[go: up one dir, main page]

CN100543232C - Double-layer continuous girder bridge with steel-concrete composite structure - Google Patents

Double-layer continuous girder bridge with steel-concrete composite structure Download PDF

Info

Publication number
CN100543232C
CN100543232C CNB2007101924793A CN200710192479A CN100543232C CN 100543232 C CN100543232 C CN 100543232C CN B2007101924793 A CNB2007101924793 A CN B2007101924793A CN 200710192479 A CN200710192479 A CN 200710192479A CN 100543232 C CN100543232 C CN 100543232C
Authority
CN
China
Prior art keywords
steel
bridge
girder
steel web
deck
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2007101924793A
Other languages
Chinese (zh)
Other versions
CN101187197A (en
Inventor
邵旭东
易笃韬
晏班夫
李立峰
彭旺虎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan University
Original Assignee
Hunan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan University filed Critical Hunan University
Priority to CNB2007101924793A priority Critical patent/CN100543232C/en
Publication of CN101187197A publication Critical patent/CN101187197A/en
Application granted granted Critical
Publication of CN100543232C publication Critical patent/CN100543232C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及一种钢混组合结构的双层连续梁桥,包括桥墩(1)、钢主梁(2)和桥面板(3),桥墩(1)支承钢主梁(2),钢主梁(2)支承桥面板(3)。钢主梁(2)主要由钢腹板(21)、小纵梁(22)和上横梁(23)构成,沿桥梁纵向按一定间隔布置的上横梁(23)与小纵梁(22)、钢腹板(21)正交并固接,每根上横梁(23)下方对应设置一根下横梁(5),非桥墩(1)处的下横梁(5)与钢腹板(21)连接,桥墩(1)处的下横梁(5)搁置于墩顶设置的支座横梁(7)上,下横梁(5)上铺设人行道板(10)。本发明兼具传统钢桁架结构和钢板梁组合结构特点,并能有效利用空间、节省建造成本,且造型美观。

The invention relates to a double-layer continuous girder bridge of steel-concrete composite structure, comprising a bridge pier (1), a steel girder (2) and a bridge deck (3), wherein the bridge pier (1) supports the steel girder (2), and the steel girder (2) supporting bridge deck (3). The steel girder (2) is mainly composed of steel webs (21), small longitudinal beams (22) and upper beams (23), and the upper beams (23) and the small longitudinal beams (22), arranged at certain intervals along the longitudinal direction of the bridge, The steel webs (21) are orthogonal and fixed, and a lower beam (5) is correspondingly arranged under each upper beam (23), and the lower beam (5) at the non-pier (1) is connected to the steel web (21), The lower beam (5) at the bridge pier (1) is rested on the support beam (7) arranged on the top of the pier, and the sidewalk slab (10) is laid on the lower beam (5). The invention has the characteristics of the traditional steel truss structure and the combined structure of the steel plate girder, can effectively use the space, save the construction cost, and has a beautiful appearance.

Description

钢混组合结构的双层连续梁桥 Double-layer continuous girder bridge with steel-concrete composite structure

技术领域 technical field

本发明涉及一种连续梁桥,尤其涉及一种钢混组合结构的双层连续梁桥。The invention relates to a continuous girder bridge, in particular to a double-layer continuous girder bridge with steel-concrete composite structure.

背景技术 Background technique

随着我国经济的快速发展和城市化进程的加快,城市中的交通流量也不断增大,过江桥梁通行能力的不足成为大部分跨江(河)城市交通网络中的瓶颈,新建过江桥梁的必要性和紧迫性也随之显现。综合考虑技术性能、空间利用、施工速度、经济效益等因素,现有国内外城市的桥梁越来越多地采用钢结构和钢混组合结构形式,其中钢板梁组合结构和钢桁架结构是常见的结构形式。传统的钢板梁组合结构一般采用∏字形截面形式,如图1所示,它主要由纵向钢梁11、横向钢梁12、竖向加劲肋13和混凝土桥面板14组成。其通常采用的构造是设置两根纵向钢梁11,通过横向钢梁12将两纵向钢梁11连接于竖向加劲肋13所在位置,竖向加劲肋13一般不与混凝土桥面板14连接。钢板梁组合结构一般适用于桥面不宽的中、小跨径桥梁,对于桥面较宽的情况,需要在混凝土桥面板14内张拉横向预应力钢筋15或采用横向悬臂钢梁。由于钢板梁组合结构的通透性很差,因此不适用于双层桥梁。钢桁架梁桥属比较古老的桥型,由上、下弦杆与腹杆构成,各杆件仅承受轴力。相比钢板梁组合结构,钢桁架梁结构具有较好的通透性,因而是双层桥梁的首选方案,但其梁高较大,对于非超大跨径的桥梁,在城市中显得笨重,一般仅用于铁路桥梁。另外,现有的城市桥梁中大多设有人行道,人行道若设于桥面板上,其一将增加桥面宽度,其二在桥上的交通流中难免会出现人车混流的情况,这不仅会影响车辆过桥的速度,还容易给桥上的交通安全造成隐患。With the rapid development of my country's economy and the acceleration of urbanization, the traffic flow in cities is also increasing, and the lack of capacity of cross-river bridges has become a bottleneck in the transportation network of most cities across the river (river). The necessity and urgency of this will also appear. Comprehensively considering factors such as technical performance, space utilization, construction speed, and economic benefits, bridges in existing cities at home and abroad are increasingly adopting steel structures and steel-concrete composite structures, among which steel plate girder composite structures and steel truss structures are common structure type. The traditional steel plate girder composite structure generally adopts a Π-shaped cross section, as shown in Figure 1, which is mainly composed of longitudinal steel girders 11, transverse steel girders 12, vertical stiffeners 13 and concrete bridge decks 14. The commonly used structure is to set two longitudinal steel girders 11, and connect the two longitudinal steel girders 11 to the position of the vertical stiffener 13 through the transverse steel girder 12, and the vertical stiffener 13 is generally not connected with the concrete bridge deck 14. Steel plate girder composite structures are generally suitable for medium and small-span bridges with narrow decks. For wider decks, it is necessary to stretch the transverse prestressed steel bars 15 in the concrete bridge deck 14 or adopt transverse cantilever steel beams. Due to the poor permeability of the steel plate girder composite structure, it is not suitable for double-deck bridges. The steel truss girder bridge is a relatively old bridge type, which is composed of upper and lower chords and web members, and each member only bears axial force. Compared with the steel plate girder composite structure, the steel truss girder structure has better permeability, so it is the first choice for double-deck bridges. For railway bridges only. In addition, most of the existing urban bridges are equipped with sidewalks. If the sidewalks are installed on the bridge deck, firstly, the width of the bridge deck will be increased, and secondly, mixed flow of people and vehicles will inevitably occur in the traffic flow on the bridge. It affects the speed of vehicles crossing the bridge, and it is also easy to cause hidden dangers to traffic safety on the bridge.

