BE834541A - SLAB IN VIBRATED CONCRETE, REINFORCED OR PRE-STRESSED, SERVING AS A COVER FOR A SHALLOW UNDERGROUND WORK - Google Patents

SLAB IN VIBRATED CONCRETE, REINFORCED OR PRE-STRESSED, SERVING AS A COVER FOR A SHALLOW UNDERGROUND WORK

Info

Publication number
BE834541A
BE834541A BE160963A BE160963A BE834541A BE 834541 A BE834541 A BE 834541A BE 160963 A BE160963 A BE 160963A BE 160963 A BE160963 A BE 160963A BE 834541 A BE834541 A BE 834541A
Authority
BE
Belgium
Prior art keywords
pipe
slab
concrete
emi
pipes
Prior art date
Application number
BE160963A
Other languages
French (fr)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to BE160963A priority Critical patent/BE834541A/en
Publication of BE834541A publication Critical patent/BE834541A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/005Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Description

       

  Dalle en béton vibré, armé ou précontraint, servant de

  
couverture pour un ouvrage souterrain 

  
peu profond.

  
L'invention a pour objet une dalle en béton vibré,

  
armé ou précontraint, servant de couverture pour un ouvrage

  
souterrain peu profond,réalisée à partir d'un chantier attenant

  
à l'ouvrage sans déranger la voierie qui surplombe la dalle,

  
et un procédé pour la construire.

  
Lorsqu'il s'agit de construire un ouvrage souterrain

  
comme un tunnel routier, une partie de métro, etc. on réalise

  
d'abord une dalle de couverture en dessous de laquelle on

  
creuse le tunnel proprement dit. Si l'ouvrage souterrain est peu profond on réalise habituellement la dalle de couver-  ture à partir de la surface, c'est-à-dire qu'on fait un déblai 

  
à ciel ouvert jusqu'au niveau inférieur de la dalle à construire, 

  
j on coule la dalle et l'on remblaie par dessus jusqu'au niveau  de la voierie initiale. 

  
 <EMI ID=1.1> 

  
qu'on éventre la voierie et perturbe la circulation en surface. 

  
 <EMI ID=2.1> 

  
une dalle en béton vibré, armé ou précontraint, servant de cou-  verture pour un ouvrage souterrain peu profond, à partir d'un  chantier attenant à l'ouvrage sans déranger la voierie qui  surplombe la dalle.

  
La dalle conforme à l'invention est constituée par  des tuyaux rigides jointifs, circulaires ou polygonaux, d'une longueur comprise avantageusement entre 30 et 100 m environ, alignés côte à cote en substance horizontalement à partir du chantier, et remplis comp lètement de béton vibré, armé ou précontraint, la distance entre la voierie intacte et la dalle étant

  
 <EMI ID=3.1> 

  
placer et les tuyaux étant mis en communication deux à deux à intervalles réguliers par des orifices coiitigus, de sorte que,

  
 <EMI ID=4.1> 

  
cevoir la conduite flexible d'une pompe à 'béton, l'extrémité

  
de cette conduite pouvant être introduite par l'orifice le plus éloigné du chantier dans le tuyau voisin, garni au préalable soit de cages d'armatures ou d'une poutrelle, soit de fils ou gaines de contrainte, puis le béton poussé dans ce dernier tuyau peut être vibré à travers les autres orifices par un homme qui se trouve dans le premier tuyau.

  
Suivant l'invention le chantier attenant à l'ouvrage est situé soit en dehors de la voierie, a la forme d'une tranchée ayant des dimensions tout juste suffisantes pour assurer l'accès

  
 <EMI ID=5.1> 

  
d'un pont mobile pour maintenir la libre circulation pendant les travaux.

  
Les tuyaux rigides jointifs, circulaires ou polygonaux de la dalle, sont en asbeste-ci.ment, métal, béton armé ou béton avec un. noyau métallique, ont un diamètre intérieur

  
 <EMI ID=6.1> 

  
des tuyaux jointifs ayant une longueur comprise entre 1 et 5 m.

  
L'invention concerne également un procédé de construction d'une dalle en béton vibré, armé ou précontraint, servant de couverture pour un ouvrage souterrain peu profond, à partir d'un chantier attenant à l'ouvrage sans déranger la voierie qui surplombe la dalle.

