注桩、或预制桩等中的任一种。上述桩体1的直径希望为能够在上述钢管5内至少均匀配置2根以上、优选可以均匀配置4~6根左右的直径,但从施工性的角度来说,希望是口径为400φmm以下或者口径为上述钢管5直径的1/6以下的小口径桩。上述小口径桩的施工可以如下进行:例如可以通过挖孔在地基中进行穿孔后,在该穿孔内插入钢管或预制桩,在周围填充水泥浆或混凝土、高流动性混凝土等固化材料进行固定,也可以在穿孔内插入架立筋,通过填充混凝土或高流动性混凝土,制成就地灌注桩。上述地基的穿孔在地基较弱时可以使用旋转式等,在岩盘或中间存在岩盘层的地基的情况下,优选使用旋转打击式的ダウンザホ一ルハンマ一(商标名,入孔冲击锤)等。The pile body 1 may be any of steel pipe piles, cast-in-place piles, and prefabricated piles, regardless of the type of the pile body. The diameter of the above-mentioned pile body 1 is desirably such that at least two or more, preferably about 4 to 6, can be evenly arranged in the above-mentioned steel pipe 5. It is a small-diameter pile below 1/6 of the above-mentioned steel pipe 5 diameter. The construction of the above-mentioned small-diameter piles can be carried out as follows: For example, after drilling holes in the foundation, insert steel pipes or prefabricated piles into the holes, fill the surrounding with solidified materials such as cement slurry or concrete, and high-fluidity concrete. It is also possible to insert vertical bars into the perforated holes and fill them with concrete or high-fluidity concrete to make cast-in-place piles. The perforation of the above-mentioned foundation can use a rotary type when the foundation is weak, and in the case of a foundation with a rock disk or a rock disk layer in the middle, it is preferable to use a rotary hammer type Dawnza Hole Hammer (trade name, hole impact hammer), etc. .

上述桩体1和混凝土结构体3的接合在图示例中采用配置跨过二者间的固定钢筋8、8…的钢筋固定方式,但在使用钢管桩的情况下,也可以采用通过在插入混凝土结构体3内的桩顶部外面向外方突出设置的环状等的支承板进行固定的支承板接合方式。The above-mentioned pile body 1 and the concrete structure 3 are joined together in the example shown in the figure by arranging the fixing steel bars 8, 8... which straddle the two, but in the case of using steel pipe piles, it is also possible to adopt A supporting plate joining method in which the outer surface of the top of the pile in the concrete structure 3 is fixed by a ring-shaped supporting plate protruding outward.

以上详细说明的基础构造的施工如下进行。首先,在混凝土结构体3的施工部进行地基挖掘,设置钢管5,接着进行用于桩体1、1…的穿孔,将桩体1、1…打入地基中。其后,设置固定筋8、8…,并将主桩柱2的基部定位在钢管5内的预定位置上,利用临时固定部件(未图示)实现固定,并且,将预定的钢筋布置在钢管5内,在钢筋布置作业全部结束后,浇筑混凝土。The construction of the foundation structure detailed above is carried out as follows. First, foundation excavation is performed in the construction part of the concrete structure 3, steel pipes 5 are installed, and then piercing for the pile bodies 1, 1... is performed, and the pile bodies 1, 1... are driven into the foundation. Thereafter, the fixing ribs 8, 8... are set, and the base of the main pile 2 is positioned at a predetermined position in the steel pipe 5, fixed by a temporary fixing member (not shown), and the predetermined steel bars are arranged on the steel pipe Within 5, after all the reinforcement layout operations are completed, the concrete is poured.