随着人们对城市美学的重视和对城市品位要求的不断提升,桥梁的美学功能也变得不可回避。我国上世纪修建的城市桥梁大部分是从功能、技术或经济角度出发,桥梁一般也采用常规的梁桥、拱桥、斜拉桥和悬索桥等形式,这些形式的桥梁在城市整体景观的大背景下,显得有些呆板、单调,与桥位环境不够协调,影响了城市建筑整体的美感。With people's emphasis on urban aesthetics and the continuous improvement of urban quality requirements, the aesthetic function of bridges has become unavoidable. Most of the urban bridges built in our country in the last century are based on functional, technical or economical perspectives. Bridges generally adopt the forms of conventional beam bridges, arch bridges, cable-stayed bridges and suspension bridges. These forms of bridges are in the context of the overall urban landscape , it seems a bit dull and monotonous, and it is not coordinated with the environment of the bridge site, which affects the overall aesthetic feeling of urban buildings.

发明内容 Contents of the invention

本发明要解决的技术问题是克服现有技术的不足,提供一种兼具传统钢桁架结构和钢板梁组合结构特点、能有效利用空间、节省建造成本、人车分流、造型美观、适宜于在城市繁华区内修建的钢混组合结构双层连续梁桥。The technical problem to be solved by the present invention is to overcome the deficiencies of the prior art, and provide a combination structure with the characteristics of traditional steel truss structure and steel plate girder, which can effectively use space, save construction cost, divert people and vehicles, and has a beautiful appearance, and is suitable for construction. A double-layer continuous girder bridge with steel-concrete composite structure built in the downtown area of the city.

为解决上述技术问题,本发明提出的技术方案为:一种钢混组合结构的双层连续梁桥,包括桥墩、钢主梁和桥面板,桥墩支承钢主梁,钢主梁支承桥面板,其特征在于所述钢主梁主要由钢腹板、小纵梁和上横梁构成,两片钢腹板构成所述钢主梁的两侧板,小纵梁位于桥面板的纵向中心线下方,沿桥梁纵向间隔布置的上横梁与小纵梁、钢腹板正交并固接,每根上横梁下方对应设置一根下横梁,非桥墩处的下横梁与钢腹板连接,桥墩处的下横梁搁置于桥墩顶部设置的支座横梁上,下横梁上铺设人行道板。In order to solve the above technical problems, the technical solution proposed by the present invention is: a double-layer continuous girder bridge of steel-concrete composite structure, comprising bridge piers, steel girders and bridge decks, the bridge piers support the steel girders, and the steel girders support the bridge decks, It is characterized in that the steel girder is mainly composed of steel webs, small longitudinal girders and upper beams, two steel webs constitute the two side plates of the steel girder, and the small longitudinal girders are located below the longitudinal centerline of the bridge deck. The upper beams arranged at intervals along the longitudinal direction of the bridge are perpendicular to the small longitudinal beams and steel webs and are fixed. A lower beam is correspondingly arranged under each upper beam. It rests on the support beam set on the top of the pier, and paves the sidewalk slab on the lower beam.

当所述钢腹板的底面在竖直平面上的投影为曲线时,若下横梁位于钢腹板底面下方,下横梁则以吊杆作为连接件固接于钢腹板下方;若下横梁位于钢腹板底面上方,则下横梁直接固接(焊接或螺栓连接)于钢腹板上,或者以固接于钢腹板内侧的支板作为支撑件,下横梁搁置于支板上。When the projection of the bottom surface of the steel web on the vertical plane is a curve, if the lower beam is located below the bottom surface of the steel web, the lower beam is fixed below the steel web with a suspender as a connector; if the lower beam is located Above the bottom surface of the steel web, the lower beam is directly fixed (welded or bolted) to the steel web, or the support plate fixed on the inner side of the steel web is used as a support, and the lower beam rests on the support plate.

当上述钢腹板为矩形直板结构时,若下横梁均位于钢腹板底面下方,则下横梁均通过吊杆作为连接件与钢腹板固接;若下横梁均位于钢腹板底面上方,则下横梁直接固接(焊接或螺栓连接)于钢腹板上,或者以固接于钢腹板内侧的支板为支撑件,下横梁均搁置于支板上。When the above-mentioned steel web is a rectangular straight plate structure, if the lower beams are all located below the bottom surface of the steel web, then the lower beams are fixed to the steel web through suspenders as connectors; if the lower beams are all located above the bottom surface of the steel web, The lower beam is directly fixed (welded or bolted) to the steel web, or the support plate fixed on the inner side of the steel web is used as a support, and the lower beam is placed on the support plate.

上述上横梁为悬臂梁,由上横梁支承的桥面板由预制矮肋型桥面板块拼接而成,相邻的预制矮肋型桥面板块的纵向现浇湿接缝设置于钢腹板和/或小纵梁上方,相邻预制矮肋型桥面板块的横向现浇湿接缝设置于上横梁上方,预制矮肋型桥面板块内设有伸至现浇湿接缝中的预留钢筋,相邻两预制矮肋型桥面板块内伸出的预留钢筋焊接连接,所有现浇湿接缝中均密布大头剪力钉。The above-mentioned upper beam is a cantilever beam, and the bridge deck supported by the upper beam is spliced by prefabricated low-rib bridge deck blocks, and the longitudinal wet joints of adjacent prefabricated low-rib bridge deck blocks are set on the steel web and Or above the small longitudinal girder, the transverse cast-in-place wet joints of the adjacent prefabricated low-rib bridge deck blocks are set above the upper beam, and the prefabricated low-rib bridge deck blocks are provided with reserved steel bars extending into the cast-in-place wet joints , the reserved steel bars protruding from two adjacent prefabricated low-rib bridge deck blocks are welded and connected, and all cast-in-place wet joints are densely covered with tack shear nails.

上述桥面板上的行车道通过桥梁引桥与城市路网相连通,人行道板上的人行道与城市的沿江风光带相连通。The traffic lane on the above-mentioned bridge deck is connected with the urban road network through the bridge approach bridge, and the sidewalk on the sidewalk board is connected with the city's riverside scenery belt.