  
Suivant le procédé, on enfonce au moyen d'un vérin hydraulique à l'emplacement de la dalle à construire, en substan-

  
 <EMI ID=7.1> 

  
d'une rangée de tuyaux rigides jointifs, circulaires ou polygonaux , alignés côte à cote, les terres étant retirées de façon connue en soi lors de l'enfoncement des segments de sorte

  
que tous les tuyaux sont tous vides et ouverts à l'air libre du côté du chantier, on enfonce avec précision des cages d'armature ou une poutrelle dans le premier tuyau de la rangée au moyen d'un vérin hydraulique ou bien on fixe de façon classique dans ce tuyau des fils ou des gaines de contrainte, on fait amener par un homme la conduite flexible d'une pompe à béton dans le tuyau voisin jusqu'à ce que l'extrémité de la conduite passe dans le premier tuyau en traversant le dernier orifice de communication prévu dans les tuyaux et, tandis qu'on pousse le béton de l'arrière vers l'avant de sorte que le premier tuyau

  
se remplit complètement, l'homme placé dans le tuyau voisin introduit un vibrateur à aiguille successivement dans tous les autres orifices pour faire vibrer le béton, on remplit ensuite

  
le second tuyau à partir du troisième et ainsi de suite jusqu'à ce que tous les tuyaux soient remplis de béton vibré, armé ou précontraint, sauf le dernier, qui peut rester vide.

  
En effet, on peut toujours prévoir un tube supplémentaire qui ne fait pas partie intégrante de la dalle mais sert uniquement de couloir communicant pour le bétonnage du tuyau précédent. Bien entendu on remplit éventuellement le dernier tuyau soit de la façon classique, c'est-à-dire en le remplissant partiellement de béton et en achevant l'opération avec du mortier, soit en introduisant le béton à l'arrière du tuyau par un canal vertical qui traverse la voierie.

  
Il va de soi que le procédé décrit ne limite pas l'ordre de remplissage des tuyaux ni le nombre de tuyaux qu'il faut utiliser en même temps pour amener le béton au fond des tuyaux voisins à bétonner; dans certains cas particuliers

  
le nombre de tuyaux vides au terme du bétonnage suivant l'invention peut être supérieur à 1.

  
La dalle ayant été réalisée sans affecter la voierie

  
on peut évidemment aborder la construction de l'ouvrage souterrain proprement dit suivant les procédés classiques. Il y a lieu de remarquer que la résistance de la dalle dépend de la résistance du béton utilisé pour remplir les tuyaux ; la résistance de la dalle ne varie pas selon que les tuyaux sont solidarisés ou non et,en pratique,un interstice de 10 cm entre deux tuyaux voisins est parfaitement tolérable. Il suffit évidemment qu'on empêche que des matières meubles et de l'eau passe entre ces interstices, ce qu'on fait de façon connue en soi. 

  
Les dessins annexés représentent à titre d'exemple une  forme d'exécution de l'invention. 

  
La Fig.l représente en élévation une vue d'ensemble  d'un ouvrage souterrain peu profond à construire avec sa dalle de couverture déjà réalisée et le chantier attenant;

  
la Fig.2 est une coupe longitudinale suivant la

  
 <EMI ID=8.1> 

  
la Fig.3 est la coupe droite agrandie de deux tuyaux adjacents communicants de la Fig.2;

  
la Fig.4 est la coupe longitudinale d'un. segment élémentaire de tuyau vue au début du bétonnage et,

  
 <EMI ID=9.1> 

  
Conformément à l'invention, la dalle de couverture 1
(Fig.l) d'un ouvrage souterrain 2 peu profond est réalisée en dessous d'une voierie 3 d'une agglomération, cette voierie 

  
 <EMI ID=10.1> 

  
brisées les murs 4 et le sol ? de l'ouvrage à construire; 

  
 <EMI ID=11.1> 

  
 <EMI ID=12.1> 

  
 <EMI ID=13.1> 

  
sa section ABCD. Il peut être avantageusement un emplacement situé en contrebas de la voierie comme la bordure d'un jardin public, ou une tranchée creusée au voisinage de la voierie.

  
La dalle 1 est constituée par des tuyaux rigides T
(Fig.2) obtenus en mettant bout à bout des segments élémentaires S (Fig.4) dont la longueur varie habituellement entre 1 et 5 m.

  
Suivant l'invention on enfonce successivement les segments élémentaires au moyen d'un vérin hydraulique qui les pousse dans le sol tandis qu'on évacue les terres au fur et à mesure de l'avancement du travail, soit à la pelle, soit au moyen d'une machine à creuser du type à vis d'Arc&#65533;imède. 

  
 <EMI ID=14.1> 

  
que à l'endroit de la jonction pour éviter l'entrée de terre

  
de sorte que les tuyaux jointifs ainsi créés restent parfaitement vides. 

