CN100363584C - Soft form and construction method for cast-in-situ concrete cavity floor utilizing soft form - Google Patents

Soft form and construction method for cast-in-situ concrete cavity floor utilizing soft form Download PDF

Info

Publication number
CN100363584C
CN100363584C CNB2005100371708A CN200510037170A CN100363584C CN 100363584 C CN100363584 C CN 100363584C CN B2005100371708 A CNB2005100371708 A CN B2005100371708A CN 200510037170 A CN200510037170 A CN 200510037170A CN 100363584 C CN100363584 C CN 100363584C
Authority
CN
China
Prior art keywords
soft form
soft
concrete
place
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2005100371708A
Other languages
Chinese (zh)
Other versions
CN1932214A (en
Inventor
傅礼铭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUBEI SYNTHETIC SPACE BUILDING TECHNOLOGY Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNB2005100371708A priority Critical patent/CN100363584C/en
Publication of CN1932214A publication Critical patent/CN1932214A/en
Application granted granted Critical
Publication of CN100363584C publication Critical patent/CN100363584C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The present invention relates to kind of flexible mould body. It includes a hollow cavity body and a first charging-discharging hole, in the first charging and discharging hole a first valve is set, and the hollow cavity body is prepared by using flexible material. Said invention also relates to a construction method for in-situ casting concrete hollow floor slab by using said flexible mould body. Said construction method includes the following several steps: (1), erecting and mounting form; (2), placing and binding form bottom steel bar; (3), placing flexible mould body; (4), placing and binding form top steel bar; (5), placing support and making the support be cover-mounted into the first charging-discharging hole of said flexible mould body; (6), charging gas or liquor into the flexible mould body and fixing said flexible mould body; (7), pouring and vibrating concrete and curing; (8), after the concrete is reached to a certain strength, discharging gas or liquor from flexible mould body interior and taking out the flexible mould body from the support place; and (9), pouring concrete into the support place so as to obtain the invented concrete hollow floor slab.