上述钢腹板为透空式工字形钢梁,透空处嵌有花纹图案和/或灯饰。The above-mentioned steel web is a hollow-type I-shaped steel beam, and patterns and/or lights are embedded in the hollow.

上述桥墩为花瓶式薄壁墩结构。The above-mentioned piers are vase-shaped thin-walled pier structures.

与现有技术相比,本发明的优点就在于:Compared with the prior art, the present invention has the advantages of:

1、本发明的钢—混凝土组合结构双层连续梁桥综合了钢桁架梁和传统钢板梁组合结构的特点,并实行人车完全分离,上层为行车道,下层为人行道,这样既减小了桥梁的总宽度,能有效利用结构空间,也相应减轻了城市土地资源紧缺所造成的道路空间压力。由于减小了桥宽,如果跨径选择适当,造价也能获得相应节省。1. The steel-concrete combined structure double-layer continuous girder bridge of the present invention combines the characteristics of steel truss girder and traditional steel plate girder combined structure, and implements the complete separation of people and vehicles. The total width of the bridge can effectively use the structural space, and correspondingly reduce the pressure on road space caused by the shortage of urban land resources. Due to the reduced bridge width, if the span is selected properly, the cost can also be saved accordingly.

2、本发明的钢—混凝土组合结构形式使得桥梁上部结构自重较轻,而桥面板在横向采用悬臂外伸形式,缩小了两片钢腹板之间的距离,这使得桥梁下部墩、台和基础的尺寸得以大大减小,这不仅减小了桥梁下部结构的建造成本,还增加了桥下的使用空间。另外,通过调节上横梁的悬臂长度,可按需要调节行车道和人行道的宽度。受上横梁支承的桥面板外伸悬臂部分也可以最大程度地避免雨水和阳光紫外线对桥梁钢结构部分的侵蚀,按照目前的防护水平,桥体的钢结构经防护处理后,至少可保用30年。2. The steel-concrete composite structure of the present invention makes the superstructure of the bridge lighter in weight, and the bridge deck adopts the form of cantilever extension in the transverse direction, which reduces the distance between the two steel webs, which makes the bridge lower pier, abutment and The size of the foundation can be greatly reduced, which not only reduces the construction cost of the bridge substructure, but also increases the usable space under the bridge. In addition, by adjusting the cantilever length of the upper beam, the width of the driveway and sidewalk can be adjusted as required. The overhanging cantilever part of the bridge deck supported by the upper beam can also avoid the erosion of rainwater and sunlight ultraviolet rays on the steel structure of the bridge to the greatest extent. According to the current protection level, the steel structure of the bridge body can be guaranteed for at least 30 years after protective treatment. Year.

3、本发明的桥面板和人行道板均为预制的混凝土板,为保证桥面板的抗弯刚度,桥面板采用了预制矮肋式混凝土板结构。由于桥梁的上部结构均采用预制施工,可以与基础施工同时进行,这样不仅可以保证施工质量,减少桥面板收缩徐变的影响,而且加快了桥梁的施工速度,可以最大限度地减小桥梁施工对城市交通的负面影响并使桥梁在最短的时间内投入运营。3. Both the bridge deck and the sidewalk slab of the present invention are prefabricated concrete slabs. In order to ensure the bending rigidity of the bridge deck, the bridge deck adopts a prefabricated low-rib concrete slab structure. Since the upper structure of the bridge is prefabricated, it can be carried out simultaneously with the foundation construction, which not only ensures the construction quality, reduces the impact of bridge deck shrinkage and creep, but also speeds up the construction speed of the bridge, which can minimize the impact of bridge construction on Negative effects of urban traffic and making the bridge operational in the shortest possible time.

4、现今城市的江河两岸大都设有沿江风光带,本发明可以使上层行车道通过引桥与城市路网相连通,下层人行道直接与沿江(河)风光带相连通,行人可从桥头的沿江(河)风景区直接上桥,十分便捷,从而克服了在桥头设置人车混合立交的难题;上层汽车专用,车辆畅通无阻,下层行人过桥避免了日晒雨淋,安全舒适,大大提高了桥梁的服务水平。若因交通规划需要,下层还可考虑布置公交线路。在人行道两侧可根据需要布置预留管线槽,以便于管线的布设、安装、检查及维护。4. Most of the rivers and rivers in today’s cities are equipped with scenic belts along the river. The present invention can make the upper carriageway communicate with the urban road network through the approach bridge, and the lower sidewalks directly communicate with the scenic belts along the river (river). Pedestrians can walk along the river ( River) Scenic Area directly on the bridge, which is very convenient, thus overcoming the problem of setting up a mixed pedestrian-vehicle interchange at the bridgehead; the upper layer is dedicated to cars, and the vehicles are unimpeded, and the lower layer of pedestrians can avoid the sun and rain, which is safe and comfortable, and greatly improves the quality of the bridge. level of service. If it is required by traffic planning, the lower floor can also consider the layout of bus lines. Reserved pipeline troughs can be arranged on both sides of the sidewalk as required to facilitate the layout, installation, inspection and maintenance of pipelines.

5、本发明的钢腹板可为透空式,且其底面在竖直平面上的投影呈曲线,该设计下的钢主梁呈现为变高度的水珠形透空式梁体,这使得桥梁的外观轻巧优美,远看如长龙卧波,富有动感。透空式钢腹板的受力特性兼有板和桁架的力学特征,相对于通透性较高的桁架梁而言,在保持良好通透性的前提下提高了桥梁整体的刚度。钢腹板的透空处可根据实际情况引入不同的具有古典建筑风格的花纹图案,也可选择不嵌花纹图案或嵌入其他图案。下部的桥墩采用花瓶式薄壁墩,以便使桥梁自身的古典建筑风格能够保持统一,并能够与桥位环境和谐映衬,保持良好的视觉效果和审美价值,共同构成城市中的一道亮丽的风景。5. The steel web of the present invention can be air-permeable, and the projection of its bottom surface on the vertical plane is curved. The steel girder under this design presents a drop-shaped air-permeable beam body with variable height, which makes The appearance of the bridge is light and graceful, and it looks like a long dragon lying on the waves from a distance, full of dynamics. The mechanical characteristics of the permeable steel web combine the mechanical characteristics of the plate and the truss. Compared with the truss beam with high permeability, the overall stiffness of the bridge is improved while maintaining good permeability. The hollow part of the steel web can introduce different patterns with classical architectural style according to the actual situation, and can also choose not to inlay patterns or embed other patterns. The lower pier adopts vase-style thin-walled pier, so as to maintain the unity of the classical architectural style of the bridge itself, and to set off harmoniously with the environment of the bridge site, maintain good visual effect and aesthetic value, and together constitute a beautiful scenery in the city.