  
Comme on n'enfonce généralement pas les segments élémentaires de tous les tuyaux en même temps, il y a assez de place disponible sur le chantier pour entreposer non seulement une réserve de segments élémentaires, mais aussi des vérins hydrauliques et des éléments d'armature ainsi que des vibrateurs à aiguille destinés à faire vibrer le béton armé ou précontraint dont seront emplis les tuyaux.

  
Chaque segment élémentaire comporte, dans son plan

  
 <EMI ID=15.1> 

  
régulièrement tous les 2 ou 3 m, de sorte que chaque tuyau

  
vide de la dalle communique avec ses voisins; ces orifices ont avantageusement un diamètre de l'ordre de 0,15 à 0,20 m. Si l'on considère par exemple les premiers tuyaux Tl et T2 (Fig.2, 3)

  
de la rangée de tuyaux de la dalle à bétonner, on voit que les orifices Ul, U2 et U3 (Fig.3,4) de la série du côté gauche du tuyau Tl correspondent aux orifices du cote droit du tuyau T2, les orifices du côté droit du tuyau Tl étant obturés par le sol. Ceci est représenté à la figure 4 où le premier segment du tuyau Tl est obturé par le sol en X,les segments successifs du tuyau Jointif étant ajoutés au bout ouvert Y, et ainsi de suite. 

  
Pour constituer un tuyau en béton armé on enfonce

  
avec précision dans ce tuyau au moyen d'un vérin hydraulique soit des cages d'armature 7 élémentaires (Fig.3), soit des bouts

  
 <EMI ID=16.1> 

  
tuyau.

  
Suivant une forme d'exécution préférée de l'invention on garnit ainsi le premier tuyau Tl de la rangée (Fin.2). 

  
 <EMI ID=17.1> 

  
et gagne le fond de ce tuyau, bouché par le sol, tirant avec lui une conduite flexible raccordée à une pompe à béton stationnant en surface. Il fait passer le bout de cette conduite par les orifices contigus Ul (Fig.4) et l'on actionne la pompe; le béton se répand au fond du tuyau Tl et remplit progressivement ce dernier sans former de cavernes, le béton étant poussé dans le sens des flèches.

  
L'homme introduit un vibrateur à aiguille 11 dans l'orifice commun U2 et fait vibrer le béton dans la région avoisinante ; il bouche ensuite l'orifice et procède de même manière pour tous les autres orifices de sorte que le béton est vibré

  
sur toute la longueur du tuyau Tl.

  
On arme ensuite le tuyau T2 et on le bétonne avec vibration en utilisant le tuyau T3 comme couloir de travail. On peut bétonner ainsi tous les tuyaux de la rangée sauf le dernier. Si ce dernier, le tuyau Z&#65533;fait partie intégrante de la dalle

  
à construire, le bétonnage peut être effectué de façon classique, c'est-à-dire en poussant du béton depuis l'ouverture vers le

  
fond et en remplissant les vides restants au moyen de mortier;

  
ou bien on peut pousser le béton du fond vers l'avant, en utilisant un canal vertical qui traverse la voierie. Il y a

  
lieu de remarquer que le béton ne peut être vibré qu'en plaçant un homme en aval du courant de béton, l'homme reculant constamment vers la sortie du tuyau.

  
Ainsi qu'on l'a indiqué plus haut, on peut éviter

  
cet inconvénient en prévoyant un tuyau supplémentaire, après

  
le tuyau Z; comme ce dernier ne fait pas partie intégrante de

  
la dalle ce tuyau peut rester vide.

  
Si l'on désire que la dalle, ou une partie de celle-ci, soit en béton précontraint, on fixe de façon connue en soi des fils ou des gaines de contrainte, par exemple en ancrant ces éléments de contrainte dans le fond des tuyaux au moyen d'un bouchon en béton. '

  
On procède ensuite comme pour le béton armé vibré .

  
On a réalisé suivant l'invention une dalle expéri-

  
 <EMI ID=18.1> 

  
jointifs d'une longueur totale de 100 m. Les segments élémentaires avaient un diamètre intérieur de 1,20 m, un diamètre extérieur

  
de 1,33m et l'écartement moyen entre deux tuyaux voisins étant

  
de l'ordre de 0,10 m. Le niveau supérieur de la dalle se situait

  
à 1,20 cm en dessous de la voierie.

  
On a remarqué que le béton armé ainsi vibré suivant l'invention, avait une résistance exceptionnelle. Des essais isolés ont révélé que cette résistance est la plus grande quand l'armature du tuyau est une poutrelle (Fig.&#65533;); on pense que ce résultat provient de ce que la poutrelle, en se mettant à vibrer elle-même sous l'action indirecte de l'aiguille du vibrateur, accélère le processus de compaction du béton liquide.

