Health Services Management Centre
CLINICAL MICROSYSTEMS: AN EVALUATION
Health Services Management Centre (HSMC),
School of Public Policy,
University of Birmingham
January 2007
Authors: Iestyn Williams, Helen Dickinson, Suzanne Robinson
CONTENTS
Executive Summary
iii
1. Introduction
1
2. Background and Literature
1
2.1 Clinical Microsystems
1
2.2 Approaches to Improvement and the Engagement of Staff
3
3. Aims and Objectives
7
4. Methodology
8
4.1 Realistic Evaluation
8
4.2 Case Study Methods
9
10
5. Findings
5.1 CMS Case Study Sites and Programmes
10
5.2 Implementation of CMS across Sample Sites
12
5.2.1 ‘People’
13
5.2.2 ‘Process’
13
5.2.3 ‘Patients’
14
5.2.4 ‘Patterns’ – Collection of Performance and Other Data
14
5.2.5 Summary
16
5.3 Perceived Benefits of CMS
16
5.3.1 Communication and Morale
17
5.3.2 Empowerment and Involvement
17
5.3.3 Self Awareness
18
5.3.4 Managing Change and Developing an Improvement Culture
18
5.3.5 Patient Benefits
19
5.4 Perceived Disbenefits of CMS
19
5.5 Key Features of CMS Implementation
20
5.5.1 ‘Small Steps’
20
5.5.2 Flexibility
20
5.5.3 CMS Resources
21
5.6 Implementation Enablers and Barriers
21
5.6.1 Leadership
21
5.6.2 Involvement
22
5.6.3 Levels of Support within the Host Organisation
23
5.6.4 Support from the Broader CMS Programme
23
5.6.5 Stable Environment
24
5.7 Succession and Sustainability
24
25
6. Discussion
6.1 CMS, Contexts and Outcomes
25
6.2 CMS and Local Improvement Capability
28
-i-
6.3 CMS and the Wider Organisational Studies Context
29
7. Conclusions
36
8. Recommendations
37
8.1 Recommendations for Programme Leaders (Preferably At National Level)
37
8.2 Recommendations at Microsystem Level
37
8.3 Recommendations at Organisational Level
38
9. References
39
Appendices: Case Study Reports
42
- ii -
EXECUTIVE SUMMARY
The commissioning specification for this project identified two primary aims:
•
•
To gain feedback on the developing role of CMS in the strategy for building local
improvement capability;
To derive specific learning as to the value of CMS in providing spread, sustainability
and service transformation in the NHS.
The project adopted a ‘realistic evaluation’ approach using case studies of CMS
implementers, each incorporating summative and formative aspects.
Case studies
included within the evaluation were drawn from three service improvement programmes
with overlapping timescales. Of the six case studies conducted:
•
Five had attended workshops introducing CMS and enabling experiences to be
•
shared with other CMS adopters;
•
change and improvement;
All six had established protected time to meet as a microsystem to identify areas for
Four reported having conducted a formal survey of microsystem members (although
•
not always using the CMS survey instrument);
•
further site had done this on a more ad hoc, opportunist basis;
•
using existing CMS tools);
Two had formally elicited the views and opinions of patients and service users and a
Five had taken time to map systems, processes and roles (although again not always
Only one of the six sites was able to make available data relating to patterns in
performance and/or activity.
The most common area of focus was on members of the microsystem – the ‘People’
dimension of the 5 Ps. The next most common activity involved adjustments to routine
systems and practices – the ‘Process’ component.
By comparison, the focus on
‘Patients’ had been relatively modest in most cases and very little data on ‘Patterns’ was
made available.
- iii -
Although the CMS ‘resource kit’ had relatively little impact or perceived use-value, a
number of other factors were seen as essential facilitators of effective implementation.
These were:
•
•
•
•
The emphasis on ‘small steps’ and the absence of ambitious aims and expectations;
Flexibility and a resulting sense of ownership and freedom from external monitoring
and sanction;
Internal leadership and the support of all members of the microsystem, and;
Support from within the host organisation and the CMS programme.
A number of benefits of implementing CMS were widely cited, including:
•
•
Improved communication, motivation and team morale;
•
initiatives;
•
•
Empowerment and involvement of individual team members in service improvement
Greater awareness of the service’s functions and individual roles in delivering these;
A shift in culture towards a more active approach to improvement, and;
A greater capacity to absorb and manage externally imposed change and upheaval.
Disbenefits identified by some respondents included:
•
•
The frustration of identifying problems that prove to be either irresolvable within the
microsystem or contrary to broader policy or directions of travel, and;
The time and capacity taken up in implementation of CMS.
Overall, based on the testimony of those involved in its implementation, there are clear
strengths of CMS as an approach to local service improvement. The flexibility of CMS
offers an implicit recognition that solutions cannot be universally applied or transferred
mechanistically across differing contexts. Given the multiplicity of ways in which CMS
may be interpreted, the question is not whether CMS ‘works’ as an improvement
methodology, but instead who it works for, when and how.
Some concerns were expressed about the sustainability or succession of developments
which had been achieved. These related to:
- iv -
•
Reliance on the leadership and efforts of a small number of individuals. For example,
in one site a key advocate had recently moved and this was seen as posing a threat
•
to continuation;
•
The absence of resources to support the process;
•
the CMS process, and;
The absence of a national profile to ensure host organisations facilitate and support
The build up of conflicting priorities and pressures.
Continuation will only occur when the approach is perceived as effective by those
engaged in the process and there is evidence demonstrating impact. Thus, there is an
important role for the measurement of the latter, not only within the individual application,
but for the future credibility of CMS as an approach within the NHS as a totality. This,
along with the need to place patients at the centre of the process, was the main area
identified as requiring of attention.
-v-
1. INTRODUCTION
This document reports findings from an evaluation of Clinical Microsystems (CMS) as an
approach to health services improvement. It begins with a brief description of CMS and
its location within a broader literature on improvement and performance. This is followed
by a discussion of the aims, objectives and methodology of the evaluation. Main findings
are then presented and key themes discussed in the light of broader organisational
studies literature. Finally, conclusions and a series of recommendations are provided.
2. BACKGROUND AND LITERATURE
2.1 Clinical Microsystems
Improvement is a broad term and may be interpreted in a number of ways, with a vast
literature which also incorporates discourses of change and organisational effectiveness.
Given the difficulties in gaining access to such a broad literature base, Goes et al (2000)
organise it along three dimensions: level of change (i.e. within the organisation or
industry); type of change (i.e. degree of change); and, mode of change (i.e. top-down or
bottom-up). Drawing on this literature within the context of healthcare, Ferlie and Shortell
(2001) focus on the level of change, suggesting four specific levels:
•
•
The individual;
•
The overall organisation; and
•
The group or team;
The larger system or environment in which individual organisations are
embedded.
Denis et al (1999) argue that operating units form the de facto elementary structures of
healthcare organisations – that is the level of the group or team. This concept has been
developed under the ‘microsystem’ label, and has emerged as a focus for clinical quality
improvement work (Institute of Medicine 2001, Nelson et al. 2002). Microsystems are the
smallest replicable unit within an organisation, having their own human, financial and
technological resources (Quinn, 1992). Ferlie and Shortell (2001) note that while the
potential of teams as a lever for change has been recognised for some time (Pettigrew et
-1-
al., 1992), the microsystem concept has emerged as the focus for much health quality
improvement work recently.
In a health care context, microsystems are the:
‘Small, functional, front-line units that provide most health care to most people.
They are the essential building blocks of larger organisations and of the health
system. They are the place where patients and providers meet. The quality and
value of care produced by a large health system can be no better than the services
generated by the small systems of which it is composed’. (Nelson et al., 2002:
473).
Thus, they are the building blocks of larger organisational forms. Microsystems have
‘clinical and business aims, linked processes, and a shared information environment, and
it produces performance outcomes’ (Nelson et al., 2002: 474). The clinical microsystems
approach involves having an in-depth understanding of the team and its associated
structures and processes, so that this might identify areas for action around improvement.
Much of the evaluation literature surrounding clinical microsystems has come from a US
context, where the Dartmouth Hitchcock Medical Centre has produced a series of nine
papers based almost exclusively on two studies. Nelson et al., (2002) reported a study of
20 high-performing clinical microsystems from across North America drawn from five
categories: primary care, specialty care, inpatient care, nursing home care, and home
health care.
The authors draw quite strong conclusions, particularly given that they
studied just 20 sites out of the ‘tens of thousands’ (Nelson et al., 2002: 486) of clinical
microsystems which operate across the US.
Nevertheless, they identify nine
characteristics of successful microsystems (2002: 485-6):
•
•
Leadership;
•
Culture;
•
Patient Focus;
•
Organisational support;
•
Staff focus;
Interdependence of care team;
-2-
•
•
•
Information and information technology;
Process improvement, and;
Performance patterns.
The study found substantial variation in the frequency with which each characteristic was
mentioned by interviewees from the microsystems, which suggested that the balance of
success characteristics differed across the five clinical settings.
The most highly rated characteristic was that of process improvement, which together
with the other characteristics is associated by the Dartmouth Hitchcock School with high
quality performance. However, there is little evidence of the effectiveness of the clinical
microsystems approach in the NHS available within the literature. Therefore a pilot to test
the clinical microsystems approach within this context was started in November 2003 with
eight teams spread across six different Strategic Health Authorities. There were mixed
responses within these pilots, with some teams embedding this as an improvement
approach, and others losing momentum with the process.
A further number of
programmes have extended the number of teams using this approach to around 100.
2.2 Approaches to improvement and the engagement of staff
In section 2.1 we outlined Ferlie and Shortell’s (2001) four levels of change (individual /
group or team / organisation / wider system). The authors also highlight the idea that
effective improvement must be successful at all these levels, and not just one or two.
Today the NHS is just over halfway through a ten-year programme which was formally
outlined in The NHS Plan (Secretary of State for Health, 2000).
Alongside
unprecedented investment in the NHS, the Labour government outlined the need for the
overhaul of the health system and to ensure that services are driven by cycles of
continuous improvement. Bate et al., (2004a: 8) estimate that just 15 to 20 per cent of
NHS staff are currently actively engaged in quality improvement work - yet in order to
achieve the goals set out in The NHS Plan, Bate and colleagues suggest that it will
require 80 or 100 per cent staff engagement.
Thus, ‘the next step of the NHS
modernisation journey is about making improvement mainstream; transforming patient
care by building improvement into everyday work at every level of the system’ (Bevan,
-3-
2004).
Therefore, the next step in terms of NHS improvement is about having
improvement embedded into the everyday activities of all staff.
Greenhalgh et al., (2004: 33) suggest, ‘the sheer size and complexity of the NHS mitigate
against the rapid and consistent introduction of improvements in service delivery and
organisation across the board’. Drawing on this concept, in the past, the strategy of the
Modernisation Agency (MA) tended to support change in a focused area, concentrating
on the spread and dissemination of learning in the hope of reaching a ‘tipping point’
(Gladwell, 2000) for catalysing positive change. The logic of the tipping point approach,
i.e. that by engaging a sufficient number of individuals this will produce wider change, is
broadly based on Everett Rogers’ (1995) theory of the ‘diffusion of innovation’.
The
central tenet of this theory is that the adoption of new ideas by a population follows a
predictable pattern. According to Rogers, the adopters of any new innovation or idea can
be categorised into
•
•
Innovators (2.5%);
•
Early majority (34%);
•
Early adopters (13.5%);
•
Late majority (34%); and,
Laggards.
The theory is based on a bell curve (see figure 1), which, when presented as a
cumulative distribution of a fixed population, is seen as an S-curve. Thus, essentially the
aim of the MA tended to concentrate on the innovators and the early adopters - in the
hope that they could encourage the rapid approach of the tipping point and disseminate
improvements throughout an entire population.
Figure 1: Bell curve and S-curve distributions
-4-
However, there are difficulties with this theory, not least a failure to consider the wider
institutional forces which may be acting upon individuals. Henrich (2001) suggests that
an R-shaped curve may actually be a more accurate reflection of diffusion, where it
occurs by a mimetic function, rather than the rational weighing up of costs and benefits.
In the transition period between the NHS Institute for Innovation and Improvement (NHS
III) superseding the MA in July 2005, it was suggested that improvement within the NHS
was not advancing quickly enough;
‘The picture painted is one of widespread, energetic (sometime almost frenetic)
improvement activity at project team level but limited strategic co-ordination and
purposeful direction at the level of the organisation. Furthermore, the prevalence
style of project leaders is ‘pragmatic activism’. NHS improvement work is typically
under conceptualised and often lacks reflection and analysis’ (Bate et al., 2004a: 8).
Bevan (2004) added that, ‘a plethora of small projects do not typically scale up to whole
organisation change’. Thus, in the transition to the NHS III, it was recognised that a
larger proportion of individual staff members needed to be involved in the improvement
process. As was earlier suggested, improvement is seen as requiring all – or nearly all –
staff members to be engaged within this process. Thus, the NHS III suggests that more
widespread engagement by staff members of all levels will more effectively embed
continuous improvement processes within the NHS.
The theory underpinning widespread staff engagement relates to that of the social
movements literature (Bate et al. 2004a, Bate et al. 2004b). Social movements theory is
thought to be useful to the NHS in mobilising staff members around ‘theoretical ideas’ or
aspirations. Examples of these kinds of ideas or aspirations are ‘there are no avoidable
deaths’, ‘care is given in the right place at the right time’ and ‘different organisations’
leaders trust each other’ (Bate et al., 2004a: 45).
In other words, individuals are
mobilised into action by appealing to emotional, social and relational, rather than simply
technical or normative factors.
In essence the aims look very similar to taking an
outcomes-orientated approach to service provision (Ball et al., 2004).
This view of
improvement removes the focus from the traditional structures for service delivery,
encouraging managers and clinicians to think about different ways of delivering services.
-5-
An approach derived from social movements theory also shifts the locus of change from a
top-down to a bottom-up grassroots approach; that is, change is not imposed on
individuals and organisations, but rather is formed and owned by the individuals charged
with implementation.
In this sense, the concept of clinical microsystems is entirely
consistent with the agenda laid out by the NHS III.
-6-
3. AIMS AND OBJECTIVES
The commissioning specification for this project identified two primary aims:
•
•
To gain feedback on the developing role of CMS in the strategy for building
local improvement capability, and;
To derive specific learning as to the value of CMS in providing spread,
sustainability and service transformation in the NHS.
These over-arching aims were addressed via a number of key evaluation questions:
•
•
What are the measurable outcomes of the CMS approach?
What are the perceptions of those involved of the benefits and disbenefits of
the approach?
•
•
How has implementation of the CMS approach proceeded?