附图说明 Description of drawings

图1为传统钢板梁组合结构的横截面示意图;Fig. 1 is the cross-sectional schematic diagram of traditional steel plate girder composite structure;

图2为本发明的桥梁单跨结构示意图;Fig. 2 is the bridge single-span structure schematic diagram of the present invention;

图3为钢主梁在吊杆连接件处的横截面示意图;Fig. 3 is a schematic cross-sectional view of the steel girder at the suspender connector;

图4为钢主梁在桥墩处的横截面示意图;Fig. 4 is the schematic diagram of the cross section of the steel girder at the bridge pier;

图5为钢主梁在支板支撑件处的横截面示意图;Fig. 5 is a schematic cross-sectional view of the steel girder at the support plate support;

图6为图2中F-F处的剖视图;Fig. 6 is the sectional view of F-F place in Fig. 2;

图7为桥面板四分法的结构示意图;Figure 7 is a structural schematic diagram of the quartering method of the bridge deck;

图8为桥面板三分法的结构示意图;Fig. 8 is a structural schematic diagram of the method of thirds of the bridge deck;

图9为桥面板二分法的结构示意图;Fig. 9 is a structural schematic diagram of bridge deck dichotomy;

图10为钢腹板透空处的B花纹图案;Figure 10 is the B pattern pattern at the hollow part of the steel web;

图11为钢腹板透空处的C花纹图案;Figure 11 shows the C pattern pattern at the hollow part of the steel web;

图12为图6中A处的局部放大示意图;Fig. 12 is a partially enlarged schematic diagram of place A in Fig. 6;

图13为采用矩形钢腹板的本发明桥梁单跨结构示意图;Fig. 13 is the schematic diagram of the bridge single-span structure adopting the rectangular steel web of the present invention;

图14为本发明与沿江风光带的连接示意图;Fig. 14 is a schematic diagram of the connection between the present invention and the scenery belt along the river;

图15为本发明施工方法步骤一的示意图;Fig. 15 is a schematic diagram of step 1 of the construction method of the present invention;

图16为本发明施工方法步骤二的示意图;Fig. 16 is a schematic diagram of step 2 of the construction method of the present invention;

图17为本发明施工方法步骤三的示意图;Fig. 17 is a schematic diagram of step three of the construction method of the present invention;

图18为本发明施工方法步骤四的示意图;Fig. 18 is a schematic diagram of step 4 of the construction method of the present invention;

图19为本发明施工方法步骤五的示意图;Fig. 19 is a schematic diagram of step five of the construction method of the present invention;

图20为本发明施工方法步骤六的示意图;Fig. 20 is a schematic diagram of step six of the construction method of the present invention;

图21为本发明施工方法步骤七的示意图。Fig. 21 is a schematic diagram of Step 7 of the construction method of the present invention.

图例说明:illustration:

1、桥墩                11、纵向钢梁1. Bridge piers 11. Longitudinal steel girders

12、横向钢梁           13、竖向加劲肋12. Horizontal steel beams 13. Vertical stiffeners

14、混凝土桥面板       15、横向预应力钢筋14. Concrete bridge deck 15. Transverse prestressed reinforcement

2、钢主梁              21、钢腹板2. Steel main girder 21. Steel web

22、小纵梁             23、上横梁22. Small longitudinal beam 23. Upper beam

24、竖向加劲板         3、桥面板24. Vertical stiffener 3. Bridge deck

31、预留钢筋           32、钢腹板处湿接缝31. Reserved steel bars 32. Wet joints at steel webs

33、小纵梁处湿接缝     34、上横梁处湿接缝33. Wet joints at small longitudinal beams 34. Wet joints at upper beams

35、预制矮肋型桥面板块 4、吊杆35. Prefabricated low-rib bridge deck blocks 4. Suspenders

41、支板               5、下横梁41. Support plate 5. Lower beam

6、大头剪力钉          7、支座横梁6. Big head shear nail 7. Support beam

71、墩顶支座           8、沥青砼桥面71. Pier top support 8. Asphalt concrete bridge deck

9、预留管线槽          10、人行道板9. Reserved pipeline trough 10. Sidewalk board

具体实施方式 Detailed ways

如图2~图14所示,本发明的钢混组合结构双层连续梁桥综合了钢桁架梁和传统钢板梁组合结构的特点,它包括桥墩1、钢主梁2和桥面板3,桥墩1支承钢主梁2,钢主梁2支承桥面板3,其中钢主梁2主要是由透空式钢腹板21、小纵梁22和悬臂型上横梁23组合构成,桥面板3是由预制矮肋型桥面板块35拼装浇缝连接而成。钢腹板21采用工字梁结构,钢腹板21的内侧按一定间距设置竖向加劲肋13(见图6),以加强其局部刚度。小纵梁22位于桥面板3的纵向中心线下方,根据桥梁所承受的荷载大小及桥梁的跨径长度,沿桥梁纵向间隔布置有上横梁23,上横梁23与小纵梁22、钢腹板21垂直正交并焊接(也可通过螺栓固接)。每根上横梁23的正下方对应地设置一根下横梁5,非桥墩1处的下横梁5与钢腹板21连接,桥墩1处的下横梁5搁置于桥墩1顶部设置的支座横梁7上,由支座横梁7直接承受其荷载,支座横梁7由墩顶支座71支撑,钢腹板21在墩顶支座71处外侧设置竖向加劲板24以加强其局部刚度(如图4所示)。下横梁5均采用工字梁结构,且位于同一高度上,所有的下横梁5作为其上部铺设的人行道板10的支撑件。As shown in Figures 2 to 14, the steel-concrete composite structure double-layer continuous girder bridge of the present invention combines the characteristics of steel truss girders and traditional steel plate girder composite structures, and it includes bridge piers 1, steel girders 2 and bridge decks 3, bridge piers 1 supports the steel girder 2, and the steel girder 2 supports the bridge deck 3, wherein the steel girder 2 is mainly composed of a hollow steel web 21, a small longitudinal beam 22 and a cantilevered upper beam 23, and the bridge deck 3 is composed of The prefabricated low-rib bridge deck blocks 35 are assembled and connected by pouring joints. The steel web 21 adopts an I-beam structure, and the inner side of the steel web 21 is provided with vertical stiffeners 13 (see FIG. 6 ) at a certain interval to enhance its local rigidity. The small longitudinal girder 22 is located below the longitudinal centerline of the bridge deck 3. According to the load on the bridge and the span length of the bridge, upper beams 23 are arranged at intervals along the longitudinal direction of the bridge. 21 are vertically orthogonal and welded (also can be fixed by bolts). A corresponding lower beam 5 is set directly below each upper beam 23, the lower beam 5 at the non-pier 1 is connected to the steel web 21, and the lower beam 5 at the bridge pier 1 rests on the support beam 7 set on the top of the bridge pier 1 , the load is directly borne by the support beam 7, the support beam 7 is supported by the pier top support 71, and the steel web 21 is provided with a vertical stiffener 24 outside the pier top support 71 to strengthen its local stiffness (as shown in Figure 4 shown). The lower beams 5 all adopt the I-beam structure, and are located at the same height, and all the lower beams 5 are used as supports for the pavement slabs 10 laid on their upper parts.