  
D'autre part, la voierie sous laquelle la dalle expérimentale a été réalisée (la place Astrid à Anvers) n'a subi

  
aucune déformation.

  
On peut évidemment constituer des dalles de couverture dont les tuyaux ont une longueur supérieure à 100 m; il

  
suffit pour cela d'appliquer au béton la pression nécessaire

  
pour le pousser jusqu'au bout des tuyaux.

  
Bien entendu, l'invention n'est pas limitée à la formation d'exécution qui a été décrite et représentée à titre d'exemple et on ne sortirait pas de son cadre en y apportant

  
des modifications.

  
 <EMI ID=19.1>  

REVENDICATIONS 

  
L.- Dalle en béton vibré, armé ou précontraint, servant de couverture pour un ouvrage souterrain peu profond , réalisée à partir d'un chantier attenant à l'ouvrage sans déranger

  
la voierie qui surplombe la dalle, caractérisée en ce que celle- 

  
ci est constituée par des tuyaux rigides jointifs, circulaires 

  
ou polygonaux, d&#65533;une longueur comprise avantageusement entre 30 

  
et 100 m environ, alignés côte à côte en substance horizontale- 

  
ment à partir du chantier, et remplis complètement de-béton' 

  
vibré, armé ou précontraint, la distance entre la voierie in- 

  
 <EMI ID=20.1> 

  
intérieur de tels tuyaux étant suffisant pour permettre à des 

  
hommes de s'y déplacer et les tuyaux étant mis en communication 

  
deux à deux à intervalles réguliers par des orifices contigus, 

  
de sorte que, avant l'introduction du béton, un des tuyaux 

  
vides peut recevoir la conduite flexible d'une pompe à béton, 

  
l'extrémité de cette conduite pouvant être introduite par l'ori- 

  
fice le plus éloigné du chantier dans le tuyau voisin, garni 

  
au préalable soit de cages d'armatures ou d'une poutrelle, 

  
soit de fils ou gaines de contrainte, puis le béton poussé dans 

  
ce dernier tuyau peut être vibré à travers les autres orifices 

  
par un homme qui se trouve dans le premier tuyau.



  Vibrated concrete slab, reinforced or prestressed, serving as

  
cover for an underground structure

  
shallow.

  
The subject of the invention is a vibrated concrete slab,

  
reinforced or prestressed, serving as cover for a structure

  
shallow underground, made from an adjoining site

  
to the work without disturbing the road which overhangs the slab,

  
and a method for constructing it.

  
When it comes to building an underground structure

  
like a road tunnel, part of a metro, etc. we realize

  
first a cover slab below which we

  
dig the actual tunnel. If the underground structure is shallow, the roofing slab is usually made from the surface, that is to say, a cut is made.

  
open to the lower level of the slab to be built,

  
j we pour the slab and backfill over it to the level of the initial road.

  
 <EMI ID = 1.1>

  
that the roads are gutted and disrupted surface traffic.

  
 <EMI ID = 2.1>

  
a vibrated concrete slab, reinforced or prestressed, serving as roofing for a shallow underground structure, from a site adjoining the structure without disturbing the road which overhangs the slab.

  
The slab according to the invention is formed by joined rigid pipes, circular or polygonal, with a length advantageously between 30 and 100 m approximately, aligned side by side substantially horizontally from the site, and completely filled with concrete. vibrated, reinforced or prestressed, the distance between the intact roadway and the slab being

  
 <EMI ID = 3.1>

  
place and the pipes being put in communication two by two at regular intervals by adjacent orifices, so that,

  
 <EMI ID = 4.1>

  
consider the flexible pipe of a concrete pump, the end

  
of this pipe which can be introduced through the orifice furthest from the site into the neighboring pipe, lined beforehand either with reinforcing cages or a joist, or with stress wires or sheaths, then the concrete pushed into the latter pipe can be vibrated through the other holes by a man who sits in the first pipe.

  
According to the invention, the site adjoining the work is located either outside the road, has the shape of a trench having dimensions just sufficient to ensure access

  
 <EMI ID = 5.1>

  
a movable bridge to maintain free movement during the works.

  
The joined rigid pipes, circular or polygonal of the slab, are made of asbestos-ci.ment, metal, reinforced concrete or concrete with a. metal core, have an internal diameter

  
 <EMI ID = 6.1>

  
contiguous pipes having a length of between 1 and 5 m.

  
The invention also relates to a method of constructing a slab in vibrated, reinforced or prestressed concrete, serving as a cover for a shallow underground structure, from a site adjoining the structure without disturbing the road which overhangs the slab. .

