CN100354179C - Transverse peninsula type ship building method - Google Patents
Transverse peninsula type ship building method Download PDFInfo
- Publication number
- CN100354179C CN100354179C CNB2004100672221A CN200410067222A CN100354179C CN 100354179 C CN100354179 C CN 100354179C CN B2004100672221 A CNB2004100672221 A CN B2004100672221A CN 200410067222 A CN200410067222 A CN 200410067222A CN 100354179 C CN100354179 C CN 100354179C
- Authority
- CN
- China
- Prior art keywords
- ship
- dock
- peninsula
- hull
- stern
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Ship Loading And Unloading (AREA)
Abstract
本发明涉及一种横向半岛式造船方法,属于造船技术领域。该方法主要包括:根据船坞的宽度来划定后半艘船的建造长度,并确定搭载区域和分段数量;采用一台下小车为主钩,两台上小车为副钩来进行搭载方案;在船坞内进行分段或总段的吊装。船体上浮过程中,整艘船和后半艘船在船坞内同时起浮;起浮流程包括起浮,转向90度,移位,落墩。利用本方法可以充分利用船坞内单船建造后剩余的长度,显著提高船坞的利用率与效率。
The invention relates to a transverse peninsula shipbuilding method and belongs to the technical field of shipbuilding. The method mainly includes: delineating the construction length of the second half of the ship according to the width of the dock, and determining the loading area and the number of sections; using one lower trolley as the main hook, and two upper trolleys as auxiliary hooks to carry out the loading scheme; Carry out segmental or total segmental hoisting in the dock. During the floating process of the hull, the whole ship and the second half of the ship float in the dock at the same time; the floating process includes floating, turning 90 degrees, shifting, and dropping the pier. The method can make full use of the remaining length of a single ship in the dock after construction, and significantly improve the utilization rate and efficiency of the dock.
Description
技术领域technical field
本发明涉及一种造船方法,尤其涉及一种船坞内横向半岛式造船方法。The invention relates to a shipbuilding method, in particular to a transverse peninsula shipbuilding method in a dock.
背景技术Background technique
对于船厂来说,船坞是最核心的生产设施,提高船坞的利用率与效率就是提高船厂的造船吨位与效益。船坞的原始设计一般是根据某一船型的最大尺寸要求而设计制定的,在此船坞内只能建造一条船。For shipyards, the dock is the core production facility, and improving the utilization and efficiency of the dock means improving the shipbuilding tonnage and efficiency of the shipyard. The original design of the dock is generally designed and formulated according to the maximum size requirements of a certain ship type, and only one ship can be built in this dock.
要在一个船坞内制造两艘船,通常采用纵向半串联造船法,纵向半串联造船法是指一艘半船在一个船坞中建造时的方法是前后纵向布置,呈串联状态,也就是说,船坞在设计时考虑到最佳造船方法即成本最大利用率。对于纵向半串联造船法,半艘船无需在船坞内转向,只需纵向移位。但如果船坞的长度尺寸不能满足纵向半串联造船法串联制造两艘船的要求就不能采用该方法。如果要造较小的船舶,并且船坞内无法并行建造两艘船,也无法采用纵向半串联建造的情况下,就会浪费船坞内的空余面积。To manufacture two ships in one dock, the longitudinal semi-tandem shipbuilding method is usually adopted. The longitudinal semi-tandem shipbuilding method refers to the way that one and a half ships are built in a dock in a longitudinally arranged front and rear, in a series state, that is to say, Shipyards are designed taking into account the best shipbuilding methods, i.e. cost-maximizing utilization. For the longitudinal semi-tandem shipbuilding method, half the ship does not need to turn in the dock, but only needs to be shifted longitudinally. However, if the length dimension of the dock cannot meet the requirements of the longitudinal semi-tandem shipbuilding method to manufacture two ships in series, this method cannot be adopted. If a smaller ship is to be built, and two ships cannot be built in parallel in the dock, nor can the longitudinal semi-tandem construction be used, the vacant area in the dock will be wasted.
而采用横向半岛式造船法,要考虑到布置的半艘船舶长度能否起浮,也就是说要有一个或两个以上的压载舱,长度一定并满足起浮条件后,也只能对机舱区域搭载进行划分,一部分机舱分段只能在移位后再搭载,具有一定的技术难度。However, when adopting the transverse peninsula shipbuilding method, it is necessary to consider whether half the length of the ship arranged can float, that is to say, there must be one or more than two ballast tanks. The cabin area is divided, and some sections of the cabin can only be loaded after being displaced, which has certain technical difficulties.