[第二实施例][Second embodiment]

其次,图2所示第二实施例的基础结构,设置从上述混凝土结构体3的钢管5的周壁部向斜下方打入的坡桩10。通过相对混凝土结构体3一体设置坡桩10,当然会提高压入力,但也可以进一步大幅度提高拉拔耐力。另外,上述坡桩10在图示例中仅有1根,也可以设置多根。Next, the foundation structure of the second embodiment shown in FIG. 2 is provided with slope piles 10 driven obliquely downward from the peripheral wall portion of the steel pipe 5 of the concrete structure 3 . By providing the slope piles 10 integrally with the concrete structure 3, the press-fitting force is of course increased, but the pull-out resistance can also be further significantly improved. In addition, the above-mentioned slope pile 10 is only one in the illustrated example, and a plurality of them may be provided.

施工首先在混凝土结构体3的施工部进行地基挖掘,从挖掘部的壁面进行穿孔,打入坡桩10后,设置钢管5。在钢管5的壁面上为了实现与上述坡桩10的一体化预先形成有固定筋11的插入口5a。In the construction, the foundation excavation is first carried out in the construction part of the concrete structure 3, the wall surface of the excavation part is drilled, the slope pile 10 is driven in, and the steel pipe 5 is installed. In order to realize the integration with the above-mentioned slope pile 10, the insertion opening 5a of the fixing rib 11 is formed in advance in the wall surface of the steel pipe 5.

接着,进行用于桩体1、1…的穿孔,将桩体1、1…设置在地基中。其后,设置固定筋8、8…,并将主桩柱2的基部定位在钢管5内的预定位置上,利用临时固定部件(未图示)进行固定,并且,将预定的钢筋布置在钢管5内,且从钢管5的插入口5a插入固定筋11,在钢筋布置作业全部结束后,浇筑混凝土。Next, perforation for the pile bodies 1, 1... is performed, and the pile bodies 1, 1... are set in the foundation. Thereafter, fixing ribs 8, 8... are provided, and the base of the main pile 2 is positioned at a predetermined position inside the steel pipe 5, fixed by a temporary fixing member (not shown), and predetermined reinforcing bars are arranged on the steel pipe 5. 5, and insert the fixing bar 11 from the insertion port 5a of the steel pipe 5, and pour concrete after all the reinforcing bar layout operations are completed.

并且,在上述钢管5的插入口5a外侧部分也浇筑入混凝土,固定坡桩10的顶部,实现与混凝土结构体3的一体化。In addition, concrete is also poured into the outer portion of the insertion port 5a of the steel pipe 5, and the top of the slope pile 10 is fixed to realize integration with the concrete structure 3.

[第三实施例][Third embodiment]

其次,图3所示的第三实施例的基础构造,设有结合相邻铁塔主桩柱2的混凝土结构体3、3之间的连接梁12。混凝土结构体3、3通过连接梁12相互连接,由此大幅度抑制基础的位移。Secondly, the foundation structure of the third embodiment shown in FIG. 3 is provided with a connecting beam 12 between the concrete structures 3 and 3 of the main piles 2 of adjacent iron towers. The concrete structures 3, 3 are connected to each other by connecting beams 12, whereby the displacement of the foundation is largely suppressed.

施工首先在混凝土结构体3的施工部进行地基挖掘,从挖掘部的壁面进行水平穿孔,形成用于设置连接梁12的通孔,或者在较浅的情况下,通过开放挖掘而在连接梁的设置部分上形成槽,设置连接梁12后设置钢管5。另外,在钢管5的壁面上为了实现与上述连接梁12的一体化而预先形成有固定筋11的插入口5a。The construction first excavates the foundation in the construction part of the concrete structure body 3, and horizontally perforates from the wall surface of the excavated part to form a through hole for setting the connecting beam 12, or in the shallow case, excavate the connecting beam through open excavation. Grooves are formed on the installation part, and the steel pipe 5 is installed after the connection beam 12 is installed. In addition, an insertion opening 5a for the fixing rib 11 is formed in advance on the wall surface of the steel pipe 5 in order to integrate with the above-mentioned connecting beam 12 .