钢腹板21的底面在竖直平面上的投影呈曲线,而下横梁5位于同一水平高度上,因此在靠近单跨中部的部分下横梁5位于钢腹板21底面下方,此时下横梁5与钢腹板21以吊杆4作为连接件固接,吊杆4一端连接钢腹板21,另一端连接下横梁5,下横梁5通过吊杆4将其所承受荷载传递给钢腹板21(如图3所示);而在靠近桥墩1处的部分下横梁5则位于钢腹板21底面上方,此时下横梁5以固接于钢腹板21内侧的支板41作为支撑件(也可将下横梁5直接固接于钢腹板21内侧),下横梁5搁置于支板41上,由支板41承受其荷载(如图5所示)。钢腹板也可采用矩形直板结构,若因设计要求致使非桥墩处的下横梁全部位于钢腹板底面下方时,则全部采用吊杆作为连接件与钢腹板连接;若因设计要求致使非桥墩处的下横梁全部位于钢腹板底面上方时,则所有下横梁直接固接(焊接或螺栓连接)于钢腹板上,或者以固接于钢腹板内侧的支板作为支撑件,所有下横梁搁置于支板上。图13所示结构即为钢腹板21为矩形直板结构,且下横梁5全部位于矩形钢腹板21底面上方时的情形,此时下横梁5直接固接(焊接或螺栓连接)于钢腹板21上。不论钢腹板采用何种形式或钢腹板与下横梁采用何种连接方式,桥墩1处的下横梁5仍可直接搁置于桥墩1顶部的支座横梁7上。The projection of the bottom surface of the steel web 21 on the vertical plane is curved, and the lower beam 5 is located at the same level, so the lower beam 5 is located below the bottom surface of the steel web 21 near the middle of the single span. The steel web 21 is fixedly connected with the suspender 4 as a connector, one end of the suspender 4 is connected to the steel web 21, and the other end is connected to the lower beam 5, and the lower beam 5 transmits the load it bears to the steel web 21 through the suspender 4 ( As shown in Figure 3); and the part of the lower beam 5 near the pier 1 is located above the bottom surface of the steel web 21, and now the lower beam 5 uses the support plate 41 fixed on the inner side of the steel web 21 as a support (also can The lower beam 5 is directly fixed on the inner side of the steel web 21), the lower beam 5 rests on the support plate 41, and the support plate 41 bears its load (as shown in FIG. 5 ). The steel web can also adopt a rectangular straight plate structure. If the lower beams at non-pier locations are all located below the bottom surface of the steel web due to design requirements, suspenders are used as connectors to connect with the steel web; When all the lower beams at the pier are above the bottom of the steel web, all the lower beams are directly fixed (welded or bolted) to the steel web, or the support plate fixed to the inner side of the steel web is used as a support. The lower beam rests on the support plate. The structure shown in Figure 13 is the situation when the steel web 21 is a rectangular straight plate structure, and the lower beam 5 is all located above the bottom surface of the rectangular steel web 21. At this time, the lower beam 5 is directly fixed (welded or bolted) to the steel web. 21 on. Regardless of the form of the steel web or the connection method between the steel web and the lower beam, the lower beam 5 at the pier 1 can still be placed directly on the support beam 7 at the top of the pier 1 .

桥面板3上铺设有沥青砼桥面8,沥青砼桥面8上为行车道;在下横梁5上铺设有人行道板10,人行道板10上为人行道。由于实行上层行车道、下层人行道的人车完全分离模式,这样既减小了桥梁的总宽度,有效利用了桥梁结构的空间,同时也减轻了城市土地资源紧缺所造成的道路空间压力。由于减小了桥宽,如果跨径选择适当,造价也能获得相应节省。上层行车道通过桥梁引桥与城市路网相连通,下层人行道直接与城市沿江(河)风光带D相连通,沿江风光带D紧邻沿江大道E,行人可十分便捷地从桥头的沿江风光带D上桥,克服了在桥头设置人车混合立交的难题(如图14所示);上层汽车专用,车辆畅通无阻,下层行人过桥避免了日晒雨淋,安全舒适,大大提高了桥梁的服务水平。另外,通过调节上横梁23的悬臂长度,可按需要调节桥梁行车道和人行道的宽度。若因交通规划需要,下层还可考虑布置公交线路。人行道两侧根据需要布置有预留管线槽9,以便于管线的布设、安装、检查及维护。An asphalt concrete bridge deck 8 is laid on the bridge deck 3, and the asphalt concrete bridge deck 8 is a carriageway; Due to the complete separation of pedestrians and vehicles from the upper carriageway and the lower sidewalk, this not only reduces the total width of the bridge, effectively utilizes the space of the bridge structure, but also reduces the pressure on road space caused by the shortage of urban land resources. Due to the reduced bridge width, if the span is selected properly, the cost can also be saved accordingly. The upper carriageway is connected to the urban road network through bridge approach bridges, and the lower sidewalk is directly connected to the urban riverside (river) scenery belt D, which is next to Yanjiang Avenue E. The bridge overcomes the problem of setting up a mixed pedestrian-vehicle interchange at the bridge head (as shown in Figure 14); the upper layer is dedicated to cars, and the vehicles are unimpeded, and the lower layer of pedestrians avoids the sun and rain to cross the bridge, which is safe and comfortable, which greatly improves the service level of the bridge . In addition, by adjusting the cantilever length of the upper beam 23, the width of the bridge driveway and sidewalk can be adjusted as required. If it is required by traffic planning, the lower floor can also consider the layout of bus lines. Reserved pipeline grooves 9 are arranged on both sides of the sidewalk as required to facilitate the layout, installation, inspection and maintenance of pipelines.