发明内容Contents of the invention
本发明要解决的技术问题是提供一种横向半岛式造船方法,该方法在船坞内采用横向建造船舶,这样即使要造较小的船舶,并且船坞内无法并行建造两艘船,也无法采用纵向半串联建造的情况下,也不会浪费船坞内的空余面积,提高了船坞的利用率与效率。The technical problem to be solved by the present invention is to provide a horizontal peninsula shipbuilding method, which adopts horizontal construction of ships in the dock, so that even if smaller ships are to be built, and two ships cannot be built in parallel in the dock, vertical In the case of semi-tandem construction, the free area in the dock will not be wasted, which improves the utilization and efficiency of the dock.
为了解决上述技术问题,本发明将起浮流程由原来纵向半串联造船法的“起浮→移位→落墩”修改为“起浮→转向90度→移位→落墩”,该方法包括以下步骤:In order to solve the above-mentioned technical problems, the present invention modifies the floating process from the original longitudinal semi-tandem shipbuilding method "floating → shifting → pier falling" to "floating → turning 90 degrees → shifting → pier falling", the method includes The following steps:
a.根据船坞的宽度来划定艉段的建造长度,并确定搭载区域和分段数量;a. Delineate the construction length of the stern section according to the width of the dock, and determine the loading area and the number of sections;
b.在船坞内进行分段或总段的吊装;b. Carry out segmental or total segmental hoisting in the dock;
c.船体上浮过程中,整膄船和后半艘船起浮顺序为:整膄船先起浮,然后后半艘船起浮;c. During the floating process of the hull, the floating order of the whole boat and the second half boat is: the whole boat floats first, and then the second half boat floats;
d.在后半艘船的甲板、娓部平台、机舱平台上的四周安装临时带缆桩和导缆孔,并用钢丝绳与坞边的牵引小车、绞缆车连接,在船舶处于起浮状态时,四周与牵引小车、绞缆车连接的钢丝绳开始逐渐收紧,后半艘船起浮平稳后首先A、B点(第一牵引小车3、第一绞缆车4连接的点)二根钢丝绳收紧,让船舶靠近坞边的靠靶,然后,牵后半艘船牵着C点的牵引小车(第二牵引小车5)开始慢慢地朝坞门方向移动,反方向D点(第二绞缆车6牵引)的一根钢丝逐渐放松,围绕B点(绞缆车4所牵引的点)慢慢旋转,转30-50度后,用一艘拖轮来牵引后半艘船,然后再转成90度,后半艘船拖到位后,即可关闭闸门,然后用后半艘船四周的牵引小车和绞缆机来牵引,对后半艘船进行定位。d. Install temporary bollards and fairleads around the deck, the platform and the engine room platform of the second half of the ship, and use steel wire ropes to connect with the traction trolley and winch cable car near the dock. When the ship is in a floating state, The steel wire ropes connected with the traction trolley and winch cable car begin to tighten gradually. After the second half of the ship floats smoothly, the two steel wire ropes at points A and B (the point where the first traction trolley 3 and the first winch trolley 4 are connected) are tightened. Let the ship be close to the target on the side of the dock, and then, lead the rear half of the ship to the traction trolley (the second traction trolley 5) at point C and begin to slowly move towards the dock door, and point D in the opposite direction (the second winch cable car 6 A steel wire for traction) gradually relaxes, slowly rotates around point B (the point drawn by the winch cable car 4), and after turning 30-50 degrees, use a tugboat to pull the rear half of the ship, and then turn it into 90 degrees, After the second half of the ship is dragged in place, the gate can be closed, and then the latter half of the ship is towed with a traction trolley and a cable winch around it to locate the second half of the ship.
根据600吨行车的特点,横向建造法中的机舱区域总组分段的吊环位置,是以FR47号舱壁为底,作一等腰三角形,吊环布置在等腰三角形的顶点。分段是采用一台下小车为主钩,两台上小车为副钩来进行搭载方案。According to the characteristics of the 600-ton crane, the location of the hoisting rings in the general group of the engine room area in the transverse construction method is an isosceles triangle with the FR47 bulkhead as the base, and the hoisting rings are arranged at the vertices of the isosceles triangle. Segmentation is to use one lower trolley as the main hook, and two upper trolleys as auxiliary hooks to carry out the loading scheme.