接着,进行用于桩体1、1…的穿孔,将桩体1、1…设置在地基中。其后,设置固定筋8、8…,并将主桩柱2的基部定位在钢管5内的预定位置上,利用临时固定部件(未图示)进行固定,并且,将预定的钢筋布置在钢管5内,且从钢管5的插入口5a插入固定筋11,在钢筋布置作业全部结束后,浇筑混凝土。Next, perforation for the pile bodies 1, 1... is performed, and the pile bodies 1, 1... are set in the foundation. Thereafter, fixing ribs 8, 8... are provided, and the base of the main pile 2 is positioned at a predetermined position inside the steel pipe 5, fixed by a temporary fixing member (not shown), and predetermined reinforcing bars are arranged on the steel pipe 5. 5, and insert the fixing bar 11 from the insertion port 5a of the steel pipe 5, and pour concrete after all the reinforcing bar layout operations are completed.

并且,在上述钢管5的插入口5a外侧部分也浇筑混凝土,固定连接梁12的端部,实现与混凝土结构体3的一体化。In addition, concrete is also poured on the outer portion of the insertion port 5a of the steel pipe 5 to fix the ends of the connecting beams 12 and integrate with the concrete structure 3 .

[本固定方式的固定耐力的设计][the design of the fixation durability of this fixation method]

其次,对本发明的铁塔基础的设计方法进行说明。Next, the design method of the steel tower foundation of the present invention will be described.

该设计方法将防止了割裂破坏之上的破坏形态(钢管5的屈服耐力、支承板周围的混凝土的附着耐力、抗剪凸缘4的耐力)作为极限耐力,做出合理的设计。In this design method, the failure mode (yield resistance of the steel pipe 5, adhesion resistance of the concrete around the support plate, and resistance of the shear flange 4) beyond the prevention of split failure is taken as the ultimate resistance, and a reasonable design is made.

本接合方式的固定耐力的设计可以考虑以下事项,并根据以下所示的式子进行设计。The design of the fixing strength of this joining method can be carried out in consideration of the following matters, and can be designed according to the formula shown below.

(1)约束混凝土的上述钢管5的屈服耐力fpipe(应力)由下式(1)决定。(1) The yield strength f pipe (stress) of the above-mentioned steel pipe 5 constraining concrete is determined by the following equation (1).

【式1】【Formula 1】

ff pipethe pipe == PP ·&Center Dot; tanthe tan θθ 22 ·· ππ ·&Center Dot; tt ·&Center Dot; ll 11 ≤≤ ff pipethe pipe __ aa γγ 11 ·&Center Dot; γγ ee ·&Center Dot; ·&Center Dot; ·· ·&Center Dot; ·&Center Dot; ·· (( 11 ))

fpipe_a:约束的钢管的容许拉伸应力f pipe_a : allowable tensile stress of the restrained steel pipe

P:设计垂直负荷P: design vertical load

t:约束的钢管壁厚t: Constrained steel pipe wall thickness

l1:固定长度(支承板最上段与最下段的间隔)l 1 : fixed length (the interval between the uppermost section and the lowermost section of the support plate)

θ:从支承板传达到混凝土的支承力的方向θ: The direction of the supporting force transmitted from the supporting plate to the concrete

γ1:与抗剪的施工条件相关的钢管的强度降低系数γ 1 : The strength reduction factor of steel pipes related to the construction conditions of shear resistance

γe:与桩体的施工误差所导致的偏芯相关的系数γ e : The coefficient related to the eccentricity caused by the construction error of the pile body

(2)支承板7周围的混凝土附着耐力τb(应力)由下式(2)决定。(2) The concrete adhesion resistance τ b (stress) around the support plate 7 is determined by the following formula (2).