How does the CMS approach sit within or alongside other service
improvement programmes at local levels?
•
What key roles or functions are required within and outside of microsystems
in order to achieve maximum impact?
•
How can the CMS approach be developed to become an integral
component of strategies for building local improvement capability?
-7-
4. METHODOLOGY
4.1 Realistic evaluation
The project adopted a ‘realistic evaluation’ approach. The major proponents of realistic
evaluation are Pawson and Tilley, who argue that there is an inadequate understanding
of why programmes work within evaluation. The equation below demonstrates how
outcomes of an evaluation are produced from a realistic evaluation perspective (Pawson
& Tilley, 1998).
(C) Context + (M) Mechanism = (O) Outcome
No individual-level intervention works for everyone, and no institution-level intervention
works everywhere. Realistic evaluation seeks to discover what mechanisms work for
whom, and within which contexts. Programmes are always introduced into pre-existing
social conditions, and so the evaluator needs to investigate the extent to which these
conditions enable or disable the intended mechanism of change. ‘The task of a realist
evaluation is to find ways of identifying, articulating, testing and refining conjectured CMO
configurations’ (Pawson & Tilley, 1998: 77). The ultimate goal is to identify regularities of
context, mechanism and outcome within social programmes. Thus, realistic evaluation
aims to open up the ‘black box’ of evaluation and examine why it is that programmes
have particular effects, and how these may be transferred to other contexts.
The evaluation included both summative and formative aspects. In order to meet the
objectives set out above the evaluation adopted a case study approach, for the following
reasons:
•
It is important to recognise local contexts and the contingency of service
improvement initiatives. A case study approach seeks to locate evaluation
findings within the immediate context from which these emerge and
identifies key factors which determine the transferability of developments to
other contexts.
•
A case study approach also enables the combining and triangulating of data
collection methods to achieve a richer and more refined picture.
-8-
4.2 Case Study Methods
In accordance with the commissioner’s specification there was an initial period in which
discussions took place between the HSMC team, the commissioning body and other
interested parties with the aim of finalising the process and scope of the evaluation. This
helped the HSMC team to identify the types of summative data which might be available
and to establish the scope for reporting on quantitative outcomes. Following this, the
HSMC team established criteria for purposively selecting a sample of case study
organisations. These were chosen to include:
•
Teams of different size – ranging from relatively small (e.g. six members) to
those with upwards of 25 members;
•
•
Coverage of primary, secondary and intermediate care, and;
Where possible, a mixture of sites reporting positive and less positive
experiences of implementing CMS.
Within four of the six case studies, face-to-face semi-structured interviews were
conducted with key figures in the CMS projects including practitioners, managers and
other staff. Interviews were tape-recorded in all instances.
In the two remaining case
studies, tape-recorded group discussions were preferred to interviews at the request of
respondents. There were six case studies in total and an average of four respondents
within each case study.
Interviews and group discussion were used to explore the
perceptions and opinions of those involved, enabling multiple perspectives to be brought
to bear on the topic of CMS.
The evaluation also intended to include outcome data made available by participating
case study sites for analysis, and to identify trends and themes from across the case
study sites. Similar HSMC evaluations have used outcome data collected by case study
sites to explore issues of efficiency, quality of service delivery and long term sustainability
(see for example McLeod et al., 2006).
-9-
5. FINDINGS
5.1 CMS case study sites and programmes
Case studies included within the evaluation were drawn from three service improvement
programmes. Three of the sites were drawn from the (then) North and East Yorkshire
and Northern Lincolnshire Strategic Health Authority CMS Programme which recruited
three waves of CMS implementers between October 2004 and January 2005. Each of
these was offered the opportunity to participate in a six-month programme of six-weekly
meetings which had the objectives of understanding the CMS approach and sharing
learning.
Specific coaching support was also offered as part of the programme and
senior management support for implementation was a precondition of recruitment. Two
case study teams had become involved as part of the North and East Yorkshire and
Northern Lincolnshire Cardiac Network CMS programme which was structured in a
similar way with equivalent support and which ‘went live’ in July 2005. The sixth case
study team adopted CMS as a means for delivering the Royal College of
Nurses/Department of Health programme for Improving Cleanliness in Hospitals which
began in April 2005. As such this team had comparatively less specialist CMS support
and expertise made available to it.
Key features of each case study site are described below. More detail is contained in the
appended site reports.
Team:
West Hull Primary Care Trust: Sexual & Reproductive Health
care Network. Genito-Urinary clinic
Size of microsystem:
Approx 25.
Involvement in CMS:
North and East Yorkshire and Northern Lincolnshire Strategic
Health Authority’s CMS programme - joined between October 2004
and January 2005.
Assessment tools:
Staff survey, incremental assessment of patient satisfaction,
analysis of processes.
Activities:
Regular meetings, changes to roles and processes.
Outcomes:
Shift towards nurse-led services, training and expanded roles for
nurses, changed role for clinicians, discontinuation of inefficient
services, introduction of nurses station and patient self-triage, staff
reward schemes.
- 10 -
Current status of CMS:
Integrated into team working, some concerns at resurfacing of
previous cultures and practices, plans for further development using
CMS.
Team:
Occupational Therapy, Hambleton & Richmondshire PCT
Size of microsystem:
Approx 20.
Involvement in CMS:
North and East Yorkshire and Northern Lincolnshire Strategic
Health Authority’s CMS programme - joined between October 2004
and January 2005.
Assessment tools:
Staff survey.
Activities:
Team building and six weekly CMS meetings.
Outcomes:
Improved communication and team morale.
Current status of CMS:
Some loss of momentum due to capacity pressures and external
changes, reliance on key individuals to sustain.
Team:
Beverly Integrated Community Mental Health Team
Size of microsystem:
Approx 30 members.
Involvement in CMS:
North and East Yorkshire and Northern Lincolnshire Strategic
Health Authority’s CMS programme - joined between October 2004
and January 2005.
Assessment tools:
Survey of staff, process-mapping.
Activities:
Monthly
meetings,
team-building,
changes
to
systems
and
processes.
Outcomes:
Changes to assessment and duty systems, tackling referral
patterns, designating central staff meeting place, Implementation of
peer supervision.
Current status of CMS:
Discontinued.
Team:
North Lincolnshire & Goole Hospitals NHS Trust:
Cardiac
Rehabilitation (CR) Team
Size of microsystem:
6 members.
Involvement in CMS:
North and East Yorkshire and Northern Lincolnshire Cardiac
Network CMS Programme – joined July 2005.
Assessment tools:
Staff survey, process-mapping.
Activities:
Regular meetings and adjustments to working practices.
- 11 -
Outcomes:
Improved communication and team morale, addition of annual ‘decluttering’ of offices, introduction of ‘discovery interviews’ and use of
staff notice-board.
Current status of CMS:
Integrated into team-working, expected to continue regardless of
personnel changes.
Teams:
Surgical and medical wards, Epsom and St Helier Hospitals
Size of microsystem:
Approx 12.
Involvement in CMS:
Six month pilot as part of Royal College of Nursing clinical
leadership team programme using CMS to deliver cleaner hospitals
– joined between April and September 2005.
Assessment tools:
Patients satisfaction questionnaire and process mapping.
Activities:
Regular CMS meetings, team building, changes to working
practices.
Outcomes:
Production of a bed hanger, introduction of ‘ideas board’.
Current status of CMS:
Some changes are now integrated into cultures of practice, future
progression threatened by lack of resources and support.
Team:
North Yorkshire Smoking Cessation Service
Size of microsystem:
Approx 12.
Involvement in CMS:
North and East Yorkshire and Northern Lincolnshire Cardiac
Network CMS Programme – joined July 2005.
Assessment tools:
Staff survey, patient survey, analysis of patterns of referral.
Activities:
Meetings, changes to processes and practices, virtual online noticeboard.
Outcomes:
Improvements to morale and empowerment of team members.
Current status of CMS:
Ongoing.
5.2 Implementation of CMS across sample sites
The clinical microsystem approach to improvement begins with an assessment phase
which takes in: the views, attitudes and opinions of all members of the microsystem; the
characteristics and needs of the patient population served; the internal processes that
underpin their current way of working, and; their patterns of performance and activity
(NHS III, 2006).
- 12 -
Of the six case studies:
•
•
Five had attended workshops introducing CMS and enabling experiences to
be shared with other CMS adopters;
All six had established protected time to meet as a microsystem to identify
•
areas for change and improvement;
•
(although not always using the CMS survey instrument);
•
users and a further site had done this on a more ad hoc, opportunist basis;
•
not always using existing CMS tools), and;
Four reported having conducted a formal survey of microsystem members
Two had formally elicited the views and opinions of patients and service
Five had taken time to map systems, processes and roles (although again
Only one of the six sites was able to make data available data relating to
patterns in performance and/or activity.
5.2.1 ‘People’
The most common area of focus was on members of the microsystem. As a result, staff
well-being and communication between team members became the focus of much early
work. Most commonly this involved:
•
Setting up communication mechanisms such as regular meetings and
•
notice-boards;
•
acknowledgement of areas of strength and good practice, and;
Implementing reward schemes such as ‘employee of the month’ and explicit
Active involvement of those occupational groups traditionally less involved
with service improvement such as administrative support and lower grade
nurses.
5.2.2 ‘Process’
The next most common activity involved adjustments to routine systems and practices.
These included:
- 13 -
•
•
Withdrawal of unnecessary or inefficient stages in the patient pathway;
Addition of stages in the patient pathway – for example in assessment and
•
triage;
•
and;
Realignment of staff workload in light of information about referral rates,
Training and expansion of roles of team members.
5.2.3 ‘Patients’
Many of the sites indicated adoption of an ordinal approach to CMS implementation.
Typically this involved focussing on patient experience after staff surveys and process
mapping had been conducted.
Three sites reported collecting some patient data or
having elicited patient views.
A ‘How was your stay?’ questionnaire was given to
inpatients at the Epsom & St Helier sites. This project demonstrated patient involvement
at a variety of stages and respondents cited this as a significant factor in progress
achieved. The smoking cessation clinic conducted patient questionnaires assessing the
service and this resulted in changes to the level of supporting information included when
making appointments. The team also planned to conduct qualitative research in order to
better understand what motivates patients to use the service, and any changes that they
might make to prove more accessible. The other three case study sites indicated that the
patient population served was an intended area of future focus.
5.2.4 ‘Patterns’ – collection of performance and other data
The evaluation indicated a paucity of routine data collection relating to service activity and
outcomes, both prior to and during the period of CMS implementation.
Representatives
from each of the six pilot sites were requested to supply data on:
•
Effects on productivity, including for example patient outcomes or raised
•
activity levels;
•
and/or resources, and;
Effects on efficiency, for example including impact on patient journey times
Information on consumer and stakeholder satisfaction, including staff and
patient satisfaction surveys.
- 14 -
One site, North Yorkshire, had recorded outcome data on success rates of the smoking
cessation programme. These results are included in the appended site report.
Overall, this response appeared to reflect the low priority placed on collection of such
data. A number of respondents indicated that, to date, the focus of CMS implementation
had been primarily on addressing morale and relationships within and between the staff
group comprising the microsystem.
Recording of performance data and impact on
service outcomes had not been central to this process. In some instances this reflected
the theme of local determination and local leadership characteristic of the CMS approach.
Sites had been free to set priorities and lead implementation internally and in most
instances this had not included routine collection of outcome or impact data. This is
linked to the popularity of CMS as an ‘organic’ approach, distinct from top-down
improvement programmes with onerous and heavily prescribed reporting regimes.
However, it also poses challenges for the evaluation exercise.
Clearly, there are
consequent limits to the summary claims that can be made for CMS as an instrument of
service improvement and as a means of delivering either productivity of effectiveness
gains.
As a result of these gaps in data, the evaluation is drawn largely from the
expressed perceptions of those involved and is therefore not able to determine which
teams might be considered high performing.
The majority of case study sites had little specialist data collection and data manipulation
capacity. This was recognised as a weakness by some respondents who felt that this
limited understanding of their microsystem and its performance. This brought an added
disadvantage when attempting to demonstrate the benefits of work undertaken and to
lever further change or resources where the need for these was identified. However, the
majority of respondents were happy for the benefits of CMS to remain relatively
‘unrecorded’ as long as these were still felt within the microsystem itself.
A further reason for the poor response in terms of outcome data may be reluctance to
disclose equivocal or unflattering information. This observation is speculative and based
on prior experience of external evaluation rather than evidence derived here. However,
data was not forthcoming from at least two sites who had indicated in interviews that
some recording of activity had been undertaken.
- 15 -
5.2.5 Summary
The overall emphasis on team working and process mapping was reflected in definitions
of CMS offered by the evaluation participants:
‘A group of people that work together with common goals and aims who want to
improve things within that team’
‘team-working and how you relate to people that you deal with day-to-day and how
you can help or hinder that working’
‘The idea that you are an important part of a team and you can make a difference’
‘Working within my immediate team looking at how we do things, how we work as
a team’
‘looking at yourself and your place in a broader system’
‘It’s another name for what goes on around you. It’s about fundamentals rather
than the big clinical stuff’
‘It’s a group of people working together to improve things’
5.3 Perceived benefits of CMS
Interviewees from each of the case study sites were asked to identify any benefits and
disbenefits which they considered to be a direct result of adopting CMS. This was initially
introduced as an open-ended question and was followed, where necessary, with specific
prompts relating to staff, patients and services provided. In order of prevalence, benefits
cited were:
•
•
•
•
•
Greater communication within the microsystem;
Improvements to morale within the team;
Empowerment and involvement of individual team members in service
improvement;
Greater awareness of the service’s functions and individual roles in
delivering these;
A shift in culture towards a more active approach to individual and collective
improvement, and;
- 16 -
•
A greater capacity to absorb and manage externally imposed change and
upheaval.
5.3.1 Communication and morale
Each of the six teams had been afforded varying amounts of protected time to undertake
CMS implementation. Although this had been used in differing ways it was unanimously
seen as having led to improved communication between members of the microsystems.
There was considerable freedom and variation in how this element of the process was
conducted and this seemed to allay fears that CMS implementation would be highly
demanding and daunting.
Overall, CMS was credited with formalising the need for
listening and sharing with all team members encouraged to attend and take an active
role. Many respondents reported an increase in openness and improvements in the flow
of information.
In some cases this was supplemented with mechanisms such as
dedicated CMS notice-boards.
As indicated, the six case study teams had adopted CMS for varying reasons including as
an attempt to ‘turn around’ a service that was seen to be failing and/or as suffering from
low team morale. In these instances CMS was widely seen as having brought about
significant improvements.