Description

Cassette ceiling is with the job practices of the hollow cast slab of soft form and utilizing soft carcass
[technical field]
The invention belongs to the hollow cast slab technical field, refer in particular to a kind of cassette ceiling with soft form and use the job practices of the hollow cast slab of this soft form.
[background technology]
Compare with structural systems such as common beam slab, ribbed slab floor, prestressing without bondn flat boards, hollow cast slab has plurality of advantages such as span is big, strong from the heavy and light shock resistance, soundproof effect is good, it also can reduce the quantity of reinforcement of floor, the use amount that reduces concrete, reduction of erection time etc. significantly and reduce the overall cost of building, so it is applied in construction construction of modern architecture more and more widely.On the original technical foundation of people, constantly improve the planform of hollow internal mold, to satisfy the needs that hollow cast slab is made.As State Intellectual Property Office on November 24th, 2004 disclosed application number be that 03118343.3 application for a patent for invention document promptly discloses a kind of hollow die for pouring concrete filling on site, this hollow matrix is formed with the hole of perforation in its main body, after it is applied to floor slab structure, concrete enters hole and forms Cast-in-place concrete post or pier, and plays the effect that improves the floor mechanical property; For another example State Intellectual Property Office on April 27th, 2005 disclosed application number be that 20031010101166.4 patent application document discloses a kind of Cavity structural member, this Cavity structural member is one by upper plate, the sidewall and the polyhedron Cavity structural member of going to the bottom and surrounding on every side, and it on the main body of Cavity structural member reinforce is set and reinforcement strengthens its bulk strength and rigidity.And aspect job practices, also improve, as State Intellectual Property Office on July 27th, 2005 disclosed application number be 200510031137.4 the application for a patent for invention document a kind of job practices of cast-in-situ reinforced concrete hollow slab is disclosed, its key step is as follows: (1) lays template; (2) reinforcing bar at the bottom of the placing plate; (3) unwrapping wire and installation internal mold; (4) the installing fixed support is connected and fixed reinforcing bar at the bottom of internal mold and the plate; (5) placing plate top reinforcing bar and connecting reinforcement; (6) pour concrete, maintenance.
The job practices of the hollow internal mold cast-in-place concrete cassette ceiling that above-mentioned document is related has the advantage of self, but it is the same with prior art, exist following defective: related hollow internal mold is all prepared by hard material, after cassette ceiling is made, hollow internal mold can not take out and reuse, and this certainly will increase the system engineering cost of cassette ceiling.So the job practices that a kind of reusable hollow internal mold need be provided and use the hollow cast slab of this hollow internal mold is arranged,, and satisfies the demand in market with the system engineering cost of reduction cassette ceiling.
[summary of the invention]
The object of the present invention is to provide a kind of reusable cassette ceiling soft form.
Another object of the present invention is to provide the job practices of the hollow cast slab of using above-mentioned reusable soft form, to reduce the system engineering cost of hollow cast slab.
The present invention realizes above-mentioned purpose by following technical solution:
A kind of cassette ceiling soft form, include that a cavity body and is arranged on this cavity body and first charge and discharge mouth with this cavity body connects, its for this cavity body charge and discharge gas/liquid provides passage, this first charges and discharge and is provided with one first valve in the mouth, it is used to seal or discharges the interior gas/liquid of this cavity body, and this cavity body is the soft material preparation.
The external surface of this soft form is a smooth outer surface, so that this soft form and concrete are separated.
The inner surface of the cavity body of this soft form is provided with a hose set, and this hose set is made up of at least one warp-wise flexible pipe and at least one broadwise flexible pipe, and radially flexible pipe and this broadwise flexible pipe connect each other for these; This hose set and one second charges and discharge mouthful to connect and is connected, and this second charges and discharge and mouthful be arranged at this and first charge and discharge in the mouth, is provided with one second valve in it.
Be provided with at least one drag-line flexible pipe in the cavity body of this soft form, an end of this drag-line flexible pipe second charges and discharge and mouthful is connected with this, and the other end is connected with this hose set perforation.
Connect between this hose set and be connected with at least one column flexible pipe, it can play the effect of the intensity that strengthens this soft form.
A kind of job practices of hollow cast slab of utilizing soft carcass, it includes following steps:
(1) formwork and mounting template;
(2) reinforcing bar at the bottom of placement and the colligation floor plate;
(3) place soft form;
(4) place also colligation floor plate top reinforcing bar;
(5) placing rack, and make this support be inserted in first of this soft form to charge and discharge mouth;
(6) soft form is charged gas or liquid, and fixing soft form;
(7) water and smash concrete and carry out maintenance;
(8) treat that concrete reaches certain intensity after, give off gas or liquid in the soft form, and take out soft form via the support place;
(9), form this Drawing-Core hollow cast slab at support place pour concrete.