为保证行车道下方桥面板3的抗弯刚度,桥面板3采用由预制矮肋型桥面板块35拼接而成的方式。如图7所示,以两侧纵向的钢腹板21和中部的小纵梁22这三根纵梁所在位置为界,本实施例中的桥面板3以预制矮肋型桥面板块35的长度为单位,沿桥梁横向被分成等宽的四个部分(也可根据实际需要分成如图8所示三个部分或如图9所示的两个部分),沿纵向则以预制矮肋型桥面板块35的宽度为单位依次拼接,各预制矮肋型桥面板块35间留有现浇湿接缝,其中包括钢腹板处湿接缝32、小纵梁处湿接缝33和上横梁处湿接缝34。各预制矮肋型桥面板块35内设有伸至现浇湿接缝中的预留钢筋31,通过对现浇湿接缝处伸出外露的预留钢筋31进行焊接并浇筑接缝,可使得预制矮肋型桥面板块35连接成一整体桥面板3。上横梁23、小纵梁22和钢腹板21顶部的各现浇湿接缝中密布大头剪力钉6,以保证桥面板3与钢主梁2之间的连接牢固。在桥梁宽度方向上,桥面板3呈悬臂外伸结构形式,这样相对缩短了下方两钢腹板21的间距,进而使得下部桥墩1及基础的尺寸得以大大减小。此外,悬臂式的桥面板3还可以最大程度地避免雨水和阳光紫外线对桥梁主体下部钢结构的侵蚀,按照目前的防护水平,桥梁主体下部的钢结构经防护处理后,至少可保用30年。In order to ensure the bending rigidity of the bridge deck 3 under the carriageway, the bridge deck 3 is spliced by prefabricated low-rib bridge deck blocks 35 . As shown in Figure 7, with the positions of the three longitudinal beams, the longitudinal steel webs 21 on both sides and the small longitudinal beam 22 in the middle, as the boundary, the bridge deck 3 in this embodiment has the length of the prefabricated low-rib bridge deck block 35 As a unit, it is divided into four parts of equal width along the transverse direction of the bridge (it can also be divided into three parts as shown in Figure 8 or two parts as shown in Figure 9 according to actual needs). The width of the panel blocks 35 is spliced in sequence, and there are cast-in-place wet joints between the prefabricated low-rib bridge deck blocks 35, including the wet joints 32 at the steel web, the wet joints 33 at the small longitudinal girders and the upper beams. Wet seams34. Each prefabricated low-rib bridge deck block 35 is provided with reserved steel bars 31 extending into the cast-in-place wet joints. By welding the exposed reserved steel bars 31 protruding from the cast-in-place wet joints and pouring the joints, the joints can be The prefabricated low-rib bridge deck blocks 35 are connected to form an integral bridge deck 3 . The upper beam 23 , the small longitudinal beam 22 and the top of the steel web 21 are densely covered with tack shear nails 6 in the wet joints at the top of the steel web 21 to ensure that the connection between the bridge deck 3 and the steel girder 2 is firm. In the width direction of the bridge, the bridge deck 3 is in the form of a cantilever overhanging structure, which relatively shortens the distance between the two steel webs 21 below, thereby greatly reducing the size of the lower pier 1 and the foundation. In addition, the cantilevered bridge deck 3 can also avoid the erosion of rainwater and sunlight ultraviolet rays on the steel structure of the lower part of the bridge body. According to the current protection level, the steel structure of the lower part of the bridge body can be guaranteed for at least 30 years after protective treatment .

本发明钢腹板21的底面在竖直平面上的投影为曲线,且为透空式结构,整个钢主梁21呈现为变高度的水珠形透空式梁体,这使得桥梁的外观轻巧优美,远观如长龙卧波,富有动感。透空式钢腹板21的受力特性兼有板和桁架的力学特征,相对于通透性较高的桁架梁而言,在保持良好通透性的前提下提高了桥梁整体的刚度。钢腹板21上开有一系列大小不等的圆孔,根据实际情况和景观性要求,本实施例在钢腹板21的圆孔中嵌入了具有古典建筑风格的不同花纹图案,如图10和图11所示,也可根据实际需要选择不嵌花纹图案或嵌入其他花纹图案。为了与本实施例的古典建筑风格相配合,下部的桥墩1采用了较轻盈的花瓶式薄壁墩,也可以根据桥梁自身的建筑风格采用其他形式的桥墩,以便使桥梁自身的建筑风格和谐统一,并能够与桥位环境和谐映衬,保持良好的视觉效果,共同构成城市中的一道亮丽的风景。The projection of the bottom surface of the steel web 21 of the present invention on the vertical plane is a curve, and it is a hollow structure. The whole steel girder 21 presents a drop-shaped hollow beam body with variable height, which makes the appearance of the bridge light and light. Elegant, from a distance, it looks like a long dragon lying on the waves, full of dynamics. The mechanical characteristics of the permeable steel web 21 have both the mechanical characteristics of the plate and the truss. Compared with the truss beam with high permeability, the rigidity of the bridge as a whole is improved while maintaining good permeability. There are a series of round holes of different sizes on the steel web 21. According to the actual situation and landscape requirements, in this embodiment, different decorative patterns with classical architectural styles are embedded in the round holes of the steel web 21, as shown in Figure 10 and As shown in Fig. 11, it is also possible to choose not to inlay pattern or to embed other patterns according to actual needs. In order to match the classical architectural style of this embodiment, the lower pier 1 adopts a lighter vase-shaped thin-walled pier, and other types of pier can also be used according to the architectural style of the bridge itself, so as to make the architectural style of the bridge itself harmonious and unified , and can set off harmoniously with the environment of the bridge site, maintain a good visual effect, and together constitute a beautiful scenery in the city.