Respondents from other sites identified more modest
increases in morale, reflecting a less extreme starting position. There were also clear
differences within teams, particularly between respondents who gained personally from
the experience of CMS and those who reported more modest personal benefit. However,
there was virtual unanimity that overall, each team had developed greater cohesiveness,
mutual support and team building. A key factor in improving morale was the weight
afforded by CMS to identifying areas of strength as well as to areas of weakness.
5.3.2 Empowerment and involvement
A related benefit cited consistently by respondents derived from the systematic
involvement of all members of the microsystem in the diagnostic and development
phases. Individuals referred to having a ‘voice’ and a ‘platform’ enabling them to take an
active role in change and improvement. This was key to achieving a levelling out of
authority and hierarchy and conferring of developmental roles on those who had
- 17 -
previously considered this as an exclusively management skill and responsibility.
This
benefit was again more pronounced in services where individuals had previously felt
marginalised but appeared to be common, in some measure, across case studies.
Respondents pointed to specific instances of staff leading on aspects of change and
development.
However, the main effect of this empowerment was in creating a
receptiveness to, and in some cases ownership of, the CMS process. The process of
arriving at this point of consensus and involvement was uneven within and across case
studies, reflecting contextual factors such as: size of teams, extent of divisions across
microsystem members, and levels of initial resistance and dissent. In some instances
these barriers were not fully overcome but in all cases overall progress was claimed.
5.3.3 Self awareness
CMS was seen as having engendered scrutiny of current roles, practices and systems
which in turn had enhanced clarity and understanding for those involved. The time taken
to ‘take a step back’ was seen as a welcome opportunity to analyse previously
unexamined practices and routines.
This was seen as a prerequisite for the more
tangible innovations and improvements which some of the sites subsequently initiated.
Although respondents cited previous involvement in ‘process mapping’ there was a
general perception that CMS had afforded a more thorough and extensive review and
that this had benefited from accompanying ‘people’ focussed activities.
5.3.4 Managing change and developing an improvement culture
The relationship between CMS and other areas of change and transition was complex
and appeared to vary between sites.
Some sites had adopted CMS as a specific
mechanism for progressing pre-identified programmes of change and/or improvement
including, for example, health and social care service integration.
Others found that
increased responsiveness and robustness to change – for example office relocation - was
a positive by-product of CMS. This was most often seen as an effect of CMS principles
and processes on the culture of teams. In particular this involved the fostering of an
openness to innovation and stronger working practices enabling disruptive external
changes to be absorbed more effectively.
- 18 -
By contrast, some case studies within the sample had suspended the CMS process and
respondents attributed this to an environment of upheaval and turmoil. In one case this
appeared to constitute a permanent discontinuation, whereas other site respondents
indicated that whilst active progress had ceased, underlying CMS principles remained in
place and would continue to do so through periods of ‘dormancy’.
5.3.5 Patient benefits
As indicated, improvement activities had focussed more on staff than patients and
service-users. Most respondents stopped short of directly citing patient benefit as an
outcome of CMS although many felt that this could be inferred from improvements in the
cohesion and organisation of services. Respondents from a minority of sites suggested
that changes adopted through CMS had resulted in a more ‘patient-centred’ service (for
example sites see Epsom & St Helier, and the Beverly Integrated Mental Health Team).
Others felt that improvements to staff working had laid a foundation for intended future
developments focussing explicitly on the patient experience.
5.4 Perceived disbenefits of CMS
There were far fewer negative outcomes attributed to CMS.
However, an issue
mentioned by a number of interviewees concerned the diagnostic phase and the dangers
of identifying problems that prove to be either irresolvable within the microsystem or
contrary to broader organisational policy or directions of travel.
A single respondent felt
that the process of self-analysis occasionally threw up perceived or actual limitations that
could negatively affect the confidence of individuals.
Interviewees also weighed the perceived benefits of CMS against the level of time and
capacity it took up and in a minority of instances considered the latter to outweigh the
former. Implementers operating in an acute setting found it especially difficult to protect
time against competing imperatives. However, respondents acknowledged that CMS was
otherwise relatively resource-light in comparison to other change management and
improvement initiatives they had experienced.
- 19 -
5.5 Key features of CMS implementation
Respondents were asked to identify the specific features of CMS implementation which
had brought about these benefits. In no particular order of prevalence, commonly cited
factors are detailed below.
5.5.1 ‘Small steps’
The emphasis on a gradual process and the absence of ambitious aims and expectations
made CMS appear less daunting than many had expected.
Team members felt
reassured that wholesale change was not expected and this was confirmed when (in
most cases) early diagnostic exercises revealed successes as well as limitations in
practice and performance.
A modest approach which eschewed the tackling of
unrealistic obstacles – at least in the early stages of implementation – made it possible for
those leading the process internally to retain a higher degree of co-operation from
reluctant or sceptical team members. The subsequent achievement of ‘quick wins’ –
adjustments on a relatively minor scale – consolidated early enthusiasm and in some
cases led to increased ambition within microsystems. The ‘small steps’ approach was
therefore seen as important in developing momentum and garnering support for CMS.
5.5.2 Flexibility
The flexibility afforded the case study sites by the modest demands and expectations of
the local CMS programme contributed to the belief that progress would be pursued at a
manageable rate and also engendered a sense of ownership and freedom from external
monitoring and sanction. As illustrated by the varying ways in which the case study
teams applied the CMS principles, this flexibility was exercised in both the speed and
focus of activity. However, the majority of respondents in sites considered some external
structure to be necessary. It was felt that outside expertise, the opportunity to learn
across organisations, and the legitimacy gained through involvement in a broader CMS
programme, were important counter-balances to local autonomy.
- 20 -
5.5.3 CMS resources
By contrast, a number of features of CMS appeared to have either a negligible or a
negative impact on implementation.
A number of respondents considered the term
‘clinical microsystems’ itself to be misleading and even off-putting. Early misperceptions
stemmed from its apparent association with technical or IT-based interventions. Many
interviewees had dropped the ‘clinical’ from CMS in their everyday usage and some
advocated a re-branding to reflect the more palatable realities of the CMS approach.
There was also a marked under-usage of pre-existing CMS tools – the adapted ‘green
book’ – to the extent that the majority of interviewees were unaware of the existence of
these.
Some expressed retrospective regret at this, arguing that greater awareness
might have led to greater usage. Others appeared content to adopt CMS principles
without making use of specific tools. A smaller number of respondents preferred not to
buy in to the framework or language of the ‘5 Ps’. Reasons for this were not always clear
but seemed to stem from a sceptical response to ‘jargon’, ‘buzzwords’ and
‘catchphrases’.
5.6 Implementation enablers and barriers
Respondents were asked to identify factors that had either helped or hindered
implementation.
Views expressed are summarised below.
The two factors most
frequently cited were: a) leadership from individual members of the team, and b)
involvement of all team members.
5.6.1 Leadership
The existence of a small group of early CMS converts and advocates was common
across all six sites. In most cases these became, to varying degrees, leaders of the
subsequent implementation process. Leadership in some cases involved little more than
providing a structure and organisation for the CMS work to be developed – including
liaising with the broader programme and keeping records of team exercises and
decisions. In other teams there was a requirement for a more active, interventionist
leadership style, including at times the adoption of a more directive approach to conflict
- 21 -
resolution and to establishing processes for making difficult decisions.
In general,
leadership styles tended to reflect the aspirations and circumstances of the
microsystems. However, respondents from one case study site indicated that a deficit in
‘strategic’ leadership had hindered progress.
Some leaders emerged from within teams as their own interest in CMS increased.
Others – for example heads of services – assumed a leadership role reflecting their
seniority.
In general the emergence of these advocates and leaders was received
positively by other microsystem members and helped to generate support. In a small
number of instances, however, people expressed concern that those leading the process
were not best placed or fully equipped to do so. Others expressed the view that ongoing
progress was heavily dependent on these individuals and therefore might be threatened
by changes in personnel.
5.6.2 Involvement
The importance of leadership was matched by the significance attached to achieving
comprehensive involvement and consensus.
Clearly, the explicit extension of
improvement activities to all members of the service is a key element of the microsystems
credo, and one which was understood by each of the case study teams. However, the
extent to which this unanimity and involvement was actually achieved varied. The two
largest teams reported highest levels of dissent or non-cooperation which posed serious
difficulties in both cases.
Within these, and other teams experiencing lower level
resistance, the strategy for overcoming this barrier involved a mixture of compulsion and
‘diffusion of innovation’ (Rogers, 1995). Elements of compulsion included insisting on
attendance at CMS meetings or insisting that all staff abide by decisions taken in their
absence.
The second strategy centred around building momentum amongst more
receptive team members in the hope that others would become involved as benefits
became clearer. This was relatively successful although some sites had not been able to
generate full involvement from the microsystem members.
- 22 -
5.6.3 Levels of support within the host organisation
Each of the six sites had been granted protected time to implement CMS. This was
crucial in the diagnostic phase although some teams had subsequently reduced the
frequency of CMS meetings.
Respondents in the majority of teams indicated that a
greater level of support – in the form of strategic direction and commitment of resources –
would have helped in achieving change and improvement. Explanations for the lack of
active support centred around the relatively low profile of the CMS programme and
projects and a subsequent lack of external appreciation of what teams were undertaking.
It was further claimed by some interviewees that intended changes identified as part of
the CMS process were unlikely to receive the necessary support of the broader
organisation in these circumstances.
5.6.4 Support from the broader CMS programme
The case study teams reported varying degrees and types of input from the broader CMS
programmes. Two of the three programmes in question had organised workshops for all
implementer teams to develop their understanding of CMS and to share experiences and
learning. In general these were seen as valuable and as helping to inject enthusiasm into
those attending. Teams attempted to spread attendance at these workshops across the
microsystem members. A small number of respondents felt that benefits accrued from
attendance did not warrant the time spent away from routine work.
Further support was available in two of the three programmes in the form of an identified
‘CMS coach’ whose responsibility was to provide specialist support and facilitation where
necessary.
Perspectives on this further input ranged from those who had found it
unwelcome and therefore proceeded without further programme involvement, to those
who had valued outside involvement and felt that more such support would have been
beneficial. The CMS coach was seen by these latter respondents as providing important
expertise – for example in advising on processes and interpreting data – and contributing
to the general legitimacy and profile of the work undertaken. For example, a number of
interviewees felt that requests from external parties were less likely to be declined or
dismissed by sceptical members of the microsystem.
Support from the broader
programmes was thus both a key enabler of, and also a potential barrier to,
implementation.
- 23 -
5.6.5 Stable environment
Other elements of the broader environment were felt to have had an impact on the CMS
implementation process. Generally, a context of relative stability was seen as conducive
to achieving change, even amongst respondents whose teams had adopted CMS
specifically as a means of managing transition. For example, some interviewees talked
about expending finite ‘change time’ and limited energy for attending meetings.
Uncertainty about broader directions of travel could also halt progress in adopting CMS
albeit temporarily in most cases. Therefore it appeared that although CMS was useful in
helping to manage a context of change there was a threshold beyond which CMS was
overtaken or superseded by other events.
5.7 Succession and sustainability
Many respondents expressed doubts when asked if they thought the CMS approach
would continue to be used within their team.
This was perhaps surprising when
considered in the light of the overwhelmingly positive assessment of its value as a means
of improving services. Although respondents from two sites were emphatic in predicting
that CMS would continue to be used, others expressed doubts due to:
•
Reliance on the leadership and efforts of a small number of individuals. For
example, in one site a key advocate had recently moved and this was seen
•
as posing a threat to continuation;
•
The absence of resources to support the process;
•
support the CMS process, and;
The absence of a national profile to ensure host organisations facilitate and
The build up of conflicting priorities and pressures.
- 24 -
6. DISCUSSION
6.1 CMS, contexts and outcomes
The evaluation drew data from six case studies and as such can offer only a partial
assessment of the clinical microsystems approach within England. However, the study
raises a number of themes worthy of further exploration and attention.
Using Pawson and Tilley’s (1998) framework, it was clear that the context of involvement
in CMS varied across the case study teams. The sample included acute, community and
partnership sector agencies of various sizes. Some of these had recently undergone
significant re-structuring or were perceived to be failing and saw CMS as a means of
tackling these challenges. In some instances CMS was therefore clearly being used as a
tool to bring about broad, pre-identified shifts in service orientation and organisation.
Other reasons for adoption of CMS included the desire to improve staff co-operation and
a general aspiration towards more effective working.
Each of the organisations had
received senior approval from their organisations and undertook CMS as part of a
broader programme operating in their areas.
There was also variation in the mechanisms adopted by the teams. The CMS approach
is commonly subdivided into the four ‘P’s
- ‘Patients, People, Patterns, Processes’
(augmented more recently by the fifth ‘P’ – Purpose (Gill & Gray, 2006)). Sites revealed a
preference for focussing on ‘people’ and ‘processes’ over ‘patient’ and ‘purposes’,
although a number of exceptions were evident. The focus on ‘people’ can be seen as
influenced by a number of aspects of context:
•
This was a powerful strategy for garnering support from potentially sceptical
team members. The emphasis on staff well-being distinguished CMS from
previous, externally imposed improvement programmes.
This might
therefore be seen as an issue of sequencing – with more patient and
•
system based initiatives to be developed at a later stage;
In some cases a focus on people reflected the avowed aims of those
introducing CMS: for example to assist with integration of health and social
care teams, to improve communication and co-operation within the team,
and;
- 25 -
•
The relative lack of resources available to teams – beyond holding regular
meetings – may have contributed to a focus on the more manageable aims
of improving staff well being and communication. Technical innovations and
the levering of extra funding were not facilitated by the various CMS
programme arrangements.
Many of the teams analysed and adjusted processes as a result of adopting CMS. These
achievements were most evident in teams that engaged CMS with specific improvement
objectives in mind – for example shifting from a clinical to a nurse-led service, and
improving hospital cleanliness - and many of the changes to systems and processes were
broadly consistent with these overarching aims. By contrast, teams who did not start out
with an identified change agenda were more likely to have concentrated on ‘people’
issues and reported fairly modest system changes.
There was some reference to teams analysing ‘patterns’ – most frequently in referrals to
the service. This was again most evident where CMS had initially been adopted as part
of an explicit concern to improve performance. Overall, however the teams indicated a
far greater emphasis on process issues than on service outcomes. This was illustrated
by the apparent weakness of data and information, reflecting findings from CMS
evaluations conducted elsewhere (Nelson et al, 2002).
It is not clear why the majority of teams had not explicitly included patients given the
focus within CMS on inclusion of service users within the microsystem. The teams that
had involved patients reported subsequent improvements in their approach to service
delivery. The majority appeared not to have incorporated patients into the diagnostic
elements of their work although many identified this as a weakness which they intended
to address.