【式2】[Formula 2]

ττ bb == PP Uu SS ·&Center Dot; ll 11 ≤≤ ττ bathe b ·· ·· ·&Center Dot; ·&Center Dot; ·· ·· (( 22 ))

P:设计垂直负荷P: design vertical load

US:支承板周围的附着剪切周长U S : Attached shear perimeter around the support plate

l1:固定长度(支承板最上段与最下段的间隔)l 1 : fixed length (the interval between the uppermost section and the lowermost section of the support plate)

τba:钢管所约束的混凝土的容许附着应力τ ba : Allowable adhesion stress of concrete confined by steel pipes

(3)为了讨论上述抗剪凸缘4的耐力,抗剪凸缘4的焊接部的剪切应力τsh由下式(3)决定。(3) In order to discuss the resistance of the above-mentioned shear flange 4, the shear stress τ sh of the welded part of the shear flange 4 is determined by the following formula (3).

【式3】[Formula 3]

ττ shsh == PP nno ribribs ·&Center Dot; ww ·&Center Dot; ππ ·&Center Dot; (( DD. -- 22 tt )) ≤≤ ττ shathe sha γγ 22 ·&Center Dot; κκ ·&Center Dot; ·&Center Dot; ·&Center Dot; ·&Center Dot; ·&Center Dot; ·&Center Dot; (( 33 ))

P:设计垂直负荷P: design vertical load

τsha:焊接部的容许剪切应力τ sha : Allowable shear stress of the weld

nrib:抗剪的根数n rib : the number of shear-resistant roots

w:焊接部的焊脚长w: Weld leg length of welding part

D:约束的钢管的外径D: Outer diameter of the steel pipe constrained

t:约束的钢管的壁厚t: wall thickness of the steel tube to be restrained

γ2:抗剪的施工条件下的焊接部的强度降低系数γ 2 : The strength reduction factor of the weld under the construction condition of shear resistance

κ:考虑抗剪的应力偏差的系数κ: Coefficient of stress deviation considering shear resistance

(4)与上述抗剪凸缘4接触的混凝土的支承应力σc由下式(4)决定。(4) The supporting stress σ c of the concrete in contact with the shear flange 4 is determined by the following formula (4).

【式4】[Formula 4]

σσ cc == PP nno ribribs ·· ππ ·&Center Dot; (( DD. -- 22 tt -- dd ribribs )) ·· dd ribribs ≤≤ αα ·&Center Dot; σσ caca κκ ·&Center Dot; ·&Center Dot; ·&Center Dot; ·&Center Dot; ·&Center Dot; ·&Center Dot; (( 44 ))

P:设计垂直负荷P: design vertical load

σca:混凝土的容许支承应力σ ca : allowable bearing stress of concrete

nrib:抗剪的根数n rib : the number of shear-resistant roots

D:约束的钢管的外径D: Outer diameter of the steel pipe constrained

t:约束的钢管的壁厚t: wall thickness of the steel pipe to be restrained

drib:抗剪的宽度d rib : the width of the shear resistance

α:双轴约束的混凝土的容许支承应力的附加系数α: additional factor for allowable bearing stress of biaxially restrained concrete

κ:考虑抗剪的应力偏差的系数κ: Coefficient of stress deviation considering shear resistance

(5)与上述抗剪凸缘4的内周接触的混凝土的剪切应力τrib_c由下式(5)决定。(5) The shear stress τ rib_c of the concrete in contact with the inner periphery of the shear flange 4 is determined by the following formula (5).

【式5】[Formula 5]

ττ ribribs __ cc == PP ππ ·&Center Dot; (( DD. -- 22 tt -- 22 dd ribribs )) ·&Center Dot; ll ribribs ≤≤ ττ bathe b ·&Center Dot; ·&Center Dot; ·&Center Dot; ·&Center Dot; ·&Center Dot; ·&Center Dot; (( 55 ))

P:设计垂直负荷P: design vertical load

τba:由钢管约束的混凝土的允许附着应力τ ba : Allowable adhesion stress of concrete bounded by steel pipes