施工步骤:Construction steps:

如图15~图21所示,本发明的施工按以下几个步骤进行:As shown in Fig. 15~Fig. 21, construction of the present invention is carried out by following several steps:

步骤一:如图15所示,首先进行桥墩1基础的施工,同时在预制场进行预制矮肋型桥面板块35的预制,并在河道内架设拼装缆吊设备,缆吊设备的架设又包括缆索吊机基础的施工、塔架的拼装、缆索的悬挂和缆索的地锚固定等步骤。然后根据缆吊设备的起吊能力确定钢腹板21的吊装节段数,综合考虑经济性和施工速度,本实施例中将其分为3段进行吊装。Step 1: As shown in Figure 15, the foundation of the pier 1 is firstly constructed, and at the same time, the prefabricated low-rib bridge deck block 35 is prefabricated in the prefabrication yard, and the assembled cable crane equipment is erected in the river channel, and the erection of the cable crane equipment includes The construction of the cable crane foundation, the assembly of the tower, the suspension of the cable and the anchoring of the cable and other steps. Then, according to the hoisting capacity of the cable hoisting equipment, the number of hoisting segments of the steel web 21 is determined, and considering economy and construction speed, it is divided into three sections for hoisting in this embodiment.

步骤二:如图16所示,首先完成桥墩1的施工;当桥墩1施工完成后,先吊装墩顶0号块钢腹板,并在墩顶处进行临时固结。Step 2: As shown in Figure 16, first complete the construction of pier 1; when the construction of pier 1 is completed, first hoist the No. 0 steel web on the top of the pier, and perform temporary consolidation at the top of the pier.

步骤三:如图17所示,沿0号块两侧依次对称吊装1号块和2号块,1号块与0号块焊接成型,2号块与1号块焊接成型。在钢腹板21的整个吊装过程中,墩顶支座71均处于临时固结状态,对称吊装过程中必须避免墩顶临时固结处出现较大的不平衡弯矩。Step 3: As shown in Figure 17, block No. 1 and block No. 2 are hoisted sequentially symmetrically along both sides of block No. 0, block No. 1 is welded to block No. 0, and block No. 2 is welded to block No. 1. During the entire hoisting process of the steel web 21 , the pier top support 71 is in a temporary consolidation state, and it is necessary to avoid large unbalanced bending moments at the temporary consolidation of the pier top during the symmetrical hoisting process.

步骤四、五:如图18、图19所示,待桥梁各跨的2号块吊装完工后再通过满堂支架方式来对边跨进行施工;待边跨合龙后撤除边跨的临时固结,然后依次合龙中间各跨并撤除所有墩顶处的临时固结。Steps 4 and 5: As shown in Figure 18 and Figure 19, after the hoisting of the No. 2 block of each span of the bridge is completed, the side spans will be constructed by means of full support; after the side spans are closed, the temporary consolidation of the side spans will be removed. Then close each span in the middle of the dragon in turn and remove the temporary consolidation at the top of all piers.

步骤六:如图20所示,桥梁的主体结构基本形成以后,安装预制矮肋型桥面板块35(即行车道板)、人行道板10,并现浇湿接缝。Step 6: As shown in Figure 20, after the main structure of the bridge is basically formed, install the prefabricated low-rib bridge deck block 35 (ie, the roadway slab), the sidewalk slab 10, and cast in-situ wet joints.

步骤七:如图21所示,撤除缆索吊机等施工设施,进行桥面系和附属设施施工,竣工验收后整个桥梁投入运营。Step 7: As shown in Figure 21, remove the construction facilities such as cable cranes, carry out the construction of the bridge deck system and auxiliary facilities, and put the entire bridge into operation after completion and acceptance.

由于桥梁梁体的主体结构均采用预制施工,可以与基础施工同时进行,这样不仅可以保证施工质量,减少桥面板3收缩徐变的影响,而且施工速度快,可以最大限度的减小对城市交通的负面影响并在最短的时间内投入运营。Since the main structure of the bridge girder is prefabricated, it can be carried out at the same time as the foundation construction, which can not only ensure the construction quality, reduce the impact of shrinkage and creep of the bridge deck 3, but also the construction speed is fast, which can minimize the impact on urban traffic. negative impact and put into operation in the shortest possible time.

Claims (9)

1, a kind of double-deck continuous girder bridge of steel-concrete combined structure, comprise bridge pier (1), steel girder (2) and bridge deck (3), bridge pier (1) support steel girder (2), steel girder (2) supporting bridge deck (3), it is characterized in that described steel girder (2) is mainly by steel web (21), stringer (22) and top rail (23) constitute, two steel webs (21) constitute the biside plate of described steel girder (2), stringer (22) is positioned at the longitudinal centre line below of bridge deck (3), top rail (23) and stringer (22) along bridge longitudinal separation layout, steel web (21) quadrature is also affixed, every top rail (23) below correspondence is provided with a lower transverse beam (5), the lower transverse beam (5) that non-bridge pier (1) is located is connected with steel web (21), the lower transverse beam (5) that bridge pier (1) is located is held on the support beam (7) of bridge pier (1) top setting, and lower transverse beam (5) is gone up and laid side walk slab (10).
2, the double-deck continuous girder bridge of steel-concrete combined structure according to claim 1, the bottom surface that it is characterized in that described steel web (21) is projected as curve on perpendicular, when lower transverse beam (5) was positioned at below, steel web (21) bottom surface, lower transverse beam (5) was fixed in steel web (21) below with suspension rod (4) as connector; When lower transverse beam (5) was positioned at top, steel web (21) bottom surface, lower transverse beam (5) directly was fixed on the steel web (21), and perhaps to be fixed in the inboard support plate (41) of steel web (21) as support member, lower transverse beam (5) is held on the support plate (41).
3, the double-deck continuous girder bridge of steel-concrete combined structure according to claim 1, it is characterized in that described steel web (21) is the straight plated construction of rectangle, if lower transverse beam (5) all is positioned at below, steel web (21) bottom surface, lower transverse beam (5) is all affixed as connector and steel web (21) by suspension rod (4); If lower transverse beam (5) all is positioned at top, steel web (21) bottom surface, lower transverse beam (5) directly is fixed on the steel web (21), and perhaps to be fixed in the inboard support plate (41) of steel web (21) as support member, lower transverse beam (5) is held on the support plate (41).
4, double-deck continuous girder bridge according to each described steel-concrete combined structure in the claim 1~3, it is characterized in that described top rail (23) is a semi girder, bridge deck (3) by top rail (23) supporting are spliced by prefabricated short rib type bridge floor plate (35), the vertical cast-in-place wet seam of adjacent prefabricated short rib type bridge floor plate (35) is arranged at steel web (21) and/or stringer (22) top, the horizontal cast-in-place wet seam of adjacent prefabricated short rib type bridge floor plate (35) is arranged at top rail (23) top, be provided with the reserved steel bar (31) that extends in the cast-in-place wet seam in the prefabricated short rib type bridge floor plate (35), the reserved steel bar (31) that stretches out in the adjacent two prefabricated short rib type bridge floor plates (35) is welded to connect, and is densely covered with major part WELDING STUDS (6) in the cast-in-place wet seam.
5, the double-deck continuous girder bridge of steel-concrete combined structure according to claim 4 is characterized in that the runway on the described bridge deck (3) is connected with city road network by access bridge, and the sidewalk on the side walk slab (10) is connected with the riverine scenic belt in city.
6, according to the double-deck continuous girder bridge of each described steel-concrete combined structure in the claim 1~3, it is characterized in that the runway on the described bridge deck (3) is connected with city road network by the bridge access bridge, the sidewalk on the side walk slab (10) is connected with the riverine scenic belt in city.
7, the double-deck continuous girder bridge of steel-concrete combined structure according to claim 5 is characterized in that described steel web (21) is the exposed throughout type girder steel, and saturating vacancy is embedded with floral designs and/or lamp decoration.
8, the double-deck continuous girder bridge of steel-concrete combined structure according to claim 7 is characterized in that described bridge pier (1) is vase formula Thin-Wall Piers structure.
9,, it is characterized in that described steel web (21) is the exposed throughout type girder steel according to the double-deck continuous girder bridge of each described steel-concrete combined structure in the claim 1~3.
CNB2007101924793A 2007-12-03 2007-12-03 Double-layer continuous girder bridge with steel-concrete composite structure Expired - Fee Related CN100543232C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2007101924793A CN100543232C (en) 2007-12-03 2007-12-03 Double-layer continuous girder bridge with steel-concrete composite structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2007101924793A CN100543232C (en) 2007-12-03 2007-12-03 Double-layer continuous girder bridge with steel-concrete composite structure