The outcomes reported by respondents clearly reflected the ways in which the
mechanism of CMS had been interpreted and implemented. The overwhelming focus on
staff and processes led to the primary outcomes of:
•
Improved communication;
- 26 -
•
•
•
Team building;
Improvements to systems and working practices, and;
Responsiveness and robustness to upheaval and transition.
The focus on ‘people’ and ‘process’ was reflected in the relative absence of outcomes for
patients and the lack of measurable impact on quality, safety, productivity or efficiency.
This may be partly explained by the relationship between teams and the broader CMS
programmes. Some sites had not fully utilised available resources (notably the CMS
coaches and the ‘green book’) and this may have contributed to the lack of data collection
and patient involvement.
Despite this, there was a widespread feeling amongst
respondents that CMS had made teams more responsive to patients and to changes in
the external environment.
A common theme across sites was the inhibiting effects of the broader organisational
context. These barriers often only came to light when teams attempted to implement
areas of change and improvement and were faced with restrictions and/or resource
constraints. The evaluation identified a strong argument for senior level support and buy
in.
The extent to which outcomes would be lasting and the likelihood of a continued
application of CMS principles were also felt to be contingent. Respondents warned of the
dangers of drifting away from the culture of openness and responsiveness developed and
returning to previous, less productive patterns of behaviour.
Important factors here
include:
•
•
•
•
Retaining and nurturing internal leaders and advocates;
Ongoing reinforcement and renewal of the principles and practices of CMS;
A receptive and supportive organisational context, and;
Avoidance of excessive strain and competing priorities – for example as a
result of staff shortages.
- 27 -
6.2
CMS and local improvement capability
Based on the testimony of those involved in its implementation, there are clear strengths
of CMS as an approach to local service improvement. The evaluation identified a trend of
empowerment and a consistent expansion of the pool of ‘improvers’ taking in those
traditionally excluded from formal programmes of change and service innovation.
Furthermore, gains were made with minimal additional resources which were seen to be
reasonably resistant to challenging circumstances and competing demands.
A key
finding was that CMS implementers appeared to adopt and embody principles of practice
which were conducive to ongoing change and improvement. This would appear to imply
an underlying shift in culture making future discrete areas of innovation more achievable.
The evaluation thus provides support for the claims made regarding the ‘integrating’
potential of CMS as compared to problem-based approaches to improvement (Golton &
Wilcock, 2005). These shifts were not however resistant to unlimited external upheaval
and to the effects of countervailing influences from outside of the microsystems in
question.
Clearly, microsystems are not untouched by the broader organisational and
policy context. Some respondents were unable to disentangle and dissociate outcomes
of CMS and other initiatives. This became problematic when CMS was conflated with
unpopular changes (such as moving to self-managed team governance). This complex
relationship between the strong sense of internal ownership of change – heightened by
the flexibility afforded by the CMS programmes – and externally derived service redesign,
requires further study. In particular the dual use of CMS as a means of, on the one hand,
managing change transition, and of, on the other, introducing new areas of improvement
identified from within the microsystem, needs to be carefully managed.
The flexibility of CMS offers an implicit recognition that solutions cannot be universally
applied or transferred mechanistically across differing contexts (Allen, 2006 unpublished).
However, resulting variation in approaches can lead to some potentially concerning gaps.
There is a need for economies of expertise and support to ensure that due consideration
is given to key priorities such as measurement of outcomes and involvement of patients
and service users. The role of the macro-system and of broader CMS programmes is
crucial here. The balance between generating expert advice, guidance and setting out
overarching expectations of CMS implementers whilst avoiding imposition and
interference is difficult to strike.
- 28 -
Given the multiplicity of ways in which CMS may be interpreted, the question is not
whether CMS ‘works’ as an improvement methodology, but instead is more nuanced
relating to who it works for, when and how. As outlined in earlier sections of this report,
key figures from the NHS III have suggested that in order to deliver on the agenda laid
out in The NHS Plan a process of continuous improvement needs to be embedded within
the NHS engaging nearly 100 per cent of all staff members. Thus, in judging CMS as an
improvement methodology we must ask whether it is a useful tool for engaging staff
members and sustaining an improvement ethos within these teams.
The evaluation
suggests that some teams have been more successful in this endeavour than others,
therefore we need to look at the how and why of this process.
A key issue seems to concern how the CMS approach is institutionally ‘framed’; that is,
how the approach is presented to staff members in a way that captures their interest and
pushes them to engage and then sustains credibility to remain an ongoing concern within
that specific organisational context. At one level, the CMS approach seems to be useful
as a sense-making tool for leaders, and lays out what it is the team does and how it fits
within the wider context.
Therefore, it is not just about the application of a specific
approach, but enabling a receptive institutional context so that the approach is
appropriate and useful. Within the evaluation, team members seemed more likely to
engage with the process where it was represented as an empowering and inclusive tool
for improvement. Moreover, continuation will only occur when the approach is perceived
as effective by those engaged in the process and there is evidence demonstrating
impact. Thus, there is an important role for the measurement of impact, not only within
the individual application, but for the future credibility of CMS as an approach within the
NHS as a totality.
6.3 CMS and the wider organisational studies context
Although Clinical Microsystems (CMS) are new to the NHS in some respects, many of the
fundamental underpinning principles are fairly well established within the literature
pertaining to organisational behaviour and change.
In a study of performance and
productivity within the private sector Quinn (1992) noted the importance of reducing large
and complex organisations to key building blocks (named ‘smallest replicable unit’ or
- 29 -
‘minimum replicable unit’), so that staff can respond to the needs of customers and
changes within the external environment. This evaluation appears to reaffirm the value of
this approach within the context of health care (and to some extent the public sector more
generally). Those respondents who advocated use of CMS – and these were distributed
amongst each of the six case study sites – identified responsiveness to both service user
needs and an ever-changing organisational landscape, as key benefits of the CMS
approach. That is, the CMS approach was a useful tool for framing the remit of the team
within a complex and shifting institutional context.
The idea that organisational structure has a high degree of salience for performance is
fairly well established, with quality theorist W. Edwards Deming (quoted in Seddon, 2004)
going as far as to suggest that 95 per cent of the cause of variation in performance is
attributable to the system that the work of an organisation is structured around. In other
words, failure is due to the way the work is designed and managed - rather than the
people executing the tasks. Although much of the literature would disagree with quite this
high degree of influence being afforded to structure given the importance that human
factors are thought to play in organisational performance; one thing that is stressed is that
organisational form should follow the purpose of the organisation (Jas & Skelcher 2005,
Mucha 2005, Walshe et al. 2004, Dalziel et al. 2004) and most of the improvement
methodologies widely adopted within health and social care have had a clear focus on
process improvement. If applied fully, the principles of CMS should offer a synthesis of
structural and people-based solutions. The evaluation was inconclusive as to the lasting
impact of the approach on performance as sites were in relatively early phases of
implementation and hadn’t collected sufficient data.
A consistent theme of the evaluation was the focus within CMS on understanding roles
and systems in order that areas of strength and weakness can be identified. This is
consistent with studies which note that high-performing organisations have clear and
consistent role and responsibility structures.
The responsibilities of the core of the
organisation and the business units need to be clarified with clear definition of
accountabilities.
An organisational map which has been communicated and
demonstrated to all members of the organisation may prove useful in achieving this
aspect and these had been developed in a number of case study teams. Weick (1987)
suggests that one of the premises of high-reliability organisations is that employees who
- 30 -
know more about their system should be better able to operate it. Care must be taken so
that the flattening of structures and devolution of resources goes hand-in-hand with the
clearly devolved responsibilities and accountabilities which holding these entails.
A number of the established concepts underpinning CMS are embodied within the
literature relating to New Public Management (NPM). NPM is heavily influenced by the
private sector; essentially suggesting the traditional public administration of the past is no
longer suitable to the management of public services within today’s context. Osborne
and Gaebler’s (1993) Reinventing Government outlines how public services may be
transformed along these lines, and their ten key principles are illustrated in Box 1.
Box 1: Osborne and Gaebler’s (1993) 10 principles for re-inventing government
1. Catalytic government: steering, not rowing.
2. Community-owned government: empowering rather than serving.
3. Competitive government: injecting competition into service delivery.
4. Mission-driven government: transforming rule-driven organisations.
5. Results-orientated government: funding outcomes, not inputs.
6. Customer-driven government: meeting the needs of the customer, not the
bureaucracy.
7. Enterprising government: earning rather than spending.
8. Anticipatory government: prevention rather than cure.
9. Decentralised government: from hierarchy to participation and teamwork.
10. Market-orientated government: leveraging change through the market.
As Box 1 illustrates, NPM drew heavily from the private sector around the introduction of
market mechanisms to improve public sector services.
Key to this paradigm is the
decentralisation of power to the ‘smallest replicable units’ identified above.
This
decentralisation is predicated on the basis that it will provide:
•
•
Greater
flexibility;
organisations
circumstances and customer needs;
Greater efficiency;
- 31 -
can
quickly
respond
to
changing
•
•
More innovation, and;
Higher morale, more commitment and greater productivity from the
workforce.
By flattening out vertical hierarchies into simpler horizontal networks it is suggested that
changes can happen much more quickly as they are no longer required to clear multiple
bureaucratic processes. As Peters & Waterman (1982) suggest in their seminal text In
pursuit of excellence, contrary to the beliefs of public administrations of the past,
organisations do not require hierarchies to be held together. Within ‘tight’ cultures the
values and mission of a team are clearly understood by all members and take the place
of rules and regulations as the glue which keeps employees moving in the same
direction. This mission is informed by the needs of the ‘customers’ who use the services,
rather than being driven by the requirements of the organisation. In other words, the
organisations are clear about their purpose in terms of serving a distinct population and
structure their processes appropriately, so that all activities offer value to the end users.
Clearly these concepts relate closely to those of ‘purpose’ and ‘patients’ as outlined in the
CMS theory. The benefits of such approaches receive some support from the outcomes
of the evaluation.
Respondents indicated a preference for more democratic and
consensual approaches over externally derived initiatives with imposed targets and
expectations.
However, the focus on customers – patients in this setting – was less
developed in most cases.
The literature suggests that as bureaucratic hierarchies are flattened out, strategy and
policy is not driven in a top-down fashion but from the bottom-up. The team members are
closest to the day-to-day issues and problems, as well as the end users and, as such, are
the most appropriate sources of creativity in overcoming problems and simplifying
processes. Not only can frontline staff often present the best solutions to difficulties, but
allowing all team members to take part in such discussions enables a process of fullengagement and empowerment for all the team. Much of the high-performance literature
stresses the fact that employees are the value added within an organisation, and that the
ability to engage staff members and get optimal performance from them will largely
determine the success of the organisation (Applebaum et al. 2000, Applebaum & Berg
2001).
This was again confirmed by the evaluation but with an important caveat: in a
- 32 -
number of cases respondents expressed frustration at the restrictions of broader
organisational and health sector policy, and their inability to implement changes where
this broader context was perceived to be unsupportive.
The recent emergence of the field of Positive Organisational Scholarship highlights the
importance of harnessing the positive aspects of human behaviour – rather than focusing
on the negative - as much organisational scholarship has tended to do (Cameron & Caza,
2004).
Seligman is generally credited as being one of the first advocates of this
movement of positive psychology suggesting that getting the best out of individuals is
about much more than trying to work out how to fix problems with them. ‘It is about
identifying and nurturing their strongest qualities, what they own and are best at, and
helping them find niches in which they can best live out these strengths’ (Seligman &
Csikszentmihalyi, 2000: 6). Staw (1986) suggests that there is a relationship between
positive feelings of employees and their performance. It has also been observed that
high performing teams have a higher ratio of positive to negative communications
(Losada & Heaphy, 2004). This field is still in a relatively young stage but commentators
highlight that in today’s turbulent economic and socio-political climate, taking a proactive
and positive approach to organisational studies would be a positive development
(Luthans, 2002). This was a key theme of the evaluation and one which ran through all of
the positive developments reported in case study organisations.
The organisational studies literature contains a number of so-called high-performance
work practices, some of which are illustrated in Box 2. Researchers like Ashton and
Sung (2002) suggest that adopting these practices in a systematic manner will improve
performance, although other commentators have disputed various aspects that have not
demonstrated clear empirical effects.
Box 2: High-performance work practices from Guest (2000)
1. Realistic job previews
2. Psychometric tests for selection
3. Well developed induction training
4. Provision of extensive training for experienced employees
- 33 -
5. Regular appraisals
6. Regular feedback on performance from many sources
7. Individual-performance related pay
8. Profit-related bonuses
9. Flexible job descriptions
10. Multi-skilling
11. Presence of work improvement teams
12. Presence of problem-solving groups
13. Information provided on the firm’s business plan
14. Information provided on the firm’s performance targets
15. No compulsory redundancies
16. Avoidance of voluntary redundancies
17. Commitment to single status
18. Harmonized holiday entitlement
In addition there are also a number of high performance management practices in the
literature, examples of these include:
•
•
•
•
Flexible work organisation;
Intensive training;
Use of self-managed production teams;
Involvement of production workers in solving production and quality control
•
problems;
•
Total quality management (TQM);
•
Quality circles;
Job rotation.
Many of these practices resemble those pioneered by large Japanese enterprises in the
1980s and 1990s, most commonly the automobile and electronics industry, but also other
industries such as machine tools (Doeringer et al., 2003). Taken together, these high
performance work and management practices are characterised by a common desire to
raise employee skills, motivation and empowerment (Applebaum & Berg, 2001). They
are typically designed to provide greater participation in decision-making, the opportunity
- 34 -
to learn new skills and the financial incentive to offer greater discretionary effort in the
service of the employer’s goals (White et al., 2003) – in essence a number of the aims
which CMS share with the service improvement aims of the 5 Ps (Godfrey et al., 2003).
The constraints of this evaluation – which was essentially exploratory in its scope – make
definitive pronouncement difficult. However, a number of benefits cited by respondents
such as the opening up of decision-making to previously ‘voiceless’ members of teams,
and the experience of ‘upskilling’ and empowerment, suggest that CMS may indeed offer
some of these broader benefits.
- 35 -
7. CONCLUSIONS
Overall, the evaluation supports many of the claims made for clinical microsystems In
relation to the flattening of hierarchies and motivating of a range of staff groups to
become involved in service improvement activity. The evaluation supports the claim that
democratic, consensual approaches can be better received than externally derived
initiatives with imposed targets. The emphasis on identifying and nurturing strengths – of
both teams and individuals – reinforced these positive aspects.
The case study sites demonstrated higher staff morale, empowerment, commitment and
clarity of purpose.
To a lesser extent the evaluation also indicated an enhanced
predisposition towards improvement and innovation and a seemingly embedded sense of
improvement as an ongoing (if essentially episodic) process.