  
According to the process, it is driven by means of a hydraulic cylinder at the location of the slab to be constructed, in substan-

  
 <EMI ID = 7.1>

  
a row of adjoining rigid pipes, circular or polygonal, aligned side by side, the earths being removed in a manner known per se when the segments are driven in so

  
that all the pipes are all empty and open to the air on the site side, reinforcing cages or a joist are inserted with precision into the first pipe of the row by means of a hydraulic cylinder or else fixed In the conventional way in this pipe, wires or stress sheaths, the flexible pipe of a concrete pump is brought by a man into the neighboring pipe until the end of the pipe passes through the first pipe while crossing the last communication hole provided in the pipes and, while pushing the concrete from the back to the front so that the first pipe

  
fills up completely, the man placed in the neighboring pipe introduces a needle vibrator successively into all the other openings to make the concrete vibrate, we then fill

  
the second pipe from the third and so on until all the pipes are filled with vibrated, reinforced or prestressed concrete, except the last, which can remain empty.

  
Indeed, one can always provide an additional tube which is not an integral part of the slab but serves only as a communicating corridor for the concreting of the previous pipe. Of course, the last pipe is possibly filled either in the conventional way, that is to say by partially filling it with concrete and completing the operation with mortar, or by introducing the concrete at the rear of the pipe by a vertical channel which crosses the road.

  
It goes without saying that the method described does not limit the order of filling of the pipes nor the number of pipes which must be used at the same time to bring the concrete to the bottom of the neighboring pipes to be concreted; in some special cases

  
the number of empty pipes at the end of the concreting according to the invention may be greater than 1.

  
The slab having been made without affecting the road

  
one can obviously approach the construction of the underground work itself according to the traditional methods. It should be noted that the strength of the slab depends on the strength of the concrete used to fill the pipes; the resistance of the slab does not vary depending on whether the pipes are joined or not and, in practice, a gap of 10 cm between two neighboring pipes is perfectly tolerable. Obviously, it suffices to prevent loose matter and water from passing between these interstices, which is done in a manner known per se.

  
The accompanying drawings show by way of example one embodiment of the invention.

  
The Fig.l shows in elevation an overview of a shallow underground structure to be built with its cover slab already completed and the adjoining site;

  
Fig. 2 is a longitudinal section along

  
 <EMI ID = 8.1>

  
Fig.3 is an enlarged cross section of two adjacent communicating pipes of Fig.2;

  
Fig.4 is the longitudinal section of a. elementary pipe segment seen at the start of concreting and,

  
 <EMI ID = 9.1>

  
According to the invention, the cover slab 1
(Fig.l) of a shallow underground structure 2 is carried out below a road 3 of an urban area, this road

  
 <EMI ID = 10.1>

  
broken the walls 4 and the floor? the work to be built;

  
 <EMI ID = 11.1>

  
 <EMI ID = 12.1>

  
 <EMI ID = 13.1>

  
its ABCD section. It can advantageously be a location located below the road, such as the edge of a public garden, or a trench dug in the vicinity of the road.

  
Slab 1 is made up of rigid pipes T
(Fig. 2) obtained by placing elementary segments S (Fig. 4) end to end, the length of which usually varies between 1 and 5 m.

  
According to the invention, the elementary segments are successively driven by means of a hydraulic cylinder which pushes them into the ground while the soil is removed as the work progresses, either with a shovel or by means of of an Arc screw type digging machine.

  
 <EMI ID = 14.1>

  
only at the junction to avoid the entry of earth

  
so that the joined pipes thus created remain perfectly empty.

  
As the elementary segments of all pipes are not generally driven in at the same time, there is enough room available on the job site to store not only a reserve of elementary segments, but also hydraulic cylinders and reinforcing elements as well. than needle vibrators intended to vibrate the reinforced or prestressed concrete with which the pipes will be filled.

  
Each elementary segment comprises, in its plane

  
 <EMI ID = 15.1>

  
regularly every 2 or 3 m, so that each pipe

  
empty slab communicates with its neighbors; these orifices advantageously have a diameter of the order of 0.15 to 0.20 m. If we consider for example the first pipes Tl and T2 (Fig. 2, 3)

  
of the row of pipes of the slab to be concreted, we see that the orifices Ul, U2 and U3 (Fig.3,4) of the series on the left side of the pipe Tl correspond to the orifices on the right side of the pipe T2, the orifices of the right side of the pipe Tl being closed by the ground. This is shown in Figure 4 where the first segment of the pipe Tl is closed by the ground in X, the successive segments of the jointed pipe being added to the open end Y, and so on.