In the above-mentioned job practices, before support place pour concrete, can place hush panel or reinforced mesh earlier in the internal stent lower end, and then pour concrete, this treatment step can prevent that concrete from entering the hollow parts of this cassette ceiling.
In the above-mentioned job practices, in the process of construction, can separate with concrete to help this soft form, thereby be convenient to the taking-up of this soft form at the coated one deck release agent of the external surface of soft form.
A kind of job practices of hollow cast slab of utilizing soft carcass, it includes following steps:
(1) formwork and mounting template;
(2) according to the storing position of the soft form planned in advance opening is set on template;
(3) corresponding opening placing rack;
(4) reinforcing bar at the bottom of placement and the colligation floor plate;
(5) place soft form, and make this support be inserted in first of this soft form to charge and discharge mouth;
(6) place also colligation floor plate top reinforcing bar;
(7) soft form is charged gas or liquid, and fixing soft form;
(8) water and smash concrete and carry out maintenance;
(9) treat that concrete reaches certain intensity after, give off gas or liquid in the soft form, and take out soft form via the support place;
(10), form this Drawing-Core hollow cast slab at support place pour concrete.
In the above-mentioned job practices, before support place pour concrete, can place hush panel or reinforced mesh and then pour concrete earlier at the support place.
In the above-mentioned job practices, in work progress, can separate with concrete to help this soft form, thereby be convenient to the taking-up of this soft form at the coated one deck release agent of the external surface of soft form.
Compared with prior art, beneficial effect of the present invention is: this soft form is the soft material preparation, and can charge and discharge gas or liquid, it is applied in the job practices of hollow cast slab, when making cassette ceiling, this soft form can charge gas or liquid and play the effect of hollow internal mold, after the cassette ceiling moulding, soft form gas inside or liquid are discharged, and via the set support place taking-up of this cassette ceiling, so reusable this soft form, thereby the system engineering cost of reduction cassette ceiling.
[description of drawings]
The present invention will be further described below in conjunction with drawings and Examples.
Fig. 1 is the schematic appearance of soft form of the present invention.
Fig. 2 is the cross-sectional schematic of soft form of the present invention.
Fig. 3 is the schematic appearance of another embodiment of soft form of the present invention.
Fig. 4 is the cross-sectional schematic of another embodiment of soft form of the present invention.
Fig. 5 is the schematic appearance of the tubulose soft form of soft form of the present invention.
Fig. 6 is the cross-sectional schematic of the tubulose soft form of soft form of the present invention.
Fig. 7 is the structural representation of the employed support of job practices of the hollow cast slab of utilizing soft carcass of the present invention.
Fig. 8 is the structural representation that is in the cassette ceiling in the manufacturing process of job practices of the hollow cast slab of utilizing soft carcass of the present invention.
Fig. 9 is the construction process figure of job practices of the hollow cast slab of utilizing soft carcass of the present invention.
Figure 10 is the structural representation that is in the cassette ceiling in the manufacturing process of another embodiment of job practices of the hollow cast slab of utilizing soft carcass of the present invention.
Figure 11 is the construction process figure of another embodiment of job practices of the hollow cast slab of utilizing soft carcass of the present invention.
[specific embodiment]
In the explanation of this specific embodiment, the shape of so-called soft form is meant that soft form is in the shape when charging gas or liquid condition.
Consult illustrated in figures 1 and 2ly, this soft form 10 includes that a cavity body 100 and is arranged on this cavity body 100 and first charges and discharge mouthfuls 110 with this cavity body 100 connects, and this first charges and discharge in mouthfuls 110 and be provided with one first valve 120.This cavity body 100 is to prepare such as soft materials such as flexible plastic, rubber coating clothes, more suitably be, this cavity body 100 and this first charge and discharge mouthfuls 110 both be smooth outer surface by the one-body molded external surface that should sky carcass 100 of soft material, when making cassette ceiling, it is fastening bonding that smooth external surface can avoid this soft form 10 and concrete to starch, thereby be convenient to take out after the cassette ceiling moulding this soft form 10; This first charge and discharge mouthfuls 110 for this cavity body 100 charge and discharge gas/liquid provides passage, this first valve 120 plays and discharges or seal the gas in this cavity body 100 or the effect of liquid.
The inner surface of the cavity body 100 of this soft form 10 is provided with hose set 130, and this hose set 130 is made up of at least one warp-wise flexible pipe 132 and at least one broadwise flexible pipe 134, and this warp-wise flexible pipe 132 connects each other with this broadwise flexible pipe 134.This hose set 130 and one is arranged at this and first charges and discharge second in mouthfuls 110 and charge and discharge mouthfuls 140 and connect and be connected, this second charge and discharge mouthfuls 140 for this hose set 130 charge and discharge gas/liquid provides passage, be provided with one second valve 150 in it, it is used to discharge/seal the gas/liquid in this hose set 130.