However, some of the
strong sense of ownership and flexible adaptation came at the expense of patient
involvement and process/outcomes monitoring. Future programmes will need to address
these components if the broader legitimacy of the approach is to be cemented and
enhanced.
In particular, the importance of strong data collection in achieving ‘high
performing’ status is emphasized.
- 36 -
8. RECOMMENDATIONS
8.1 Recommendations for programme leaders (preferably at national level)
•
Establish minimum commitment from those teams recruited to undertake CMS
implementation in order to ensure key elements of induction and ongoing contact
•
are in place.
Ensure a thorough understanding of the CMS concept is imparted during
induction. Emphasise the importance of establishing a rationale for adoption of the
•
CMS approach.
Reconsider the name ‘clinical microsystems’ and revisit the CMS tools in the light
of their relatively sparse use by the case study sites. This may be an issue of
unfamiliarity or the tools being difficult to adapt to an NHS context. Programme
leaders could develop and hold an alternative central ‘resource kit’ for CMS
•
implementers.
•
those experiencing difficulties in facilitating CMS adoption.
•
improvement work of microsystems.
Help to cultivate leaders and champions from within sites and provide support for
Facilitate access to a budget to fund one-off applications for resources to further
Train and allocate CMS ‘experts’, ‘coaches’ and/or improvement workers to
provide ongoing and systematic support to implementer sites.
A minimum
•
involvement should be a precondition of recruitment to the programme.
•
public sector).
•
Develop a centrally held evidence base for CMS within health care (and the wider
Assist in framing CMS so that institutional support is provided to implementer
teams. This will involve profile raising and dissemination.
Carry out longer term research into the measurable impact of CMS on activity and
patient/service user outcomes.
8.2 Recommendations at microsystem level
•
Identify
internal
champions
and
advocates
implementatiuon process.
- 37 -
at
an
early
stage
of
the
•
•
•
As much as possible, achieve democratic and unanimous commitment from within
the team involved to support implementation of CMS.
Put patients at the centre of the implementation process throughout diagnostic and
development phases.
Assist in the collection of qualitative and quantitative data to demonstrate impact of
developments.
8.3 Recommendations at organisational level
•
Provide senior level understanding and support to ensure successful adoption of
CMS and to enable levering of resources to implement improvements. This goes
beyond provision of initial ‘time-out’ and includes supporting continuation of
improvements and where appropriate encouraging other teams to adopt CMS as
•
well as embracing the ‘culture’ of CMS more generally.
•
feed into and are effected by broader organisational strategy and policies
Map linkages between microsystems at a meso level and identifying how these
Link developments emerging from CMS to other service improvements and
innovations ongoing within the organisation.
•
•
Help to create a relatively stable
environment throughout the early stages of CMS implementation.
Assist and facilitate data collection and analysis where necessary.
Link with internal CMS leaders and with programme representatives as necessary.
- 38 -
9. REFERENCES
Applebaum E., Bailey T., Berg P., & Kalleberg A.L. (2000) Manufacturing advantage: why
high-performance work systems pay off. Cornell University Press, Ithaca.
Applebaum E. & Berg P. (2001) High-performance work systems and labor market
structures. In I.Berg and A.L.Kalleberg (Eds) Sourcebook of Labor markets. Kluwer
Academic / Plenum Publishers, New York.
Ashton D.N. & Sung J. (2002) Supporting workplace learning for high performance
working. International Labour Office, Geneva.
Ball,S., Mudd,J., Oxley,M., & Pinnock,M. (2004) Make outcomes your big idea: using
outcomes to refocus social care practice and information. Journal of Integrated Care 12,
13-19.
Bate P., Bevan H., & Robert G. (2004a) Towards a million change agents. A review of
the social movements literature: implications for large scale change in the NHS. NHS
Modernisation Agency, London.
Bate,P., Robert,G., & Bevan,H. (2004b) The next phase of healthcare improvements:
what can we learn from social movements? Quality Safety Health Care 13, 62-66.
Bevan H. (2004) The importance of theory.
Cameron,K.A. & Caza,A. (2004) Contributions to the discipline of positive organizational
scholarship. American Behavioral Scientist 47, 1-9.
Dalziel,M., DeVoge,S., & LeMaire,K. (2004) Six principles for designing the accountable
organization. Journal of Organizational Excellence 59-66.
Denis J.-L., Lamonthe L., Langley A., & Valette A. (1999) The struggle to redefine
boundaries in health care systems. In D.Drock, M.Powell, and C.Hinings (Eds)
Restructuring the professional organisation. Routledge, London.
Doeringer,P.B., Lorenz,E., & Terkla,D.G. (2003) The adoption and diffusion of highperfomance management: lessons from Japanese multinationals in the West. Cambridge
Journal of Economics 27, 265-286.
Ferlie,E.B. & Shortell,S. (2001) Improving the quality of health care in the United Kingdom
and the United States: a framework for change. Milbank Quarterly 79, 281-315.
Gill, M. & Gray. M. (2006) Using Clinical Microsystems and Mesosystems as Enablers for
Service Improvement in Mental Health Services. Humber Mental Health Teaching NHS
Trust (unpublished)
Gladwell M. (2000) The tipping point: how little things can make a big difference. Little,
Brown and Company, New York.
Godfrey,M.M., Nelson,E., Wasson,J.H., Mohr,J.J., & Batalden,P.B. (2003) Microsystems
in health care: Part 3. Planning patient-centred services. Joint Commission Journal on
Quality Improvement 29, 159-170.
- 39 -
Goes J.B., Friedman L., Seifert N., & Buffa B. (2000) Theory, research, and practice on
organizational change in health care. In J.Blair and M.Fottler (Eds) The future of
integrated delivery systems. JAI/Elsevier Press, London.
Golton, I. & Wilcock, P. (2005) The NHS Clinical Microsystems Awareness and
Development Programme. Final Report. NHS Modernisation Agency
Greenhalgh T., Robert G., Bate P., Kyriakidou O., & Peacock R. (2004) How to spread
good ideas: a systematic review of the literature on diffusion, dissemination and
sustainability of innovations in health service delivery and organisation. National Coordinating Centre for NHS Service Delivery and Organisation, London.
Guest,D.E. (2000) HR and the bottom line: has the penny dropped? People Management
26-31.
Henrich,J. (2001) Cultural transmission and the diffusion of innovations: adoption
dynamis indicate that biased cultural transmission is the predominant force in behavioural
change. American Anthropologist 103, 992-1013.
Institute of Medicine (2001) Crossing the quality chasm: a new health system for the 21st
century. National Academy Press, Washington DC.
Jas,P. & Skelcher,C. (2005) Performance decline and turnaround in public organizations:
a theoretical and empirical analysis. British Academy of Management 16, 195-210.
Jones E. (2004) A Matron's Charter: an action plan for cleaner hospitals. NHS Estates,
Leeds.
Losada,M. & Heaphy,E. (2004) The Role of Positivity and Connectivity in the
Performance of Business Teams: A Nonlinear Dynamics Model. American Behavioral
Scientist 47, 740-765.
Luthans,F. (2002) The need for and meaning of positive organizational behaviour.
Journal of Organizational Behavior 23, 695-706.
McLeod,H., Dickinson, H., Williams, I., Robinson, S. & Coast, J. (2006) Evaluation of the
chronic eye care services programme: final report. Health Services Management Centre
University of Birmingham
Mucha,R.T. (2005) Business as performance art: are you getting rave reviews?
Organization Development Journal 23, 67-73.
NHSII (2006) Evaluation of Clinical Microsystems. Research and Evaluation
Specification Template.
Nelson,E., Batalden,P.B., Huber,T.P., Mohr,J.J., Godfrey,M.M., Headrick,L.A., &
Wasson,J.H. (2002) Microsystems in health care: Part 1. Learning from high-performing
front-line clinical units. Journal on Quality Improvement 28, 472-493.
Osborne D. & Gaebler T. (1993) Reinventing government: how the entrepreneurial spirit
is transforming the public sector. Penguin Books, London.
- 40 -
Pawson, R. & Tilley, N. (1998).Realistic Evaluation London, Sage
Peters T.J. & Waterman R.H. (1982) In search of excellence: lessons from America's
best-run companies. Harper & Row, New York.
Pettigrew A., Ferlie E., & McKee L. (1992) Shaping strategic change. Sage, London.
Quinn J. (1992) Intelligent enterprise: a knowledge and service based paradigm for
industry. The Free Press, New York.
Rogers E.M. (1995) Diffusion of innovations. Free Press, New York.
Secretary of State for Health (2000) The NHS plan: A plan for investment, a plan for
reform. HSMO, London.
Seddon,J. (2004) It's the way we work...not the people. Personnel Today.
Seligman,M. & Csikszentmihalyi,M. (2000) Positive psychology. American Psychologist
55, 5-14.
Staw,B.M. (1986) Organizational psychology and the pursuit of the happy/productive
worker. California Management Review 28, 40-53.
Walshe,K., Harvey,G., Hyde,P., & Pandit,N. (2004) Organizational failure and turnaround:
lessons for public services from the for-profit sector. Public Money & Management 201207.
Weick,K.E. (1987) Organizational culture as a source of high reliability. California
Management Review XXIX, 112-127.
White,M., Hill,S., McGovern,P., Mills,C., & Smeaton,D. (2003) 'High-performance'
management practices, working hours and work-balance. British Journal of Industrial
Relations 41, 175-195.
- 41 -
Appendices: case study reports
- 42 -
WEST HULL PRIMARY CARE TRUST: SEXUAL & REPRODUCTIVE HEALTH CARE
NETWORK. GENITO-URINARY CLINIC
Introduction
West Hull PCT (part of Hull PCT as of October 1st 2006) oversees a range of services for
sexual health delivered from Conifer House in Hull. This facility was conceived as a ‘onestop shop’ for people’s sexual health needs and includes: teenage pregnancy services,
Chlamydia testing, family planning, community gynaecology, erectile dysfunction,
vasectomy clinics, sexual health screening and genitor-urinary medicine. Allied to this,
sexual health services are provided from local acute settings (Castle Hill Hospital and
Bridlington Hospital). These national services draw particularly from the populations of
Hull and East Riding.
CMS was introduced into the workings of the Genito-Urinary
Medicine team in response to promotion by the North and East Yorkshire and Northern
Lincolnshire Strategic Health Authority of it’s CMS programme which had three ‘waves’ of
sites joining between October 2004 and January 2005. This document summarises the
implementation process, reported outcomes and perceptions of those involved in the
process of the value of the CMS approach.
The team
The GU service is made up of representatives from across GU medicine and numbers
approximately 25 staff. Within this group, three GUM consultants conduct general clinics
in conjunction with GU nurses and other personnel. A number of contextual factors led
the team to opt for the CMS approach.
They had recently moved into an integrated environment co-located with other sexual
health services, having previously delivered a standalone genitor-urinary sexually
transmitted infection service in an acute setting. This had led to a greater complexity in
linkages between providers – particularly as a result of implementing an integrated
reception within the building. Patient pathways were seen as having been significantly
slowed down as a result.
- 43 -
The service operated a mixture of appointment and walk-in for potential users with the
latter seen on a ‘first-come-first-serve’ basis. This meant that at times of heightened
demand patients were often faced with a long wait and/or being turned away.
These bottlenecks in access were accentuated as all service users were treated by
clinical staff, including consultants, regardless of nature or severity of complaint. No
triage system was in place to divert milder cases. Therefore, irrespective of need and
complexity only, on average, 16 patients were being seen per day and routine services
(such as sexual health screening) were being provided by senior clinical staff.
The overall sexual health service – and the GU clinic in particular – had recently been
subject to intense media exposure and scrutiny which had focussed on issues such as
waiting times and the lack of confidentiality for patients. Thus the service had come to be
seen as ‘failing’ and staff morale was commensurately low. There was a perception that
the skills of nursing staff were under-used.
Feedback suggested that patients were
happy with the service they received but unhappy with waiting times, the lack of
confidentiality, and the inaccessibility of the 2nd floor reception area. Respondents in the
evaluation indicated that prior attempts had been made to address these flaws but these
had amounted to little by way of changed working practices or impact on waiting times.
Data collection
In September 2006 the HSMC evaluation team and the West Hull PCT GU service
agreed to conduct a case study of the latter in order to explore and evaluate their use of
CMS. The proposed site evaluation included:
•
Face-to-face interviews with a sample of those involved, conducted in a site visit
on September 11 2006, and;
•
Ongoing collection of data relating to the CMS implementation process and its
impact on the team. Any such data was collected during the site visit and in
ongoing liaison between HSMC and the Sexual Health Team.
- 44 -
At the time of writing, interviewees included a manager involved in the CMS
implementation process, a lead GU nurse and a GU consultant.
Other potential
respondents (such as the modern matron within the team) were not available for interview
at the time of the evaluation.
Following data collection, all data was collated and
analysed by the evaluation team.
The implementation process
Members of the team who were seeking solutions to the difficulties they were
experiencing made contact with the local CMS programme. Respondents estimated that
the CMS approach was first initiated within the team approximately 18 months prior to the
evaluation and the decision was taken to focus on GU – hitherto the most clearly
underperforming service within the centre. The GU team received presentations from
other teams in the area that had implemented CMS with positive results before seeking
senior management approval and submitting a formal application to be part of the 2nd
wave of CMS sites, following an earlier national pilot.
A core group of willing and enthusiastic volunteers was established from within the team
to take forward the initiative in its early stages.
Representation at CMS workshops
organised by the SHA was shared amongst team members and included administrators,
doctors, nurses and health advisors. Of those interviewed, all had attended at least two
of these monthly meetings which enabled sharing of learning and experiences with other
teams implementing the CMS approach.
Those within the team leading and managing the process then set up weekly internal
meetings. These involved facilitated discussion and clinical pathway mapping through
the sexually transmitted diseases service in order to identify bottlenecks in the patient
journey and any other areas requiring improvement. External facilitators were engaged
to assist in this process which was given priority over other forms of training and
development at the time. Notification of meetings was given, including through use of a
‘CMS notice-board’ which also served as a tool for staff to detail any complaints they had
and how they would like to see these addressed. External facilitation from the SHA
Service Improvement Team was used to support this process. This diagnostic stage
identified issues of access as being of primary importance. In particular, the team sought
- 45 -
to specify roles and how these could be altered in order to speed up the patient’s journey
through the system.
For example, the clinical model hitherto adopted – in which
consultants conducted the vast majority of front-line work – was considered costineffective and excessively time-consuming. Once preferred models of working were
identified a gradual process of incremental change was introduced which was heavily
directed by the core CMS team with the assistance of external facilitation.