  
To constitute a reinforced concrete pipe we push

  
with precision in this pipe by means of a hydraulic cylinder either elementary 7 reinforcement cages (Fig. 3), or ends

  
 <EMI ID = 16.1>

  
pipe.

  
According to a preferred embodiment of the invention, the first pipe Tl of the row (Fin.2) is thus lined.

  
 <EMI ID = 17.1>

  
and reaches the bottom of this pipe, blocked by the ground, pulling with it a flexible pipe connected to a concrete pump stationed on the surface. It passes the end of this pipe through the contiguous orifices Ul (Fig.4) and the pump is actuated; the concrete spreads to the bottom of the pipe Tl and gradually fills the latter without forming caverns, the concrete being pushed in the direction of the arrows.

  
The man introduces a needle vibrator 11 into the common orifice U2 and vibrates the concrete in the neighboring region; he then plugs the orifice and proceeds in the same way for all the other orifices so that the concrete is vibrated

  
over the entire length of the pipe Tl.

  
The T2 pipe is then armed and it is concreted with vibration using the T3 pipe as a working corridor. All the pipes in the row can be concreted in this way except the last one. If the latter, pipe Z &#65533; is an integral part of the slab

  
to be constructed, the concreting can be carried out in a conventional way, that is to say by pushing concrete from the opening towards the

  
melting and filling the remaining voids with mortar;

  
or we can push the concrete from the bottom forward, using a vertical channel that crosses the road. There is

  
It should be noted that concrete can only be vibrated by placing a man downstream of the concrete stream, the man constantly backing up towards the outlet of the pipe.

  
As indicated above, we can avoid

  
this disadvantage by providing an additional pipe, after

  
the Z pipe; as the latter is not an integral part of

  
the slab this pipe can remain empty.

  
If it is desired that the slab, or part of it, is made of prestressed concrete, wires or stress sheaths are fixed in a manner known per se, for example by anchoring these stress elements in the bottom of the pipes. by means of a concrete plug. '

  
We then proceed as for vibrated reinforced concrete.

  
An experimental slab was produced according to the invention.

  
 <EMI ID = 18.1>

  
contiguous with a total length of 100 m. The elementary segments had an internal diameter of 1.20 m, an external diameter

  
1.33m and the average spacing between two neighboring pipes being

  
of the order of 0.10 m. The upper level of the slab was

  
1.20 cm below the road.

  
It has been noted that the reinforced concrete thus vibrated according to the invention had exceptional resistance. Isolated tests have shown that this resistance is greatest when the reinforcement of the pipe is a joist (Fig. &#65533;); it is believed that this result comes from the fact that the joist, by starting to vibrate itself under the indirect action of the vibrator needle, accelerates the process of compaction of the liquid concrete.

  
On the other hand, the road under which the experimental slab was built (the Astrid square in Antwerp) did not undergo

  
no distortion.

  
It is obviously possible to form cover slabs with pipes having a length greater than 100 m; he

  
it suffices to apply the necessary pressure to the concrete

  
to push it to the end of the pipes.

  
Of course, the invention is not limited to the execution formation which has been described and shown by way of example and one would not depart from its scope by providing

  
modifications.

  
 <EMI ID = 19.1>

CLAIMS

  
L. - Vibrated concrete slab, reinforced or prestressed, serving as cover for a shallow underground structure, made from a site adjacent to the structure without disturbing

  
the road which overhangs the slab, characterized in that it

  
this is made up of joined rigid pipes, circular

  
or polygonal, with a length advantageously between 30

  
and about 100 m, aligned side by side essentially horizontal -

  
ment from the site, and completely filled with concrete '

  
vibrated, armed or prestressed, the distance between the

  
 <EMI ID = 20.1>

  
interior of such pipes being sufficient to allow

  
men to move there and the pipes being put in communication

  
two by two at regular intervals through contiguous orifices,

  
so that, before the concrete is introduced, one of the pipes

  
empty can accommodate the flexible pipe of a concrete pump,

  
the end of this pipe can be introduced through the ori-

  
fice furthest from the site in the neighboring pipe, lined

  
beforehand either reinforcement cages or a joist,

  
either wires or stress sheaths, then the concrete pushed into

  
this last pipe can be vibrated through the other holes

  
by a man who is in the first pipe.