D:约束的钢管的外径D: Outer diameter of the steel pipe constrained

t:约束的钢管的壁厚t: wall thickness of the steel pipe to be restrained

drib:抗剪的宽度d rib : the width of the shear resistance

lrib:抗剪的设置宽度l rib : set width of shear resistance

Claims (7)

1. the base configuration of an iron tower, the many piles body that will squeeze in the ground by concrete body engages with the king pile post of iron tower, it is characterized in that,
Described concrete body is that concreting is gone in internal face has the steel pipe of the shearing resistance flange that multistage along the circumferential direction fixedly installs along the vertical direction and the structure of making, lower side at described concrete body engages the top of squeezing into the many piles body in the described ground, and the bottom at described iron tower king pile post is provided with fixed part, the king pile post that is provided with described fixed part partly is embedded in the described concrete body
If the diameter of described iron tower king pile post is φ, the configuration siding-to-siding block length of the base plate of described iron tower king pile post is L, when the internal diameter of described steel pipe is D, satisfies following condition: L/ φ=2~5, and D/ φ=2~10.
2. the base configuration of iron tower according to claim 1 is characterized in that,
Described many piles body is that bore is below the 400 φ mm or bore is the small-bore stake below 1/6 of described diameter of steel tube.
3. the base configuration of iron tower according to claim 1 and 2 is characterized in that,
Described shearing resistance flange is the border with the base plate configuration position of described iron tower king pile post, is located at its upper side and lower side respectively.
4. the base configuration of iron tower according to claim 1 and 2 is characterized in that,
The major part of described concrete body is embedded in the ground.
5. the base configuration of iron tower according to claim 1 and 2 is characterized in that,
Has the slope stake of squeezing into towards oblique direction down from the steel pipe surrounding wall portion of described concrete body.
6. the base configuration of iron tower according to claim 1 and 2 is characterized in that,
Have in conjunction with the tie-beam between the concrete body of described adjacent iron tower king pile post.
7. the base configuration of iron tower according to claim 1 and 2 is characterized in that,
The radical of described iron tower king pile post is 2 to 4.
CNB200580029551XA 2004-09-17 2005-09-16 The basic structure of the tower Expired - Fee Related CN100567659C (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP271161/2004 2004-09-17
JP2004271161A JP3754698B1 (en) 2004-09-17 2004-09-17 Steel tower basic structure

Publications (2)

Publication Number Publication Date
CN101010465A CN101010465A (en) 2007-08-01
CN100567659C true CN100567659C (en) 2009-12-09

Family

ID=36060140

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB200580029551XA Expired - Fee Related CN100567659C (en) 2004-09-17 2005-09-16 The basic structure of the tower

Country Status (3)

Country Link
JP (1) JP3754698B1 (en)
CN (1) CN100567659C (en)
WO (1) WO2006030893A1 (en)