Respondents indicated that they had found the implementation process to be less
demanding than expected.
‘When I first heard about it, it sounded very complex but I have been very
surprised and very pleased that it’s not complex at all. It’s actually about simple,
small steps.’ (resp 1)
‘Eating the elephant: looking at a task which might previously have appeared to be
difficult or insurmountable and then breaking it down into component bits, making
a pathway and involving a relatively small number of core people and meeting
regularly with them, doing small amounts of things along the way until eventually
you get there.’ (resp 3)
‘Easily manageable bite-sized steps that are taken. Nothing too radical, nothing
too shocking that upsets too many people.’ (resp 2)
The adoption of a piecemeal, incremental approach had the benefit of establishing a
sense of progress and control. Early successes were instrumental in bringing other team
members on board. Team-building was an integral element to this programme which was
made easier by not being ‘weighed down by timescales and objectives’ (resp 1).
Benefits
CMS was seen by respondents as having fostered significant changes in behaviour.
‘Microsystems, in this service, has been phenomenally successful, and I don’t
know whether it’s the environment or the people that have been doing it but I think
- 46 -
it’s just totally transformed the attitudes and behaviours of some of the people in it.’
(resp 1)
This was both illustrated and enhanced by the involvement of ‘grassroots’ workers as well
as those more traditionally allied to improvement approaches. This was cited as an
advantage over previous schemes although there was a perception that CMS was
inappropriately named.
‘The fundamental flaw in change management is around people .You’re reliant on
people adopting new ways of working.
Microsystems uses a huge amount of
common sense. I don’t think the name does it justice. It turns people off. They
think ‘academic’ and it’s not.’ (resp 1)
As a result of CMS it was felt that nursing staff were sufficiently confident to offers views
and objections and to be involved in taking decisions, where necessary without
consultant involvement. These benefits were seen as helping the team both instigate
change and react to changes imposed on them.
‘I think everybody working in the NHS accepts that we’re going to be constantly
wading through change and you’ve got to have methods to deal with that and this
would be one method’ (resp 3)
Outcomes/changes to practice
The general perception from respondents was that the service still required significant
change and improvement but that CMS had led to direct benefits in both team morale and
the effectiveness of its workings.
‘We were a service that I would say was three or four years behind. But I now feel
we are in a totally different positions. In terms of PGDs, clinical pathways, nurseled care we have developed at a considerable pace and achieved amazing results
in just two years. I put that down to the commitment of the staff and the use of
Microsystems. It’s the mechanism that enabled the change to happen.’ (resp 1)
- 47 -
Some changes were directly attributable to CMS whereas others were a product of a
culture of improvement to which CMS has contributed. A broad shift had been towards
more nurse-led services. This had involved greater recruitment and training and allowing
nurses, rather than clinical staff, to see asymptomatic patients. The line management
structure had been altered so that nurses reported to the modern matron and the balance
of consultant activity had been altered to include more training and expert practice and
less routine patient contact. Some services, such as the provision of ‘telephone results’
to patients, were discontinued and new innovations were introduced including a nurses
station and patient self-triage.
Reward schemes such as the team ‘person of the week’
scheme were also introduced albeit with a mixed assessment from respondents.
Information on measurable improvements to the service were not forthcoming at the time
of writing. Respondents indicated that this was due to:
•
•
The lack of data collection – proposals were in placed for recruitment of a
performance analyst, and;
The interim stage currently occupied.
The view was expressed that ‘building
blocks’ of an improved service were now in place and the next step was to
transform practice.
Interviewees stopped short of arguing that direct benefits had been accrued to patients as
a result of CMS although one did indicate a perception that activity levels had increased.
At the time of evaluation, however, the service remained over-subscribed – perhaps
partly as a result of increased demand following improvements.
Key enablers and barriers
Issues were raised regarding the importance and extent of senior involvement and
support in achieving change. For one respondent, the CMS process had identified the
need for improvements which could not be actioned from within the team.
These
included reorganising reception services.
‘One of the recommendations was having a dedicated receptionist for this part of
the service but I think because of the policy of having an administrative system for
- 48 -
all I think it wasn’t acceptable at the time … I’m not too sure how, having worked
through a problem and made some recommendations, those recommendations
actually connect with the real movers and shapers for change. There’s often a
conflict between the evidence base and policy if you like. It’s probably best to pick
something that’s likely to agree with policy change.’ (resp 3)
This linked with a further area of potential difficulty which related to the overlap with other
microsystems, although some respondents saw this interlinking as positive rather than
inhibiting.
Overall, all respondents indicated that the changes undertaken were both
effected by and had implications for groups outside of the microsystem.
By far the most important barrier experienced by the core team was resistance from
within the team which was seen as stemming from perceived threat to established and
familiar ways of working. Structural solutions offered by other improvement programmes
were seen as inappropriate in this context and the benefits of an empowering and
incremental approach were cited in overcoming resistance. CMS had helped to distribute
power and influence more evenly within the team and had instituted a process of selfanalysis and problem solving.
‘It’s the best plan that we’ve had so far. We had tried things before. It’s a way of
getting round obstructers. You always get people resistant to change and in CMS
they are not allowed to be resistant just for the sake of it because there are so
many other people behind an idea.’ (resp 2)
‘The success of microsystems is down to the people who have used it. It’s not just
the processes, it’s how you engage and enable the people.’ (resp 1)
Leadership from within and outside the team was seen as important in driving the
process and establishing a core team of advocates who were then in turn important in
maintaining momentum. Outside input was seen by respondents as being more difficult
to contest and/or dismiss. The process was inclusive but offered no veto to those who
disengaged.
- 49 -
‘We started with a very clear philosophy: if you’re not there and you don’t want to
participate then changes will be proposed and actioned on a democratic basis
irrespective of roles and grades. If its right for the service and team we need to get
on and do.’ (resp 1)
Although, as had been indicated, CMS was seen as useful in helping to manage changes
imposed from outside, there was a threshold at which the process became overtaken by
other events and pressures. At the time of evaluation a series of ‘major issues’ had
resulted in relative dormancy in the CMS process.
‘Other change agendas have used up a lot of time, a lot of change-time, if you like.
Also a lot of meetings haven’t been happening as well. I think those things have
taken over a bit. I think people get a bit of meeting fatigue as well.’ (resp 3)
There had been changes in personnel including promotion out of the team for a key
member of the management team. In the process, some momentum had been lost.
‘The characters are such and the service is so complex it needs very strong, very
clear leadership on a daily basis … Even though the service has progressed,
attitudes and behaviours slip back at times.’ (resp 1)
Despite this, it was felt that the under-pinning principles of microsystems had become
routine and that the CMS toolkit could in future merely be ‘picked up’ as required.
Respondents envisaged using CMS to integrate with the other sexual health
microsystems and in the planned development of self-managed teams.
Conclusions
Overall, despite some variation in levels of enthusiasm and involvement the team
considered the CMS process to be extremely beneficial and as having:
•
•
•
Empowered team members;
Improved morale;
Improved efficiency of service provision, and;
- 50 -
•
Paved the way for further improvements.
CMS was favourably compared to other improvement tools, as it:
•
•
•
Focussed primarily on people, rather than structures and processes;
Encouraged tackling of small, achievable steps, and;
Did not set up unrealistic expectations and pressures.
Despite being unable to demonstrate measurable improvement in productivity or quality,
respondents were confident that CMS had enabled them to introduce substantive change
and that demonstrable benefits would be shown in future.
- 51 -
Occupational Therapy, Hambleton & Richmondshire PCT
Introduction
Occupation Therapy services for the geographical area of Hambleton and Richmondshire
have been overseen by Hamilton & Richmondshire PCT since 2003.
The OT team
covers the: medical, orthopaedic, surgical, Accident and Emergency, rheumatology,
community hospitals (x 3), intermediate care, children services, learning disabilities, and
palliative care.
The team numbers approximately 20 staff and the majority of these
remain located at the Friarage Hospital, Northallerton with satellite services in other acute
settings, intermediate care, the children’s centre, and at a Learning Disabilities service
within the community. Within the hospital sites, junior OTs rotate, senior and support staff
are static.
This service became involved in clinical microsystems as part of North and
East Yorkshire and Northern Lincolnshire Strategic Health Authority’s CMS programme
which had three waves of sites joining between October 2004 and January 2005. This
document summarises the implementation process, reported outcomes and perceptions
of those involved in the process of the value of the CMS approach.
Data collection
In September 2006 the HSMC evaluation team and the Hamilton & Richmondshire PCT
Occupational Therapy service agreed to conduct a case study of the latter in order to
explore and evaluate their use of CMS. The proposed site evaluation included:
•
Face-to-face interviews with a sample of those involved, conducted in a site visit
on September 15 2006, and;
•
Ongoing collection of data relating to the CMS implementation process and its
impact on the team. Any such data was collected during the site visit and in
ongoing liaison between HSMC and the OT Team.
At the time of writing, interviewees had been conducted with four of the Occupational
Therapists involved in implementation of CMS. One of these joined the team during the
- 52 -
implementation process. Following data collection, all data was collated and analysed by
the evaluation team.
The implementation process
The decision to introduce CMS reflected awareness within the team that they were not
operating as effectively as they would have liked and that better communication and coworking amongst OT’s within and between sites would benefit the service. Some of these
difficulties stemmed from the dispersed nature of the team and subsequently little
interaction between some members. Involvement in the SHA programme was initially
suggested by the then service head and this was subsequently taken forward by two
members of the team who attended the early programme workshops. After the first two
of these meetings subsequent attendance was shared amongst team members. Each
interviewee reported attending at least one meeting and some as many as five. Initial
judgements varied with some respondents immediately impressed whilst others struggled
with what they considered to be a ‘woolly’ and ‘difficult’ concept. An external CMS coach
was assigned to the team who attended workshops with the team and spoke to the Trust
at departmental level. Apart from this involvement, however, leadership of the process
was provided from within the team. Following initial meetings the team attempted to set
the parameters of their ‘microsystem’.
‘It developed into the microsystem of the people that were interested in it. We
looked at the issues that we felt we had and most of them were to do with the OT’s
and if we solved them we could work on expanding it to include other people.’
(resp 1)
Six-weekly meetings of those designated part of the microsystem were arranged by the
lead OT within the team with the purpose of identifying and overcoming impediments to
effective co-working, as well as identifying positive aspects to current practise. These
took place at locations outside of the dept: a fact which was cited as important by
respondents. Issues raised in these meetings included: the need to improve listening and
communication skills, as well as the need to improve the physical environment and
access additional capacity and resources. With regards to communication emphasis was
placed on the need for better sharing of information and mutual recognition of areas of
- 53 -
good work, and the importance of having confidence in colleagues.
These aspects
formed a programme of improvement which the team worked towards in the ensuing
months. Weekly staff meetings were arranged following the first CMS meeting. These
were short communication meetings for main department staff.
Involvement and
engagement in CMS increased during this process although not all team members
participated equally.
‘Initially it was very, very slow to get off the ground because we were thinking ‘Oh
it’s just yet another NHS hair-brained scheme’. You think ‘Yes more high paid
managers sitting round in suits when there’s a shortage of nurses.’’ (resp 2)
‘Some of OT are keener than others, some have been to all the meetings and
really give it their all and others turn up occasionally and some have dropped out
completely. ‘ (resp 1)
Within meetings the team were asked to share the lead in devising means of addressing
identified areas for development. These involved group activities (such as word games),
information giving and discussion. These were devised by the team rather than deriving
from either the ‘Green Book’ of CMS tools or techniques borrowed from other CMS
implementer sites.
The team discontinued involvement with the broader SHA programme preferring to take
forward developments internally. This was partly a reaction to perceived limitations of the
programme approach and partly due to practical difficulties in assigning time to attend
programme sessions. In general, maintaining internal enthusiasm and momentum was
prized more highly than external facilitation and sharing with other sites. For example,
schemes developed elsewhere which involved IT-based solutions were not embraced by
the team. However, more recently someone from outside of the team with improvement
expertise (an ex-lead for the service) led a process of re-visiting and re-evaluation of the
CMS initiative.
Overall, respondents indicated that these and other factors may have made progress
more drawn-out.
- 54 -
‘It has taken us longer and it’s been slower but we have had quite a lot of upheaval
and lot of staff leaving.’ (resp 1)
Perhaps also as a result of the relatively isolated approach adopted by the team, some
respondents indicated a lack of familiarity with the origins and components of the CMS
approach.
‘I’d like to know where it’s come from. I’ve not known if it is a rolling program. Is it
something that’s with us for all the time or is it coming and going?’ (resp 3)
However, the underlying principles were widely understood and interviewees were able to
offer cogent definitions of CMS:
‘A group of people that work together with common goals and aims who want to
improve things within that team.’ (resp 1)
‘It’s to do with team-working and how you relate to people that you deal with dayto-day and how you can help or hinder that working.’ (resp 2)
This was despite initial confusion sparked by misinterpretations of the title ‘Clinical
Microsystems’ which evoked associations with Information Technology.
Benefits
Respondents varied in the extent of benefit which they attributed to adoption of a CMS
approach.
However, all agreed that communication had improved as a direct result
although this was seen as susceptible to changes in circumstance:
‘I think on the whole the department is more cohesive than it was. We still have
blips if something happens that isn’t popular or flattens everybody. They don’t
seem to use the microsystems to be able to react differently but it has improved
the day-to-day stuff.’ (resp 1)
- 55 -
‘By being good with your communication you can help it rather than paddling your
own canoe and not let others know what’s going on … I think team spirit over here
has improved. I noticed that within the first couple of sessions.’ (resp 2)
‘I would say we’ve all benefited. We’ve all learnt to talk better, support each other
and back each other up. Even if they might not always agree with you, you know
that they listen to you and give you their support.’ (resp 4)
‘Communication has improved but it is very fluid. It’s something we have to do
constantly otherwise we just get caught up in our own little things.’ (resp 3)
CMS was credited with formalising the need for listening and sharing, and also with
having given a platform for less qualified members of the team to input into service
improvements. Respondents spoke of having been granted ‘permission’ and ‘a voice’ to
get involved in change.
A cautionary note was expressed by one respondent who felt that the process of selfanalysis occasionally threw up perceived or actual limitations that could negatively affect
confidence. This was despite the adoption of recognition and reward schemes such as
the ‘star of the month’ award.
Outcomes/changes to practice
The team appear to have applied the CMS approach primarily as a means of team
building and improving working relationships – for example identifying routine issues such
as keeping the workplace clean. Thus the focus has been on the ‘People’ aspect of the
‘5 Ps’. Process and patient issues have not been specifically addressed to date.