This cavity body 100 also is provided with at least one drag-line flexible pipe 160, one end of this drag-line flexible pipe 160 second charges and discharge mouthfuls 140 and is connected with this, the other end connects the effect that is connected this drag-line flexible pipe 160 with this hose set 130 two: when charging gas/liquid, can be embodied as this hose set 130 via this drag-line flexible pipe 160 and charge gas or liquid; After the cassette ceiling moulding and when taking out this soft form, but this this soft form 10 of drag-line flexible pipe 160 pull-ups is convenient to the disengaging of this soft form 10 and concrete.
When this soft form 10 is charged gas or liquid, can be earlier second charge and discharge mouthful 140 pairs of these hose set 130 and fill via this, and close this second valve 150 and seal gas or liquid in this hose set 130, and then first charge and discharge mouthful 110 pairs of these cavity body 100 and charge, and close this first valve 110 and seal gas or liquid in it via this.Be in when charging state, this hose set 130 is attached to the inner surface of this cavity body 100 crisscrossly, can increase the intensity of this soft form 10.
Consult Fig. 3 and shown in Figure 4, it is respectively schematic appearance and the cross-sectional schematic of another embodiment of soft form of the present invention.130 perforations of the hose set of this soft form 10 are connected with at least one column flexible pipe 170, and it cooperates with this hose set 130, play the effect that increases these soft form 10 intensity.The otherwise structure of this soft form is identical with the structure of the described soft form of a last embodiment.
Among above-mentioned two embodiment, soft form 10 is respectively spherical soft form and box-like soft form, this soft form can also be the soft form such as tubulose soft form regular shapes such as (with reference to figure 5 and shown in Figure 6), or erose soft form but apparently.
As shown in Figure 7, this support 20 is for having the tubular or the box-like frame members of the two ends perforation of sidewall 200 on every side, and its lower port extends internally and is formed with flange 210, and this flange 210 can be used for support hush panel or reinforced mesh.
In conjunction with Fig. 8 and shown in Figure 9, when utilization job practices of the present invention is made hollow cast slab, at first carry out formwork and mounting template 30 (step S100), this template 30 is fixed by supports support, and it can adopt timber shuttering, punching block or other composite shutterings.This template provides working platform for the making of hollow cast slab, and has stipulated the shape and the size of the cassette ceiling that will make simultaneously.
Place and colligation floor plate at the bottom of reinforcing bar 40 (step S101), when carrying out the arrangement of reinforcement of reinforcing bar and plate top reinforcing bar at the bottom of the plate, can carry out corresponding arrangement of reinforcement to the diverse location of cassette ceiling.
Place soft form 10 (step S102),, placement more accurate for the location that makes soft form operated more simple, in advance the position line of sign soft form on reinforcing bar at the bottom of soffit formwork or the plate.
Behind placement and colligation floor plate top reinforcing bar 50 (the step S103), put support 20, and make this support 20 be inserted in first of this soft form 10 to charge and discharge mouthful (a step S104), then this soft form 10 is charged gas or liquid, and fix this soft form 10 (step S105), the liquid that is charged can be water, oil, perhaps other liquid.The effect of this support 20 is to provide passage for the taking-up of soft form 10.
Water and smash concrete 60 and carry out maintenance (step S106), in watering the process of smashing concrete, note to prevent that the concrete slurry from flowing into this support 20, is not easy to the taking-up of this soft form 10 in order to avoid stop up this support 20.After treating that concrete reaches certain intensity, give off gas or liquid in the soft form 10, and take out soft form 10 (step S107) via support 20 places.After giving off the gas or liquid in the soft form 10, can pull first of this soft form 10 and charge and discharge mouth, this soft form 10 is separated with concrete 60, and take out via these support 20 places.For the ease of the disengaging of this soft form, in the process of construction, can be at the coated one deck release agent of the external surface of this soft form.
Place hush panel or reinforced mesh 70 in support 20 interior lower end, pour concrete (step 108) then, thus make this Drawing-Core hollow cast slab.Because this support 20 is less, also direct pour concrete and need not at support 20 places placement hush panel or reinforced mesh 70.
Consult Figure 10 and shown in Figure 11, with another embodiment of the job practices of hollow cast slab that utilizing soft carcass of the present invention is described.When making hollow cast slab, at first carry out formwork and mounting template 30 (step S200); Opening 80 (step S201) is set on template 30, this opening 80 is provided with according to the storing position of the soft form of being planned in advance, the quantity of the opening 80 of required setting determines that according to the quantity of the soft form of required placement a soft form need be provided with an opening; To should opening 80 placing racks 20 (step S202); Reinforcing bar 40 (step S203) at the bottom of placement and the colligation floor plate is placed soft form 10 (step S204) again, makes first of soft form 10 charge and discharge muzzle and goes into this support 20; Place and colligation floor plate top reinforcing bar 50 (step S205), then soft form 10 is charged gas or liquid, and fix this soft form 10 (step S206); Water and smash concrete 60 and carry out maintenance (step S207); After treating that concrete reaches certain intensity, give off gas or liquid in the soft form 10, and take out soft form 10 (step S208) via support 20 places; Place hush panel or reinforced mesh at support 20 places, pour concrete (step S209) then, thus make this Drawing-Core hollow cast slab.Other operations of present embodiment are identical with a last embodiment.