Families Citing this family (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4783746B2 (en) * 2007-01-29 2011-09-28 公益財団法人鉄道総合技術研究所 Joint structure of slant pile and foundation
CN101871217B (en) * 2009-04-23 2013-12-18 润弘精密工程事业股份有限公司 Pre-cast pile cap structure and its joining method
CN102713077B (en) * 2010-01-19 2015-04-01 新日铁住金株式会社 Steel pipe pile
JP5563512B2 (en) * 2011-04-12 2014-07-30 レンドリース・ジャパン株式会社 Columnar structure and installation method of columnar structure
CN103174162A (en) * 2011-12-21 2013-06-26 上海市电力公司 Composite pile structure for iron tower of electric transmission line
CN102767189B (en) * 2012-07-31 2014-06-25 中铁第五勘察设计院集团有限公司 Set bearing platform foundations and construction method thereof
CN104790423B (en) * 2015-03-12 2017-03-01 中国能源建设集团浙江省电力设计院有限公司 A kind of large-scale transmission tower is combined and expands top bored concrete pile foundation
JP2017197984A (en) * 2016-04-28 2017-11-02 清水建設株式会社 Joint structure of PHC pile and steel column
CN106049521A (en) * 2016-06-23 2016-10-26 中国电力工程顾问集团中南电力设计院有限公司 Cross cantilever beam single-column self-balance foundation of power transmission line and construction method thereof
CN106381881B (en) * 2016-09-14 2018-06-22 中国海洋大学 A kind of gravity type single-pile foundation
CN106223356B (en) * 2016-09-21 2018-11-06 成都九十度工业产品设计有限公司 A kind of swelling column foot of Fast Installation
CN106968159A (en) * 2017-04-01 2017-07-21 徐冲 A kind of bridge structure of town airbus
JP7263671B2 (en) * 2018-08-09 2023-04-25 株式会社竹中工務店 pile foundation structure
JP7449880B2 (en) * 2021-01-18 2024-03-14 大成建設株式会社 Steel pipe column base structure
CN113914701A (en) * 2021-11-01 2022-01-11 峻江建设有限公司 Anti-toppling iron tower capable of being applied to soft soil
CN115419103A (en) * 2022-10-19 2022-12-02 四川省送变电建设有限责任公司 Power transmission line engineering foundation structure and construction method thereof
CN115680008A (en) * 2022-10-29 2023-02-03 广东宏茂建设管理有限公司 Construction method of concrete high pile cap for large-scale tower crane equipment

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5498009A (en) * 1978-01-19 1979-08-02 Kubota Ltd Method of building foundation for pylon on mountain
JP2000355938A (en) * 1999-06-17 2000-12-26 Nippon Steel Corp Connection structure between pile head and column and pull-out resistance structure between pile head and footing
JP4576067B2 (en) * 2001-04-13 2010-11-04 新日本製鐵株式会社 Joint structure of pile head and steel underground beam
JP2003082689A (en) * 2001-09-11 2003-03-19 Chubu Electric Power Co Inc Steel pipe pile foundation construction method

Also Published As

Publication number Publication date
JP3754698B1 (en) 2006-03-15
WO2006030893A1 (en) 2006-03-23
CN101010465A (en) 2007-08-01
JP2006083641A (en) 2006-03-30

Similar Documents

Publication Publication Date Title
CN100567659C (en) The basic structure of the tower
JP3981379B2 (en) Steel pier structure and its construction method
CN108571070B (en) Prefabricated steel tube concrete ring beam connecting structure and construction method
JP4691690B2 (en) Joint structure and joining method of pedestal
KR101904491B1 (en) Seismic reinforcing method for column with structure lifting and ground reinforcement to improve aseismicity
JP3831737B2 (en) Steel tower basic structure
JP3700102B2 (en) Building basic structure
JP5785476B2 (en) Reinforcing method and structure of existing foundation
JP3899094B2 (en) Foundation reinforcement method for existing structures by press-fitting steel pipe piles
JP2016223208A (en) Pile foundation structure
JP7263671B2 (en) pile foundation structure
JP2004244844A (en) High section performance pile
JP2886376B2 (en) Anchor structure of pile head
CN221030200U (en) Connecting piece and combination support stand of steel-pipe column and prefabricated square pile
KR102614593B1 (en) External Reinforcement Structure of Head Cutting PC Pile
JP4517228B2 (en) Steel pipe concrete pile head structure, steel pipe concrete pile head joining method, unit for joining
JPH06117052A (en) Precast horizontal central pillar
JP2006207306A (en) Frame structure and connection structure of frame body and pile
JP5267242B2 (en) Pier foundation structure and bridge pier foundation construction method
JPH04366229A (en) Temporary corresponding standard used for method of reverse driving construction
JPS60242224A (en) Construction of pile foundation reinforced against horizontal force
JP4621538B2 (en) Joining device for driving pile and upper column
JP3093625B2 (en) Foundation structure
KR20240027360A (en) External Reinforcement Structure of Head Cutting PC Pile
TWI616575B (en) Concrete pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20091209

Termination date: 20110916