    

Claims (1)

2.- Dalle suivant la revendication 1, caractérisée 2.- Slab according to claim 1, characterized en ce que le chantier attenant à l'ouvrage est situé en dehors in that the site adjoining the structure is located outside de la voierie,a la forme d'une tranchée ayant des dimensions tout of the road, has the shape of a trench having dimensions all juste suffisantes pour assurer l'accès à l'emplacement de la just sufficient to ensure access to the location of the dalle à construire et peut être recouvert d'un pont mobile pour slab to be built and can be covered with a movable bridge to maintenir la libre circulation pendant les travaux. maintain free movement during the works. 3.- Dalle suivant la revendication 1, caractérisée en 3.- Slab according to claim 1, characterized in ce que les tuyaux rigides jointifs, circulaires ou polygonaux, sont <EMI ID=21.1> <EMI ID=22.1> what the joined rigid pipes, circular or polygonal, are <EMI ID = 21.1> <EMI ID = 22.1> comprise entre 1 et 5 m. between 1 and 5 m. <EMI ID=23.1> <EMI ID = 23.1> vibré, armé ou précontraint, servant de couverture pour un vibrated, reinforced or prestressed, serving as a cover for a <EMI ID=24.1> <EMI ID = 24.1> <EMI ID=25.1> <EMI ID = 25.1> vant la revendication 1, caractérisé en ce qu'on enfonce au moyen d'un vérin hydraulique, à l'emplacement de la dalle à construire, en substance horizontalement, successivement les segments élémentaires d'une rangée de tuyaux rigides jointifs. circulaires ou polygonaux, alignés côte à côte, les terres Vant claim 1, characterized in that one pushes by means of a hydraulic cylinder, at the location of the slab to be constructed, substantially horizontally, successively the elementary segments of a row of adjoining rigid pipes. circular or polygonal, aligned side by side, the land étant retirées de façon connue en soi lors de l'enfoncement being withdrawn in a manner known per se during the depression des segments de sorte que tous les tuyaux sont tous vides et ou- verts à l'air libre du côté du chantier, on enfonce avec précision des cages d'armature ou une poutrelle dans le premier tuyau de la rangée au moyen d'un vérin hydraulique ou bien on fixe de façon classique dans ce tuyau des fils ou des gaines de contrainte, on fait amener par un homme la conduite flexible d'une pompe à béton dans le tuyau voisin jusqu'à ce que l'extrémité de la conduite passe dans le premier tuyau en traversant le dernier orifice de communication prévu dans les tuyaux et, tandis qu'on pousse le béton de l'arrière vers l'avant de sorte que le premier tuyau se remplit complètement, l'homme placé dans le tuyau voisin introduit un vibrateur à aiguille successivement dans tous les autres orifices pour faire vibrer le béton, segments so that all the pipes are all empty and open to the air on the construction site side, reinforcing cages or a joist are inserted with precision into the first pipe of the row by means of a jack hydraulic or else wires or stress sheaths are fixed in a conventional manner in this pipe, the flexible pipe of a concrete pump is brought by a man into the neighboring pipe until the end of the pipe passes in the first pipe by passing through the last communication hole provided in the pipes and, while pushing the concrete from the back to the front so that the first pipe fills up completely, the man placed in the neighboring pipe introduce a needle vibrator successively into all the other holes to vibrate the concrete, on remplit ensuite le second tuyau à partir du troisième et ainsi de suite jusqu'à ce que tous les tuyaux soient remplis de béton vibré, armé ou précontraint, sauf le dernier, qui peut rester vide. <EMI ID=26.1> the second pipe is then filled from the third and so on until all the pipes are filled with vibrated, reinforced or prestressed concrete, except the last, which can remain empty. <EMI ID = 26.1> qu'on remplit éventuellement le dernier tuyau soit de la façon classique, c'est-à-dire en le remplissant partiellement de béton et that the last pipe is possibly filled either in the conventional way, that is to say by partially filling it with concrete and <EMI ID=27.1> <EMI ID = 27.1> l'arrière du tuyau par un canal vertical qui traverse la voierie. the back of the pipe by a vertical channel which crosses the road. 6.- Dalle en béton armé ou précontraint, servant de couverture pour un ouvrage souterrain peu profond, réalisée à partir d'un chantier attenant à l'ouvrage sans déranger la voierie 6.- Reinforced or prestressed concrete slab, serving as a cover for a shallow underground structure, made from a site adjacent to the structure without disturbing the road qui surplombe la dalle, en substance comme décrit ci-dessus et représenté aux dessins annexés. which overhangs the slab, in substance as described above and shown in the accompanying drawings. 7.- Procédé de construction d'une dalle en béton vibré,armé ou précontraint, servant de couverture pour un ouvrage souterrain peu profond, à partir d'un chantier attenant à l'ouvrage sans déranger la voierie qui surplombe la dalle, en substance comme décrit ci-dessus. 7.- Construction process of a vibrated concrete slab, reinforced or prestressed, serving as a cover for a shallow underground structure, from a site adjoining the structure without disturbing the road that overhangs the slab, in substance as described above.
BE160963A 1975-10-15 1975-10-15 SLAB IN VIBRATED CONCRETE, REINFORCED OR PRE-STRESSED, SERVING AS A COVER FOR A SHALLOW UNDERGROUND WORK BE834541A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
BE160963A BE834541A (en) 1975-10-15 1975-10-15 SLAB IN VIBRATED CONCRETE, REINFORCED OR PRE-STRESSED, SERVING AS A COVER FOR A SHALLOW UNDERGROUND WORK