Publications (2)

Publication Number Publication Date
CN101187197A CN101187197A (en) 2008-05-28
CN100543232C true CN100543232C (en) 2009-09-23

Family

ID=39479779

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2007101924793A Expired - Fee Related CN100543232C (en) 2007-12-03 2007-12-03 Double-layer continuous girder bridge with steel-concrete composite structure

Country Status (1)

Country Link
CN (1) CN100543232C (en)

Families Citing this family (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535326A (en) * 2012-01-18 2012-07-04 中铁大桥勘测设计院集团有限公司 Double-layer highway bridge with integrated upper beam on frame mound and beam of polycarbonate (PC) continuous box girders
CN103741579A (en) * 2013-12-25 2014-04-23 广西科技大学 Corrugated steel web combination curve beam bridge with horizontal partition plates
CN104389267B (en) * 2014-11-20 2016-06-22 中铁工程设计咨询集团有限公司 Large-span suspension bridge stiff girder floorings
CN104929033A (en) * 2015-06-04 2015-09-23 长沙市规划设计院有限责任公司 Bridge structure similar to double-layer structure
CN105002817B (en) * 2015-08-04 2017-05-10 中铁第四勘察设计院集团有限公司 Prestressed concrete double-deck box girder bridge
CN106498842B (en) * 2016-12-19 2017-12-05 厦门市市政工程设计院有限公司 A kind of voluntarily axle beam and its method of construction under existing elevated bridge
CN107905084B (en) * 2017-12-12 2024-05-14 长沙市公路桥梁建设有限责任公司 RPC steel truss combined bridge deck and continuous beam bridge
CN109267439B (en) * 2018-11-02 2024-03-15 江苏沪宁钢机股份有限公司 Efficient and stable three-layer viaduct and construction process thereof
CN109371800A (en) * 2018-11-15 2019-02-22 莆田华侨中学 Human and vehicle shunting and sight seeing and pastime structural bridge
CN110904756B (en) * 2019-12-13 2021-08-03 华北水利水电大学 A construction method of a three-story bridge
JP2021139218A (en) * 2020-03-06 2021-09-16 エム・エムブリッジ株式会社 Steel floor slab and bridge
CN112878196A (en) * 2021-01-11 2021-06-01 中铁大桥局集团第一工程有限公司 Highway bridge deck construction method for highway and railway dual-purpose bridge
CN113293687B (en) * 2021-06-07 2024-12-10 北京市市政工程设计研究总院有限公司 A prefabricated pipe gallery cross-sea bridge
CN115369735B (en) * 2022-07-14 2024-10-29 重庆大学 Multilayer steel-concrete frame bridge for co-construction of mountain urban traffic and squares and construction method thereof

Also Published As

Publication number Publication date
CN101187197A (en) 2008-05-28

Similar Documents

Publication Publication Date Title
CN100543232C (en) Double-layer continuous girder bridge with steel-concrete composite structure
JP2022023107A (en) System for construction of complex u-shaped reinforcement beam bridge deck, and method thereof
CN113279324A (en) Semi-prefabricated UHPC-NC combined cover beam connecting structure and assembling method
CN107905084B (en) RPC steel truss combined bridge deck and continuous beam bridge
US20240200290A1 (en) Bridge girder with high central-wall-beam
Russell et al. Prefabricated bridge elements and systems in Japan and Europe
CN111455799A (en) Double-layer assembled viaduct and construction method thereof
CN215164570U (en) Ultra-wide bridge floor open-type light combined bridge floor special-shaped arch bridge
CN215405528U (en) Bridge structure suitable for asymmetric rotation
CN204370284U (en) A kind of automobile and light rail are with the intermediate deck arch bridge of layer
Siwowski et al. The recently built polish large arch bridges–A review of construction technology
CN113174839A (en) Ultra-wide bridge deck open type light combined bridge deck special-shaped arch bridge and construction method thereof
CN212801166U (en) Closed pedestrian bridge
CN215210482U (en) Pedestrian overpass and canopy structure attached to vehicle travelling bridge
CN207027858U (en) A kind of post stretching precast beam pedestal for being applicable different length and cross sectional shape
CN221218456U (en) Prefabricated assembled box girder structure of variable height
CN215629282U (en) Double-tower cable-stayed overpass
CN216074709U (en) Space double-helix steel structure bridge
CN205741869U (en) A kind of guy system overpass
CN222182939U (en) Bridge structure for cross intersection
RU2136802C1 (en) Megapolice ring highway and method for its reconstruction
Żółtowski et al. Recent steel structures in Poland–the selected projects
CN214939206U (en) Abutment structure with channel and bridge
CN217266879U (en) Gate-type pier viaduct
CN211665456U (en) Urban intersection pedestrian street crossing system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090923

Termination date: 20161203

CF01 Termination of patent right due to non-payment of annual fee