Claims (10)

1. cassette ceiling soft form, described soft form includes that a cavity body and is arranged on the described cavity body and first charges and discharge mouth with described cavity body connects, described first charges and discharge and is provided with one first air valve in the mouth, described cavity body is the soft material preparation, it is characterized in that: the inner surface of described cavity body is provided with a hose set, described hose set is made up of at least one warp-wise flexible pipe and at least one broadwise flexible pipe, and described warp-wise flexible pipe and described broadwise flexible pipe connect each other; Described hose set and one second charges and discharge mouthful to connect and is connected, and described second charges and discharge mouth is arranged at described first and charges and discharge in the mouth, is provided with one second air valve in it.
2. cassette ceiling soft form as claimed in claim 1 is characterized in that: the external surface of described soft form is a smooth outer surface.
3. cassette ceiling soft form as claimed in claim 1 or 2 is characterized in that: be provided with at least one drag-line flexible pipe in the described cavity body, an end of described drag-line flexible pipe and described second charges and discharge mouth and is connected, and the other end connects with described hose set and is connected.
4. cassette ceiling soft form as claimed in claim 3 is characterized in that: connect between described hose set and be connected with at least one column flexible pipe
5. a job practices of using cassette ceiling as claimed in claim 1 with the hollow cast slab of soft form is characterized in that described job practices comprises the steps:
(1) formwork and mounting template;
(2) reinforcing bar at the bottom of placement and the colligation floor plate;
(3) place soft form;
(4) place also colligation floor plate top reinforcing bar;
(5) placing rack, and make this support be inserted in first of this soft form to charge and discharge mouth;
(6) soft form is charged gas or liquid, and fixing soft form;
(7) water and smash concrete and carry out maintenance;
(8) treat that concrete reaches certain intensity after, give off gas or liquid in the soft form, and take out soft form via the support place;
(9), form this Drawing-Core hollow cast slab at support place pour concrete.
6. the job practices of the hollow cast slab of utilizing soft carcass as claimed in claim 5 is characterized in that: before support place pour concrete, place hush panel or reinforced mesh earlier in the internal stent lower end, and then pour concrete.
7. as the job practices of the hollow cast slab of claim 5 or 6 described utilizing soft carcasses, it is characterized in that: in work progress, at the coated one deck release agent of the external surface of soft form.
8. a job practices of using cassette ceiling as claimed in claim 1 with the hollow cast slab of soft form is characterized in that described job practices comprises the steps:
(1) formwork and mounting template;
(2) according to the storing position of the soft form planned in advance opening is set on template;
(3) corresponding opening placing rack;
(4) reinforcing bar at the bottom of placement and the colligation floor plate;
(5) place soft form, and make this support be inserted in first of this soft form to charge and discharge mouth;
(6) place also colligation floor plate top reinforcing bar;
(7) soft form is charged gas or liquid, and fixing soft form;
(8) water and smash concrete and carry out maintenance;
(9) treat that concrete reaches certain intensity after, give off gas or liquid in the soft form, and take out soft form via the support place;
(10), form this Drawing-Core hollow cast slab at support place pour concrete.
9. the job practices of the hollow cast slab of utilizing soft carcass as claimed in claim 8 is characterized in that: before support place pour concrete, place hush panel or reinforced mesh earlier at the support place, and then pour concrete.
10. the job practices of the hollow cast slab of utilizing soft carcass as claimed in claim 8 or 9 is characterized in that: in work progress, at the coated one deck release agent of the external surface of soft form.
CNB2005100371708A 2005-09-14 2005-09-14 Soft form and construction method for cast-in-situ concrete cavity floor utilizing soft form Expired - Fee Related CN100363584C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2005100371708A CN100363584C (en) 2005-09-14 2005-09-14 Soft form and construction method for cast-in-situ concrete cavity floor utilizing soft form

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2005100371708A CN100363584C (en) 2005-09-14 2005-09-14 Soft form and construction method for cast-in-situ concrete cavity floor utilizing soft form

Publications (2)

Publication Number Publication Date
CN1932214A CN1932214A (en) 2007-03-21
CN100363584C true CN100363584C (en) 2008-01-23

Family

ID=37878215

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2005100371708A Expired - Fee Related CN100363584C (en) 2005-09-14 2005-09-14 Soft form and construction method for cast-in-situ concrete cavity floor utilizing soft form

Country Status (1)

Country Link
CN (1) CN100363584C (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102358790B (en) * 2011-07-19 2012-10-31 李佃场 Filling core mould for hydraulic engineering
CN104847106A (en) * 2015-05-25 2015-08-19 赵启荣 Inflation die
CN108222496B (en) * 2016-12-21 2019-12-13 清华大学 A kind of flexible pouring formwork and construction method
CN112177317A (en) * 2020-09-30 2021-01-05 云南建投第五建设有限公司 Construction method for filling concrete by using detachable gas mold

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4060218A (en) * 1975-06-26 1977-11-29 Kandiah Tharma Nayagam Pneumatically controlled rigid core-former
CN87205722U (en) * 1987-04-02 1988-05-04 威海市水利勘测设计室 Combined inflatable inner mould in curved shape
CN2254921Y (en) * 1996-09-23 1997-05-28 戚志强 Flexiable mould for square buildings
JP2000257259A (en) * 1999-03-11 2000-09-19 Masatoshi Okura Sleeve forming tool
CN1555422A (en) * 2001-02-27 2004-12-15 诺兰达公司 Preparation of zinc oxide from complex sulfide concentrates using chloride processing
CN1644834A (en) * 2005-01-28 2005-07-27 刘国模 Construction of steel bar reinforced hollow concrete floor cast-in-situs
CN2723599Y (en) * 2004-08-28 2005-09-07 青岛吉尔工程橡胶有限公司 Irregular rubber inflation core mold
CN2823434Y (en) * 2005-09-14 2006-10-04 傅礼铭 Soft lineer for hollow floor slab