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
BE834541 1975-10-15
BE160963A BE834541A (en) 1975-10-15 1975-10-15 SLAB IN VIBRATED CONCRETE, REINFORCED OR PRE-STRESSED, SERVING AS A COVER FOR A SHALLOW UNDERGROUND WORK

Publications (1)

Publication Number Publication Date
BE834541A true BE834541A (en) 1976-04-15

Family

ID=25648894

Family Applications (1)

Application Number Title Priority Date Filing Date
BE160963A BE834541A (en) 1975-10-15 1975-10-15 SLAB IN VIBRATED CONCRETE, REINFORCED OR PRE-STRESSED, SERVING AS A COVER FOR A SHALLOW UNDERGROUND WORK

Country Status (1)

Country Link
BE (1) BE834541A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2482185A1 (en) * 1980-05-08 1981-11-13 Frankignoul Pieux Armes METHOD FOR CONSTRUCTING A UNDERGROUND WORK AND WORK SO OBTAINED

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2482185A1 (en) * 1980-05-08 1981-11-13 Frankignoul Pieux Armes METHOD FOR CONSTRUCTING A UNDERGROUND WORK AND WORK SO OBTAINED

Similar Documents

Publication Publication Date Title
EP1559847B1 (en) Tensioning element for the manufacturing of an anchoring
CH642416A5 (en) METHOD OF CONSTRUCTING UNDERGROUND WORKS WITH VERTICAL WALLS, DEVICE FOR EXECUTING THE METHOD AND UNDERGROUND WORK.
EP0102340A2 (en) Method of making reinforced concrete constructions such as subways, road tunnels and the like; prefabricated concrete elements for making such constructions
NL8503448A (en) METHOD FOR MANUFACTURING A RE-PRESSED CONCRETE CONCRETE POLE BY MOVING TUBES.
WO1986000358A1 (en) Method and equipement for making a rigid slab enabling to carry a building
FR2531733A1 (en) METHOD AND DEVICE FOR EXTRACTING A FORMWORK IN THE CONTEXT OF PRODUCING A MOLDED WALL IN THE GROUND
BE834541A (en) SLAB IN VIBRATED CONCRETE, REINFORCED OR PRE-STRESSED, SERVING AS A COVER FOR A SHALLOW UNDERGROUND WORK
CA1167650A (en) Building of an underground structure, and structure so produced
CH434335A (en) Method of construction of a passage under track and installation for the implementation of this method
FR2580011A1 (en) Method for building the foundations of a construction, formwork intended for the implementation of this method, and construction thus obtained
FR2824851A1 (en) PREFABRICATED BRIDGE SUPPORT
EP0242497A1 (en) Tunnel construction process
EP0931879A1 (en) Guardrail and method of construction
FR2724960A1 (en) Anchor for supporting cradle
WO1990001089A1 (en) Process for repairing foundations including damaged pile heads, in particular for timber piles
KR20190101001A (en) Temporary cip retaining wall construction method
BE864136A (en) METHOD AND DEVICE FOR CONSTRUCTION IN THE SOIL OF VERTICAL WALLS FROM AN UNDERGROUND DUCT
JP2984728B2 (en) Construction method of cast-in-place concrete pile
JP2657733B2 (en) Open shield method and open shield machine
FR2732714A1 (en) Reinforced concrete panel for making tank and esp. slurry pit
BE482679A (en)
JP2004308324A (en) Construction method for tunnel branch part
FR2483978A1 (en) Replacement of embankment side slope by retaining wall - entails placement of pile curtain on top line so that relieved wedge can be removed
CH478299A (en) Process for manufacturing a retaining wall using slabs and wall obtained by this process
JP2004183448A (en) Open shield method

Legal Events

Date Code Title Description
RE20 Patent expired

Owner name: CONSTRUCTIONS ET ENTREPRISES INDUSTRIELLES S.A.

Effective date: 19951015