为了保证整膄船出坞后,后半艘船能直接移到位,在整艘船未起浮前先做好后半艘船艉段的坞墩布置,并在后半艘船定位后,移除多余坞墩。这样就能使整个流程做到一气呵成,省去在整艘船出坞后,抽水,布置坞墩,放水,再进行后半艘船的转向、移动、定位。In order to ensure that the second half of the ship can be moved directly to its place after the whole ship is undocked, the pier layout of the second half of the ship’s stern section should be done before the whole ship is floated, and after the second half of the ship is positioned, remove it. Extra docks. In this way, the whole process can be achieved in one go, eliminating the need to pump water, arrange docks, release water, and then turn, move, and position the second half of the ship after the entire ship is undocked.
本发明提供的横向半岛式造船方法具有这样的有益效果,即充分利用了船坞内的剩余空间,并由于可以提前在船坞内进行分段,使每条船舶在船坞内的生产周期大幅度的缩短,显著提高了船厂的造船吨位与效益。The horizontal peninsula shipbuilding method provided by the present invention has the beneficial effect that the remaining space in the dock is fully utilized, and the production cycle of each ship in the dock is greatly shortened because it can be segmented in advance in the dock , Significantly increased the shipbuilding tonnage and benefits of the shipyard.
附图说明Description of drawings
图1是横向半岛式建造位置示意图。Figure 1 is a schematic diagram of the construction location of the horizontal peninsula.
图2是横向半岛式建造移位示意图。Figure 2 is a schematic diagram of the displacement of the horizontal peninsula type construction.
图3是101,102总段纵向建造吊环布置图。Fig. 3 is 101, 102 total section longitudinal construction suspension ring arrangement diagram.
图4是101,102总段横向建造吊环布置图。Fig. 4 is 101, 102 total section transverse construction hoisting ring arrangement diagrams.
图5是522/532横向建造吊马布置图。Fig. 5 is the layout drawing of 522/532 horizontal construction hoisting horses.
图6是522/532纵向建造吊马布置图。Fig. 6 is a layout diagram of the 522/532 longitudinal construction hoisting horse.
图7是后半艘船H1013散货船和整艘船H1010船艉部坞墩布置图Figure 7 is the layout of the rear half of the ship H1013 bulk carrier and the pier pier of the whole ship H1010
具体实施方式Detailed ways
下面结合附图与具体实施方式对本发明做进一步详细描述,如图1和图2所示,二号船坞尺度为360m×76m,整艘船H1010船(2),总长为288m,型宽51m,整艘船H1010船(2)的艏部与船坞的后壁间存在60m左右的长度。后半艘船H1013散货船(1)的主尺度为总长289m,型宽42m。Below in conjunction with accompanying drawing and specific embodiment the present invention is described in further detail, as shown in Figure 1 and Figure 2, No. two dock scale is 360m * 76m, and whole ship H1010 ship (2), total length is 288m, and width 51m, There is a length of about 60m between the bow of the whole ship H1010 ship (2) and the rear wall of the dock. The main dimensions of the second half ship H1013 bulk carrier (1) are 289m in overall length and 42m in molded width.
在制订起浮工艺前:Before formulating the flotation process:
1.通过对该散货船的起浮状态分析,在满足起浮的基本条件下,根据二号船坞的宽度76米来划定艉段的建造长度为68米,对角线为72米(旋转半径),也就是在二号船坞内采用横向建造17.5万吨后半艘船H1013船(1),并确定搭载区域和分段数量。1. Based on the analysis of the floating state of the bulk carrier, under the basic condition of floating, the construction length of the stern section is determined to be 68 meters according to the width of the No. 2 dock of 76 meters, and the diagonal line is 72 meters ( Radius of rotation), that is, to construct the 175,000-ton second-half ship H1013 ship (1) horizontally in the No. 2 dock, and determine the loading area and the number of sections.
2.对船舶在转向移位过程中,外形尺寸与船坞之间保持有一定的安全操作间距。在转向时,船体最大对角线尺寸必须小于船坞宽度加上船与坞壁的最小操作距离。2. During the process of steering and shifting of the ship, a certain safe operation distance is maintained between the external dimensions and the dock. When turning, the maximum diagonal dimension of the hull must be less than the width of the dock plus the minimum operating distance between the boat and the dock wall.