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4060218A (en) * 1975-06-26 1977-11-29 Kandiah Tharma Nayagam Pneumatically controlled rigid core-former
CN87205722U (en) * 1987-04-02 1988-05-04 威海市水利勘测设计室 Combined inflatable inner mould in curved shape
CN2254921Y (en) * 1996-09-23 1997-05-28 戚志强 Flexiable mould for square buildings
JP2000257259A (en) * 1999-03-11 2000-09-19 Masatoshi Okura Sleeve forming tool
CN1555422A (en) * 2001-02-27 2004-12-15 诺兰达公司 Preparation of zinc oxide from complex sulfide concentrates using chloride processing
CN2723599Y (en) * 2004-08-28 2005-09-07 青岛吉尔工程橡胶有限公司 Irregular rubber inflation core mold
CN1644834A (en) * 2005-01-28 2005-07-27 刘国模 Construction of steel bar reinforced hollow concrete floor cast-in-situs
CN2823434Y (en) * 2005-09-14 2006-10-04 傅礼铭 Soft lineer for hollow floor slab

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
充气橡胶芯模在空心梁预制中的应用. 李洪臣,李彦茹.水利科学与经济,第11卷第5期. 2005 *

Also Published As

Publication number Publication date
CN1932214A (en) 2007-03-21

Similar Documents

Publication Publication Date Title
CN100467810C (en) A component for forming holes in cast-in-place reinforced concrete
CN100363584C (en) Soft form and construction method for cast-in-situ concrete cavity floor utilizing soft form
CN100535309C (en) Hollow slab in reinforcing steel bar concrete
JP2021004516A (en) Method for constructing hollow structure
CN203080767U (en) Cast-in-situ densely-ribbed beam assembly box hollow floor
CN101319533A (en) Concrete pore-creating core component
CN101240569A (en) In-situ integrated placing construction method for aerated concrete wall
CN2823434Y (en) Soft lineer for hollow floor slab
CN110861190A (en) Component for placing air conditioner external unit and construction method
CN217998563U (en) Light high-strength hollow floor slab
CN100489238C (en) Hollow reinforced concrete slab
CN100458063C (en) Precast member for reinforcing bar concrete
CN101158201B (en) Cavity mould component
CN100458056C (en) Cast-in-situ concrete filled hollow mould and application thereof
CN112983087A (en) Construction method of silo structure
HK1263162A1 (en) Prefabricated bathroom and methods for constructing and installing the same
CN117188613A (en) A kind of European-style building top-loading construction method
CN101158202B (en) Cavity mould component
CN100469991C (en) A cavity formwork member
CN101240603B (en) Cast-in-situ concrete hollow slab
CN101187234B (en) In situ casting concrete hollow building board
CN101158192A (en) Cast-in-situs concrete hollow slab
CN101255742A (en) Cast-in-situ reinforcing concrete floor
CN101230652A (en) Cast-in-situs reinforcing wire concrete floor
CN101230651A (en) Cast-in-situs reinforcing wire concrete floor

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Hubei Synthetic Space Building Technology Co., Ltd.

Assignor: Fu Liming

Contract record no.: 2010420000050

Denomination of invention: Soft form and construction method for cast-in-situ concrete cavity floor utilizing soft form

Granted publication date: 20080123

License type: Exclusive License

Open date: 20070321

Record date: 20100510

ASS Succession or assignment of patent right

Owner name: HUBEI SYNTHETIC SPACE BUILDING TECHNOLOGY CO., LTD

Free format text: FORMER OWNER: FU LIMING

Effective date: 20120105

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 518023 SHENZHEN, GUANGDONG PROVINCE TO: 430074 WUHAN, HUBEI PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20120105

Address after: Luo East Lake Development Zone 430074 Hubei city of Wuhan Province Yu Road B Optics Valley International Plaza, No. 889 room 2401

Patentee after: Hubei Synthetic Space Building Technology Co., Ltd.

Address before: 518023 Luohu District, Guangdong, Baoan, North Road, talent market building

Patentee before: Fu Liming

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080123

Termination date: 20180914

CF01 Termination of patent right due to non-payment of annual fee