Key enablers and barriers
There was a consistent thread of mistrust towards externally imposed improvement
initiatives which extended to CMS for a number of respondents. The decision to take the
process forward internally had therefore been important in generating broader support.
- 56 -
‘When (internal leads) got personally involved and it was coming from among us
rather than the latest green paper, sort of thing, then yes it made more sense.’
(resp 2)
Some respondents actively disapproved of external involvement, considering this
inhibiting, whilst others felt that an injection of outside expertise may have aided the
process.
‘It would have been nice initially if somebody had come and looked at what we
were doing and maybe given us a bit more leadership, to try and get more people
on board.’ (resp 1)
Despite this, respondents were unanimous in emphasizing the importance of internal
leadership. This was seen as crucial in achieving widespread involvement which in turn
was cited as major condition of continued progress. Concern was expressed in this light
at the number of staff members recently recruited who had no formal involvement in CMS
– especially those based within the community and therefore routinely removed from the
main site.
The process was seen as not being robust to pressures on capacity.
‘Staff shortages make it harder. You get bogged down in what we’ve got to do,
you prioritise and for me personally that comes behind some of the other things I
have to do, pressures on the ward, things like that.’ (resp 3)
‘Not having enough staff threatens the process. We are low staffed currently and
the more people that leave the harder it is to get a group with time or inclination
because obviously the stresses from work increase as you’ve got more to do.’
(resp 1)
Also ‘catastrophic events’ were seen as threatening and as potentially triggering a
resurfacing of less positive ways of working:
- 57 -
‘We introduced a proposed reconfiguration to the service in January and when we
introduced it the whole microsystems was forgotten about, dissolved, and
everybody went back to old ways.’ (resp 1)
The importance of continuing regular meetings was asserted in the light of such threats
although some respondents noted a growing call for these to be held less regularly.
Sustainability/spread
A number of factors – including staff turnover and shortages – posed difficulties for the
continued application of the CMS approach, although at the time of evaluation the team
intended to continue and build on the improvements achieved.
In general, those
interviewed felt that the process relied for its succession on the leadership and
enthusiasm of key individuals rather than being more self-sustaining, although this was
not a unanimous view.
‘We come up with lots of ideas but it’s following them through that is the hardest
bit. I think it needs somebody to run with and keep pushing it otherwise you slip
back … I think it will continue but I think it will be very sparse. It will need people to
really push it. I think it is dependent on those people. Otherwise other things take
over.’ (resp 3)
Levels of commitment to the process were cited as being variable although it was felt this
reflected the difficulties of being a dispersed team.
Conclusions
Overall, CMS was adopted primarily as a form of team-building which consisted of
internally
arranged
weekly
meetings
focussing
on
improving
co-working
and
communication. In this respect, interviewees all expressed the view that benefits had
been accrued and that the process had been worthwhile. Although these benefits were
widely cited, none felt that the team was currently operating ideally or that the possibility
of retrenchment into previous patterns of behaviour could be discounted. This was seen
as a possible effect of external factors and staffing issues and as being influenced by
- 58 -
some ongoing areas of distrust between team members. The team clearly had felt some
scepticism and doubt in relation to the broader CMS SHA programme and had therefore
taken forward the process internally. This may have impacted upon momentum although
it had also clearly enhanced involvement.
- 59 -
BEVERLY INTEGRATED COMMUNITY MENTAL HEALTH TEAM
Introduction
The Beverly Integrated Community Mental Health Team was created in October 2002
following the merger of NHS and Social Care mental health services into one NHS
organisation in a Section 31 partnership agreement between Hull and East Riding
Community Health NHS Trust and Yorkshire Council. The team provides a range of
services for people with mental health problems resident in the East Riding area and their
carers. The integrated service includes community mental health provision from both
organisations, in-patient units for adult mental health and the Assertive Outreach Service.
Overall the team numbers approximately 30 staff.
This service became involved in
clinical microsystems as part of North and East Yorkshire and Northern Lincolnshire
Strategic Health Authority’s CMS programme which had three ‘waves’ of sites joining
between October 2004 and January 2005. This document describes: implementation,
reported outcomes, and perceptions of those involved in the process of the value of the
CMS approach.
Data collection
In September 2006 the HSMC evaluation team and the Beverly Integrated Community
Mental Health Team agreed to conduct a case study of the latter in order to explore and
evaluate their use of CMS. The proposed site evaluation included:
•
Face-to-face interviews with a sample of those involved, conducted in a site visit
on September 18 2006, and;
•
Ongoing collection of data relating to the CMS implementation process and its
impact on the team. Any such data was collected during the site visit and in
ongoing liaison between HSMC and the Beverly Team.
At the time of writing interviewees included operational managers from both health and
social care backgrounds and a mental health nurse. Following interviews and other data
collection the evaluation team conducted collation and analysis.
- 60 -
The implementation process
The Beverly team were recruited to the Strategic Health Authority CMS programme which
was initiated between October 2004 and January 2005. This involved submission of a
written application, which, when accepted, entitled the team to access a series of
workshops in which CMS was explained and teams involved in the programme could
share experiences and progress. The SHA also made the option of accessing a ‘CMS
Coach’ – a specialist in this area of improvement – for external support and facilitation.
A business case was made for involvement in the programme which involved arranging
off-site CMS days for the entire team and this was approved at senior manager level
within the service.
Those leading the process within the Beverly team attended the
programme meetings at the outset and made attendance at further meetings available to
all team members on a voluntary basis.
Three team members attended all of the
programme workshops and others attended an average of between two and three.
Representatives were required to feed back from these days to the six half-day meetings
arranged internally.
Attendance at the team ‘days out’ was voluntary although non-attenders were exhorted to
participate and emphasis was placed on the importance of the CMS process. The focus
of these meetings was initially on the ‘process’ element and involved mapping current
systems and activities. Attention was given to key areas of work such as assessment,
review, planning processes, and team objectives. A staff questionnaire – although not
that provided as a specific CMS tool – was also used to gauge views and feelings. This
questionnaire was later returned to in order to gauge patterns and shifts in team morale.
The meetings took place over a period of approximately six to nine months and a number
of areas for work were identified.
As a result of these processes the team identified team building as an important area for
improvement. They also used the PDSA (Plan, Do, Study Act) cycle in order to help
implement identified areas of change and improvement, and to analyse referral patterns.
In all of these activities the team drew on support from their designated CMS coach – for
example in administering and analysing staff surveys.
- 61 -
Respondents felt that a number of factors had impeded the implementation process.
Initially, the most important of these was the relative unfamiliarity of those leading the
process internally, with the underlying principles of CMS and expressions of these
including for example the ‘5 Ps’.
‘I think a few people should have gone on a few days about microsystems in order
to know what it means and how you are going to use it. It was only until half way
through that we saw how it fitted really. If we’d done that earlier we probably would
have used it differently.’ (resp 1)
The resulting lack of clarity was compounded as the implications of integrating services
and the proposed adoption of self-managed teams were being worked through at the
same time as CMS.
The implementation process was therefore hampered by the
association of CMS with these other difficult and sometimes unpopular changes.
‘Because people were feeling that we needed a manager, that the self-managed
concept was not for them, I think the waters got muddied so it was easy to blame
the microsystems when it was more to do with the self-management.’ (resp 2)
During the process it was decided that adopting self-managed teams would work against
fostering a joined-up approach and so an overall manager was appointed. By this stage,
however, respondents felt that valuable momentum had been lost.
Benefits
Despite these difficulties respondents were able to point to a number of benefits from
CMS.
Chief among these were felt to be improvements to processes and team
communication. Thus, CMS was seen as helping to address some of the difficulties of
instituting inter-agency partnerships.
‘Eventually, when we understood the ‘P’s, it made us focus. It began to be clearer
that we were all here for patient care and so that was a joining for us really and it
was probably some of the process stuff that was getting in the way.’ (resp 1)
- 62 -
‘I think that clinical microsystems probably helped people to get more involved and
people started to take on roles.
People who normally would fade into the
background or sit on the fence were doing bits of research or working on projects.’
(resp 2)
‘It gave us some tools – some positive tools – because we were in quite a negative
place and it gave us some positive ways of team building. It gave us some ways
out that would bring us together … At the end of the day that’s what we got out of
it: it helped the partnership.’ (resp 1)
The monthly meetings were seen as positive in that they made team members more open
to change and new ways of working, and the delivery of real changes made people feel
more positive about CMS. Morale was improved by the focus within CMS on positive as
well as negative aspects of current work and it was felt that professional barriers were
being eroded.
One respondent noted that the periodic survey exercise contained, if
anything, increasingly negative comments and opinions.
However, this was interpreted
as evidence of an increasing openness and engagement, and the empowerment of less
senior staff members to be critical:
‘Some people saw it as a waste of clinical time but others got a lot out of it and felt
that they could get involved with something that normally just managers or leaders
get involved in.’ (resp 2)
Further benefits were identified in areas of clinical governance and professional
development as a result of attention paid to current working practices although some
were sceptical about attributing this solely to CMS.
‘I’m not sure microsystems made a whole lot of difference apart from it did give us
an opportunity to look at ourselves as a team. But a lot of it we could have
probably done without the microsystem.’ (resp 3)
The incremental approach adopted in the CMS framework was seen as especially helpful
given the major upheaval that the team had undergone and were still undergoing. No
- 63 -
negative consequences of adopting CMS were identified apart from the opportunity cost
of taking regular time out of routine work. Respondents were wary of asserting any major
impact on patient care or service quality.
This was inferred in some cases from
improvements to assessment and the increasing clarity in roles and responsibilities but
the team were unable to evidence these inferences with outcomes or other data.
Outcomes/changes to practice
As indicated a number of potential innovations had been identified and implemented.
These included:
•
•
•
•
•
Changes to assessment (including conducting joint assessments);
Re-working of the duty system through imposition of a rota system;
Re-balancing of capacity to reflect bulges in weekly referral rates;
Use of team building techniques – including organising a central meeting place for
staff lunch, and;
Implementation of peer supervision.
At the time of writing the team had not reported data indicating any measured impact of
these activities.
Key enablers and barriers
Respondents valued the programme meetings as a means for sharing experiences,
particularly of difficulties and how these were overcome. The internal monthly meetings
were also considered central to the developments undertaken and benefits accrued. In
particular, the opportunity for reflection - identifying areas of good and bad practice and
strategies for improving the latter - was considered important by respondents. However,
there was a perception that momentum generated initially had tailed off somewhat. This
was attributed to the simultaneous re-organisations detailed earlier.
Interviewees
indicated that, in retrospect, CMS might have been more actively pursued and therefore
more effective if adopted at a different time.
- 64 -
‘I think we rushed at the door a bit too quickly. We shouldn’t have engaged in the
CMS process at that point. The reasons why I say that is because we’d only just
integrated as a service. We were still trying to find our feet operationally and
otherwise. We didn’t have anything in place. You had two huge, independent
organisations suddenly being integrated into one team, and we didn’t have anyone
to drive it – we didn’t have a manager. I think if we did it now we’d do a better job
of it.’ (resp 3)
Respondents described resistance from team members to components of the CMS
approach – including the ‘5 P’s framework and the tools contained in the CMS ‘Green
Book’. In the early stages of implementation those leading the process did not fully
appreciate the extent to which these elements were optional and felt that this knowledge
could have helped with presentation of the CMS approach to the team. Even so, early
successes and development of wider support convinced some, although not all, sceptics
to engage. Whilst the leadership team were appreciative of the external support they
received, some expressed a view that more involvement from the broader programme
might have helped overcome difficulties. Another view expressed was that some team
members felt that CMS had been imposed rather than explored and that this had
contributed to resistance. Again, this may have been due to a misperception as to the
principles of CMS implementation as set out in the literature.
‘I think some people probably thought we were just like guinea pigs being
experimented on. They get suspicious and just think ‘Oh here’s something else
that they’re going to foist upon us.’’ (resp 2)
Another theme mentioned in interviews concerned the role of senior management within
the service. From this perspective some of the issues identified in the CMS process
could not be responded to effectively from within the microsystem and required strategic
input to achieve substantive change. It was felt that understanding, enthusiasm and input
at a higher organisational level had not been forthcoming at this time.
‘We naively felt that we could use the microsystems to help us during the transition
but I think we found that the things that needed to be resolved weren’t at that level.
It was the strategic partnership – that layer, that microsystems wasn’t even
- 65 -
touching … We needed somebody to take things forward on our behalf to the
strategic boards and for somebody to fight our corner.’ (resp 3)
It was felt that issues such as, for example, the need to resource identified improvements
and the need for learning to be shared with other areas of the local health service were
left unaddressed. This issue was part of the rationale for rejecting a structure of selfmanaged teams in favour of appointing an overall service manager. Concerns were also
expressed at the difficulty of achieving change with a relatively large microsystem.
‘What we started to realise was that the other teams using CMS were small – no
more than eight people. And there’s us with 30 people. So the alarm bells started
to ring then. For it to work I think you need to have a smaller team to be honest.’
(resp 3)
Sustainability/spread
Respondents found it difficult to identify the boundaries of CMS’s influence on the team
although there was consensus that some current areas of good practice clearly dated
back to its introduction.
However, in an active sense, application of CMS tools and
meetings had ceased at the time of writing. Again, there was a belief that to some extent
CMS had helped the team to manage change but also that it could have been more
effective if implemented under different circumstances.
Respondents felt that CMS had relied heavily on key individuals whose absence would
have made its implementation impossible and that a similar ‘championing’ of the process
would be required in any future revisiting.
Ironically, rejection of the idea of self-
managed teams did not lead to re-appraisal of CMS. Instead, CMS was considered by
some in the team to be redundant in the absence of the proposed arrangements.
Conclusions
Benefits accruing from the team’s adoption of CMS were cited by each respondent and
each could see the potential value of the approach for teams like theirs (albeit not
necessarily the size of the Beverley team). Few of the CMS tools were actually used,
- 66 -
although concrete and apparently lasting adjustments were made to systems and
practices. Ultimately a combination of environmental factors, the unfamiliarity with CMS,
and limitations to the level of support and outside input, were seen as weakening the
process.
The relationship of CMS with self-management and the broader partnership
agenda were never successfully untangled and at times those leading the change
process felt isolated.
- 67 -
NORTH
LINCOLNSHIRE
&
GOOLE
HOSPITALS
NHS
TRUST:
CARDIAC
REHABILITATION (CR) TEAM
Introduction
Northern Lincolnshire and Goole Hospitals NHS Trust was established in 2001 following
the merger of North East Lincolnshire NHS Trust and Scunthorpe and Goole Hospitals
NHS Trust.