3.船体移位落墩的测量条件必须做好,包括起浮中的船体密性、压载平衡等。3. The measurement conditions for hull displacement and pier must be well established, including hull tightness and ballast balance during floating.
起浮工艺包括如下步骤:The flotation process includes the following steps:
1.起浮前,散货船的船体结构:机舱艉部与货舱区域分段装焊作业结束。1. Before floating, the hull structure of the bulk carrier: the segmental assembly and welding of the stern of the engine room and the cargo hold area is completed.
2.散货船艉段的前后临时水尺标志完成,船坞内原理论中心线和二条直剖线驳到主船体上,并作好标记,用激光仪把中心线驳到坞门上,作为艉段移位时使用,在船体的两侧和坞壁两侧作好肋骨定位标志。2. The front and rear temporary water gauge marks for the stern section of the bulk carrier are completed. The original theoretical centerline and two straight lines in the dock are barged to the main hull and marked, and the centerline is barged to the dock door with a laser device as the stern. It is used when the section is shifted, and the rib positioning marks are made on both sides of the hull and both sides of the dock wall.
3.所述散货船上的临时带缆桩和导缆孔安装到位,船体与坞壁之间设置靠把,所述散货船上的首端管弄及尾轴出口处的封板密封,并关闭有关阀门。根据起浮项目完整性确认表要求,对船体作一次全面的检查。为了防止管系和阀门等泄漏发生,准备快速水泥和抽水机等。3. The temporary bollards and fairleads on the bulk carrier are installed in place, a handle is provided between the hull and the dock wall, the head pipe lane on the bulk carrier and the sealing plate at the outlet of the stern shaft are sealed, and Close the relevant valve. Carry out a comprehensive inspection of the hull according to the requirements of the Flotation Project Integrity Confirmation Form. In order to prevent leakage of piping systems and valves, etc., prepare quick cement and water pumps, etc.
4.船体上浮过程中的起浮顺序为:整艘船H1010船(2)先起浮,吃水约3.51m,然后后半艘船H1013散货船(1)起浮,吃水约4.5m。如果艏艉产生倾斜时,吃水差大于0.5m,加压铁或压载水调整纵向平衡。横倾>50mm时,通过左右加压铁或压载水调整横向平衡;4. The floating sequence during the floating process of the hull is: the whole ship H1010 (2) floats first with a draft of about 3.51m, and then the second half of the ship H1013 bulk carrier (1) floats with a draft of about 4.5m. If the bow and stern tilt and the trim difference is greater than 0.5m, pressurize iron or ballast water to adjust the longitudinal balance. When the heel > 50mm, adjust the lateral balance by pressing iron or ballast water on the left and right;
5.在后半艘船H1013散货船(1)的甲板和艉部平台上的四周安装临时带缆桩和导缆孔,并用φ38mm钢丝绳与坞边的第一牵引小车(3)、第二牵引小车(5)、第一绞缆车(4)、第二绞缆车(6)连接,在船舶处于起浮状态时,四周与第一牵引小车(3)、第二牵引小车(5)、第一绞缆车(4)、第二绞缆车(6)连接的钢丝绳开始逐渐收紧,后半艘船H1013散货船(1)艉段起浮平稳后首先A、B点(第一牵引小车3、第一绞缆车4连接的点)连接的二根钢丝绳收紧,让船舶靠近坞边的靠靶,然后,牵着C点的第二牵引小车(5)开始慢慢地朝坞门方向移动,反方向第二绞缆车(6)连接的一根钢丝一点点放松,围绕B点(第一绞缆车4所牵引的点)慢慢旋转,转40度后,用一艘拖轮(7)来牵引后半艘船H1013散货船(1),再转50度。再移位220M,散货船艉段拖到位后,即可关闭闸门,然后用后半艘船H1013散货船(1)四周的牵引小车和绞缆机来牵引,对后半艘船H1013散货船(1)艉段进行定位。5. Install temporary bollards and fairleads around the deck and stern platform of the latter half of the ship H1013 bulk carrier (1), and use φ38mm steel wire ropes to connect with the first traction trolley (3) and the second Traction dolly (5), the first winch cable car (4), the second winch cable car (6) are connected, when ship is in floating state, around with the first traction dolly (3), the second traction dolly (5), the 2nd draw dolly (6) The wire ropes connected by the first winch cable car (4) and the second winch cable car (6) begin to tighten gradually, and after the stern section of the second half ship H1013 bulk carrier (1) floats smoothly, first points A and B (the first traction car 3 , the point that the first winch cable car 4 is connected) the two wire ropes that connect are tightened up, let the boats and ships approach the target near the dock, and then, the second traction trolley (5) that leads C point begins to slowly move toward the dock door direction , a steel wire connected by the second twisted cable car (6) in the opposite direction is loosened a little bit, slowly rotates around point B (the point pulled by the first twisted cable car 4), and after turning 40 degrees, use a tugboat (7) to Tow the latter half of the ship H1013 bulk carrier (1), and then turn 50 degrees. Move another 220M, and after the stern section of the bulk carrier is dragged in place, the gate can be closed, and then the traction trolley and cable winch around the second half of the ship H1013 bulk carrier (1) are used to pull, and the second half of the ship H1013 is scattered. The stern section of the cargo ship (1) is positioned.
6.船舶落墩前,要求艏艉吃水差小于150mm,横倾差小于40mm。船坞抽水时,船底离坐墩位置还差500mm时,暂停抽水。操作人员根据艉、舯激光位置立即将船拉正,确定船体位置正确后,立即抽水,直到坐墩结束。在船体落墩位后,对船体的基线再做一次检查,并重新确认中心线。6. Before the ship falls to the pier, the draft difference between bow and stern is required to be less than 150mm, and the heel difference is less than 40mm. When the dock is pumping water, when the bottom of the ship is 500mm away from the position of the pier, the pumping will be suspended. The operator straightens the boat immediately according to the position of the stern and midship lasers, and after confirming that the position of the hull is correct, immediately pumps water until the pier ends. After the hull falls to the pier, check the baseline of the hull again and reconfirm the centerline.
在船坞内进行分段或总段的吊装,吊环的设置是关键。由于600吨行车的三只吊钩是直线运行,一只下小车,二只上小车,无法象龙门高吊那样可旋转。For the hoisting of subsections or total sections in the dock, the setting of the hoisting ring is the key. Because the three hooks of the 600-ton crane run in a straight line, one gets off the trolley and the other two go on the trolley, which cannot be rotated like the gantry high crane.
在二号船坞内采用横向建造法,与纵向建造方法中的吊装方案是完全不同的。纵向建造方法如图3所示,如机舱区域101,102总组分段,纵向建造法的吊环是以距船舯第五号纵骨+200的构架位置线L5+200(12)为底边作~等腰三角形来布置,吊环布置在等腰三角形的顶点。而横向建造法如图4所示,横向建造法的101,102总组分段的吊环位置,是以FR47号舱壁隔舱(11)为底,作一等腰三角形,吊环布置在等腰三角形的顶点,并通过对总段的受力分析、来布置吊环(9、10)和选用吊环型号。The horizontal construction method used in the No. 2 dock is completely different from the hoisting scheme in the vertical construction method. The longitudinal construction method is shown in Figure 3. For example, the engine room areas 101 and 102 are divided into general groups, and the suspension ring of the longitudinal construction method is based on the frame position line L5+200 (12) which is at a distance from the fifth longitudinal in the midship + 200 (12). Arranged as an isosceles triangle, and the rings are arranged at the vertices of the isosceles triangle. The horizontal construction method is shown in Figure 4. The suspension ring positions of the 101 and 102 general group sections of the horizontal construction method are based on the FR47 bulkhead compartment (11), making an isosceles triangle, and the suspension rings are arranged on the isosceles The apex of the triangle, and through the force analysis of the total section, arrange the lifting rings (9, 10) and select the ring type.
但是此总段的吊装难点是钢丝绳的配置,根据6001吨行车的吊排特点,下小车吊排上的钢丝绳,按常规是无法直接与总段上8只B型吊环连接,因为8只吊环的布置成八字型。在本发明的实施过程中,须经过计算来配置下小车吊排的每组钢丝绳的长度,长度公差应控制在吊排所能调节平衡的范围之内,保证每只吊环受力均匀。However, the difficulty of hoisting in this general section is the configuration of the wire ropes. According to the characteristics of the hoisting row of the 6001-ton crane, the steel wire ropes on the lifting row of the lower trolley cannot be directly connected to the 8 B-shaped lifting rings on the general section as a rule, because the 8 lifting rings Arranged in a figure eight shape. In the implementation process of the present invention, the length of each group of steel wire ropes of the trolley suspension must be configured through calculation, and the length tolerance should be controlled within the range that the suspension can adjust the balance to ensure that each suspension ring is evenly stressed.
如图5所示,对于散货船横向建造中的521/31、522/32等分段,采用一台下小车(14)为主钩,2台上小车(13)为副钩来进行搭载方案。与纵向方式下的521/31、522/32等分段的吊装方案也是不同的,纵向建造如图6所示,是用2台上小车(13)为主钩,一台下小车(14)3号钩为副钩。As shown in Figure 5, for the 521/31, 522/32 and other segments in the transverse construction of bulk carriers, one lower trolley (14) is used as the main hook, and two upper trolleys (13) are used as auxiliary hooks for loading plan. It is also different from the segmental hoisting schemes of 521/31, 522/32 in the longitudinal mode. The longitudinal construction is shown in Figure 6, with two upper trolleys (13) as the main hook and one lower trolley (14) No. 3 hook is an auxiliary hook.
采用横向建造,对吊环布置的要求也就更高。在实际施工中,一只分段、总段的重心是由钢结构重量和舾装重量等合计而成。重心计算的误差,对2台上小车作主钩来吊分段或总段的话,可以用二只主钩中的任何一只吊钩来调整前后平衡。如果用一只吊钩作主钩来吊的话,就可能产生左右或前后无法达到平衡。With horizontal construction, the requirements for the arrangement of the lifting rings are also higher. In actual construction, the center of gravity of a segment and the total segment is formed by the sum of the weight of the steel structure and the weight of the outfitting. For the error of the calculation of the center of gravity, if the two upper trolleys are used as the main hook to hang the segment or the total segment, any one of the two main hooks can be used to adjust the front and rear balance. If a suspension hook is used as the main hook to hang, it may not be possible to achieve balance from left to right or from front to back.
二号船坞中,17.5万吨散货船横向搭载的31只分段中,需要调整吊环位置的,基本上与102总段、522/32总组分段相似。In the No. 2 dock, among the 31 sections of the 175,000-ton bulk carrier, the position of the lifting ring needs to be adjusted, which is basically similar to the 102 general section and the 522/32 general group section.
为了保证H1010船出坞后,H1013散货船能直接移到位,需要在主起浮前把散货船的坞墩根据施工时的《坞内分段搭载划线图》以及《坞墩布置图》布置好,如图7所示。为了保证散货船的坞内楞木水平符合要求,首先对H1010船的船底水平进行测量,所述船底水平是指船底外板基面中心线到坞底的垂直高度,测量公差±25mm,如超过此公差,船底1800mm的高度需要进行调整,重新设定一个水平高度。In order to ensure that the H1013 bulk carrier can be directly moved into place after the H1010 ship is undocked, the docking pier of the bulk carrier needs to be moved according to the "Sectional Loading and Marking Drawing in the Dock" and "Docking Pier Layout" before the main floatation. Arranged, as shown in Figure 7. In order to ensure that the corrugated wood level in the dock of the bulk carrier meets the requirements, first measure the bottom level of the H1010 ship. The bottom level refers to the vertical height from the center line of the base surface of the outer plate of the ship bottom to the bottom of the dock, and the measurement tolerance is ±25mm, such as If this tolerance is exceeded, the height of the bottom of the ship of 1800mm needs to be adjusted to reset a level.
对高度大于1800+25mm的坞墩在H1010船出坞时,一同拆除。如果此坞墩与散货船合用,就在此旁增加一只坞墩。Dock piers with a height greater than 1800+25mm shall be dismantled together when the H1010 ship is undocked. If this dock is used together with the bulk carrier, add a dock next to it.
Claims (8)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2004100672221A CN100354179C (en) | 2004-10-15 | 2004-10-15 | Transverse peninsula type ship building method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2004100672221A CN100354179C (en) | 2004-10-15 | 2004-10-15 | Transverse peninsula type ship building method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1760079A CN1760079A (en) | 2006-04-19 |
CN100354179C true CN100354179C (en) | 2007-12-12 |
Family
ID=36706334
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB2004100672221A Expired - Fee Related CN100354179C (en) | 2004-10-15 | 2004-10-15 | Transverse peninsula type ship building method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100354179C (en) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101987652B (en) * | 2009-08-07 | 2013-04-03 | 上海外高桥造船有限公司 | Ship block displacement method |
CN102092458A (en) * | 2009-12-09 | 2011-06-15 | 江苏新世纪造船有限公司 | In-dock super-large ship floating secondary positioning process |
CN104890834A (en) * | 2015-06-10 | 2015-09-09 | 上海船舶研究设计院 | Tail-wide-and-flat linear structure conductive to sitting on docking blocks |
CN107914841B (en) * | 2017-11-09 | 2023-05-09 | 江苏新扬子造船有限公司 | Dock gate underwater positioning and mounting device and method |
CN112093005A (en) * | 2020-08-10 | 2020-12-18 | 广州文冲船舶修造有限公司 | Pier arranging method for docking piers shared by multiple ships |
CN113942620A (en) * | 2021-10-27 | 2022-01-18 | 沪东中华造船(集团)有限公司 | A Ship Position Arrangement Method to Improve Dock Utilization Rate |
CN116443207A (en) * | 2023-04-24 | 2023-07-18 | 江南造船(集团)有限责任公司 | A method for carrying the general section of a liquefied gas carrier |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3955523A (en) * | 1974-03-20 | 1976-05-11 | Nippon Kokan Kabushiki Kaisha | Method of continuously building ships |
JPH06107274A (en) * | 1992-01-09 | 1994-04-19 | Metro Mach Corp | Double hull and its manufacture |
CN1131159C (en) * | 2001-03-08 | 2003-12-17 | 上海交通大学 | Secondary positioner for stern section in dock |
-
2004
- 2004-10-15 CN CNB2004100672221A patent/CN100354179C/en not_active Expired - Fee Related
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3955523A (en) * | 1974-03-20 | 1976-05-11 | Nippon Kokan Kabushiki Kaisha | Method of continuously building ships |
JPH06107274A (en) * | 1992-01-09 | 1994-04-19 | Metro Mach Corp | Double hull and its manufacture |
CN1131159C (en) * | 2001-03-08 | 2003-12-17 | 上海交通大学 | Secondary positioner for stern section in dock |
Also Published As
Publication number | Publication date |
---|---|
CN1760079A (en) | 2006-04-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101920766B (en) | A method of building a ship | |
CN101920771B (en) | A method for undocking and ballasting in shipbuilding | |
US10836459B2 (en) | Self-propelled integrated ship for transporting and installing immersed tubes of underwater tunnel and construction process | |
CN103112553B (en) | Self-propelled semi-submersible repair ship and its use | |
CN103991511B (en) | Platform conveying arrangement | |
JP2020513364A (en) | Self-propelled integrated vessel for transportation and installation of submerged tunnel submerged pipes | |
CN107905116A (en) | Construction method of large-span through type rigid tied steel arch bridge | |
CN110617945B (en) | Real sea area large scale ship model resistance test system | |
CN110877666A (en) | Self-propelled underwater tunnel immersed tube carrying and mounting integrated ship and construction process | |
CN107719580A (en) | A kind of horizontal building berth method on 10 ton ships | |
CN101850831A (en) | A hoisting method for the general section of the living area of a large-scale ocean-going offshore platform | |
CN101508327A (en) | Ro-ro passenger ship incline test method | |
CN103803036B (en) | Large ship utilizes the technique of water under air bag | |
CN206634166U (en) | A kind of working ship | |
CN100354179C (en) | Transverse peninsula type ship building method | |
WO2019000757A1 (en) | Method for adding water in vessel lightering | |
CN207045637U (en) | A kind of floating ship terminals | |
CN206141776U (en) | Large -scale component transportation of self -navigation formula installs integrative ship | |
CN201538941U (en) | Wharf flying bridge | |
CN111017130B (en) | Method for improving navigation capacity of ship lock | |
KR101654608B1 (en) | Semi-submergible rig and inclining test method thereof | |
CN111101515A (en) | Large-diameter single-pile floating transportation construction method | |
CN109080792A (en) | The stowage method of half ship not floating in a kind of dock | |
CN205396468U (en) | Special buoyancy formula lash of lockage | |
CN110356980B (en) | Novel integral platform hoisting launching method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20071212 Termination date: 20121015 |