The Northern Lincolnshire and Goole Hospitals NHS Trust Cardiac
Rehabilitation team covers the Scunthorpe and Goole sites. CMS was introduced to the
team in July 2005 when North and East Yorkshire and Northern Lincolnshire Cardiac
Network asked for expressions of interest from organisations in the area following the first
wave of CMS national pilots. This document summarises the implementation process,
reported outcomes and perceptions of those involved in the process of the value of the
CMS approach.
The Cardiac Rehab team
The team had been in existence for approaching ten years and consisted of cardiac
specialist nurses (one based in the community), a further cardiac specialist nurse with a
counselling role, and a full time administrator. Many of the team were long-serving in the
hospital and had previously worked in the Trust’s Coronary Care department. Patient
populations included those with myocardial infarction, heart failure and PTCA, and those
undergoing cardiac surgery. At the time of embarking upon the CMS implementation
process the team were temporally relocated whilst building work was undertaken and this
had led to upheaval and some disruption to normal working practices.
Data collection
In September 2006 the HSMC evaluation team and the Cardiac Nurses agreed to
conduct a case study of the latter in order to explore and evaluate their use of CMS. The
proposed site evaluation included:
•
Face-to-face interviews with a sample of those involved, conducted in a site visit
on September 8 2006, and;
- 68 -
•
Ongoing collection of data relating to the CMS implementation process and its
impact on the team. Any such data was collected during the site visit and in
ongoing liaison between HSMC and the Cardiac Nurses Team.
Interviewees included Cardiac Specialist Nurses, the team’s Cardiac Counsellor and the
administrative worker.
The initial CMS lead within the team was not available for
interview at the time of the evaluation. All data was subsequently collated and analysed
by the evaluation team.
The implementation process
The local Cardiac Network was integral to the process of implementing CMS. Following a
number of initial meetings, the team began to attend CMS workshops organised by the
Cardiac Network which enabled them to develop an understanding of the approach and
to interact with other teams involved in its implementation.
These were made available
across the team - with each team member attending at least two such meetings - and
constituted the primary source of outside learning and support throughout the early
stages of implementation.
Following the initial workshops, the cardiac rehab team undertook a process of
‘identifying their microsystem’ and established a regular weekly meeting in order to
progress the implementation process. Two of these meetings were primarily taken up
with the two CMS leads within the team introducing the CMS concept. Involvement in
these meetings was initially not universal but eventually came to include all team
members. Prior to this the team had undertaken a mapping exercise (although not using
tools from the CMS ‘Green Book’) to identify their areas of work and to plot the patient
journey through their service. This led to suggested changes which were implemented by
the team. Then, as progress was made, individual team members were assigned the role
of reporting back and sharing ideas at subsequent workshops.
The team had been selective in their use of CMS tools and facilities. The website made
available for implementers to share learning and resolve difficulties had proved
impractical and had apparently suffered from technical failure. The tools contained in the
- 69 -
‘green book’ were unfamiliar to the majority of interviewees, as to differing extents, were
the ‘5 Ps’, the ‘CMS coach’, and the origins of the CMS approach in general. Despite
this, the team were generally convinced of the value of the approach and had a clear idea
of its essential principles and features. In response to a request for a definition of CMS,
one was unable to offer a response, and the others stated:
‘It’s about looking at yourself and your place in a broader system’ (resp 1)
‘It’s another name for what goes on around you. It’s about fundamentals rather
than the big clinical stuff’ (resp 2)
‘It’s a group of people working together to improve things’ (resp 4)
The main tool adopted by the team had been the Staff Survey which they completed and
submitted to representatives of the Cardiac Network for analysis.
This exercise,
combined with the prior process mapping exercise, and weekly CMS team meetings,
enabled them to identify area of strength and weakness in their practice and to implement
improvements.
Overall, the process of implementation was seen by respondents as having been far less
daunting and time consuming than anticipated and this was a major feature in winning
over sceptical team members.
However, this was not a universally held view and
respondent comments reflected differential levels of involvement, engagement and
perceived benefit with one team member feeling that the broader benefits accrued to the
team were not shared in their specific case.
CMS was seen as offering a flexible and non-prescriptive approach to implementation
with those involved free to select the elements that most suited the specific requirements
of their microsystem. This was identified as a strength of the programme.
‘You can use as little of it as you want or you can use the whole lot of it. You don’t
have to use everything that’s in the folder. You can take out what you want, and
you can also keep going back.’ (resp 4)
- 70 -
Benefits
Respondents framed the perceived benefits of CMS in terms of the team and what they
had gained (as opposed to other measures of benefit perhaps relating to productivity or
patient satisfaction). Enabling self-reflection was seen as a major benefit.
‘It makes you look at yourself and what you do. Because sometimes you just bob
along don’t you? Without really looking at whether what you’re doing is the best
way to do it.’ (resp 1)
The staff survey was seen as having been useful in identifying the relatively healthy
relationships between team members and this had a reassuring effect on the team.
Interviewees felt a strength of CMS as an approach was that it identified and
acknowledged their successes. It had, however, also highlighted areas for improvement
which were tackled in the weekly meetings.
This was almost unanimously seen as
having led to better communication between team members:
‘Before, there was no communication. Now we’re more communicative. That’s the
main benefit of it.’ (resp 2)
Formalising the process of discussion and group interaction had an empowering impact
on team members previously reluctant to broach difficult topics:
‘It gave us a voice and that could be used to stop any back-biting among people
because you were able, when you had your meeting, if you had something to say
you were able to say it without causing any offence.’ (resp 2)
Two interviewees saw specific benefits from the CMS approach in helping to manage
transition and upheaval – for example due to changes in the location of the team.
Outcomes/changes to practice
As a result of CMS the team had implemented a number of adjustments and additions to
their working practices. A team notice-board was used to provide updates and reminders
- 71 -
to team members.
This was considered to be of particular benefit to those whose
working practices diverged from the majority of ward-based nurses.
An annual ‘de-
cluttering’ of the team’s working environment was also implemented, although not all
interviewees attributed this innovation to the CMS process. The team also implemented
an additional stage into the patient pathway with one Cardiac Specialist Nurse charged
with conducting ‘discovery interviews’ with potential service users.
Outcomes deriving from these fairly minor adjustments to practice were emphasized less
than the benefits of increased communication which was seen as the primary area of
progress. Some went further and argued that practices hadn’t changed to any significant
extent and that this reflected the relatively effective prior working of the team.
‘For me, there was nothing really new out of it … ok we implemented notice-boards
and things like that but I think that would have happened any way.’ (resp 3)
All interviewees agreed that the relatively piecemeal changes undergone were a
reflection of the relative strength of the team prior to adoption of the CMS. Respondents
perceived that, in this, they were untypical of teams involved in the broader CMS
programme.
As indicated, interviewees did not support their advocacy of CMS with reference to
improved patient outcomes, although each identified this as the primary objective of the
service. CMS leads within the team indicated that this was an area of potential future
work.
In particular, it was felt that potential patient sub-groups – for example those
currently not referred to the team – could be consulted about their service needs.
At the time of writing there were no specific data referring to the impact of the changes
undertaken on any aspect of the team’s work.
Key enablers and barriers
The importance of gaining the support and consensus of the whole team was
emphasized as an important factor in successful implementation of the CMS approach.
The extent to which this had been achieved was perhaps slightly overstated by the more
- 72 -
enthusiastic exponents of the approach although all respondents agreed that the process
had become inclusive.
‘The important thing is that we all agreed to do it. I know other teams have tried it
and it hasn’t worked and I think that might be the reason. At the beginning we all
sat down and agreed to do it.’ (resp 1)
A small number of the team had some prior experience in service improvement initiatives
– including some promoted by the local Cardiac Network - whilst the majority had not.
These latter team members expressed some cynicism at the volume of ‘initiatives’ and
‘reforms’ to which health care was subject, indicating that they were sceptical of the
benefits of many such schemes.
The other frequently cited enabler was the leadership provided from within the team. This
seemed to involve two team members pioneering and ‘championing’ the process.
External support and facilitation, inasmuch as this was forthcoming, was also seen by
selected respondents as having had a significant impact:
‘Key to our success with (microsystems) was the support we’ve had from the
Cardiac Network. We couldn’t have done it in isolation. It’s crucial to have a third
party actively involved.’ (resp 4)
Allied to this was the support of the Trust in enabling protected time to conduct the
implementation process and to attend workshops.
Other factors cited by individual
respondents were:
•
•
The structure provided by the programme, so that: ‘instead of you rambling you’ve
got specific focuses.’ (resp 4);
The emphasis in CMS on small, achievable steps. This incremental approach was
seen as a significant advantage over more intrusive service improvement
initiatives;
- 73 -
•
The relatively small size of the team and the continuity of service of the staff group
employed. Despite recent upheavals the benefits of having a co-located team
•
were also seen as significant in implementing CMS;
The flexibility to proceed at a pace that suited the team, rather than being
hamstrung by targets and milestones. In some cases this involved the realisation
•
that some changes could not be made from within the microsystem, and;
The level of organisational upheaval that team members had had to negotiate
meant that they were not fazed or overly anxious at the prospect of further
changes.
Initially not all respondents had felt part of the process. This was partly because of the
difficulties in communication which the CMS process highlighted and also partly as a
result of the different day-to-day activities and movements of team members, with some
standing somewhat outside of common working routines. From the point of view of those
championing the process this was overcome by concentrating on maximising support
from those more receptive in the hope that others would come on board gradually and
indeed when the benefits became more clear some detractors became proponents
whereas others, whilst retaining reservations about the value to themselves,
acknowledged the benefit to other members of the team. There remained a concern that
a difficult context was made more difficult by the expending of time and energy on CMS
although this was a minority perspective.
‘In the end we imposed (CMS). There were enough people in favour and the
others eventually came on board.’ (resp 4)
‘I didn’t get anything out of it that would help me but I’m sure the others did get
more out of it.’ (resp 3)
Sustainability/spread
The majority of respondents were emphatic in recommending the CMS approach to other
teams within and outside of health care. In particular, it was recommended to teams
experiencing difficulties.
The majority of interviewees also felt the benefits of the
approach would continue to be felt and built upon regardless of potential future staff
- 74 -
turnover. At a fairly early stage of the process one of the CMS leads within the team left
for maternity leave and had not returned at the time of the evaluation and this had not derailed implementation.
‘It wouldn’t matter who was here and who was not because what we’ve got now is
various small things in place … and everything that we’ve done has become our
work and we longer notice it – its part of who we are.’ (resp 2)
This perspective was not universally shared, with some respondents feeling that the
absence of key individuals would pose a threat to continued use of the CMS approach.
However, in general there was a belief that CMS would be implicitly and actively
continued irrespective of personnel changes.
Changes in the broader organisational context it was felt could not ‘derail’ but could make
‘dormant’ the application of the CMS approach in some instances. However, it was noted
by respondents that the team were relatively unhindered by nationally derived targets. As
indicated, in other cases it was felt that CMS helped the team manage change.
Some respondents described aspirations towards broader organisational change along
CMS lines, envisaging a ‘blotting paper’ gradually covered by interconnected individual
departments or ‘systems’.
Conclusions
Overall, despite some variation in levels of enthusiasm and involvement the team
considered the CMS process to be worthwhile, particularly in facilitating greater
communication between team members and empowering all involved to have a voice.
There was some dispute as to the distinctive benefits of CMS beyond this, perhaps
reflecting that improvements were experienced more by some staff groups than others,
with some respondents feeling slightly removed from the routine processes of CMS
implementation.
For these individuals, a more calibrated involvement – with team
members committing varying amounts of time according to their centrality to the process
– might have made the experience less onerous.
As the primary strength of CMS was
seen to be its impact on internal communication, improvements in service delivery to
- 75 -
patients were more perceived than demonstrated, and the team indicated that they were
planning to focus more closely on this issue in the future.
- 76 -
EPSOM AND ST HELIER
Introduction
Epsom and St Helier University Hospitals NHS Trust is a large acute Trust serving South
West London and Surrey. The Trust's two district general hospitals, Epsom General
Hospital and St Helier Hospital, both offer an extensive range of acute services. St Helier
Hospital also incorporates Queen Mary’s Hospital for Children and is situated in
Carshalton.
St Helier introduced Clinical Microsystems (CMS) on two wards – one
surgical and one medical (Alex Ward at Epsom Hospital and Ward B6 at St Helier
Hospital) - with both teams having different experiences and outcomes of CMS. The
CMS were led by the Ward Sisters, and a working group was also established which
included nurses, matrons, ward clerks, managers and representatives from the Trust’s
Patient and Public Involvement (PPI) forum. The Sisters led the process on their own
wards, and the working group was used to stimulate ideas and share good practice and
experiences.
Matron’s Charter
Epsom and St Helier were selected as one of eight initial pilot sites for the Matron’s
Charter; which sets out ten broad principles for delivering cleaner hospitals (see Jones,
2004 for further information). The pilot sites ran for six months led by the RCN clinical
leadership team on behalf of the Chief Nursing Officer, using a CMS approach. Being
selected as one of eight national pilots meant that Epsom and St Helier were in the
national spotlight, but besides this prestige there was no additional funding attached to
the programme.
Epsom and St Helier used the Matron’s Charter as an opportunity to address the issue of
hospital cleanliness, which it recognised as an important issue to both staff and patients.
Within the whole of the NHS, Nurses and Matrons are traditionally recognised as being
responsible for cleanliness, but this role is perceived as having shifted in recent years
with changes to the educational processes of nurses and the contracting of cleaning to
professional contractors in a number of acute Trusts. Interviewees at Epsom and St
Helier suggested that they interpreted the Matron’s Charter as an attempt to embed
- 77 -
particular practices back into nursing behaviour nationally, but also recognised that it was
important to make sure that everybody has a role to play in keeping hospitals clean.
CMS Process
The Epsom and St Helier teams had little access to specific CMS resources prior to the
implementation, and felt that some sort of toolkit with a set of resources that could be
chosen from would have been useful.
Case studies from other sites who have
successfully implemented CMS, contacts within a network, or access to a coach who may
be able to offer support / training to those who led the project were also cited as
potentially useful tools which would have helped the process.
The Epsom and St. Helier experience of CMS was that it brought the teams together with
a specific focus on a project, and the protected time to work on a project.
‘When they’re told to take a step back from the project, they can very much look at
it with a different eye. Really the ward sisters were very much key to the project,
where they were being given time to stop and listen, whereas they usually just get
on day to day and don’t often have time to listen. Some people are very good at
taking that step back, but others can’t and they very much get caught up in the
here and now’.
The teams became quickly enthused by the project, although the two wards had quite
different experiences of this. Staff from a whole range of levels within the teams were
involved, and all were asked to provide input to the project. The CMS operated under the
policy that “no idea is a bad idea”, and the Epsom and St. Helier experience was that staff
became very creative and offered a number of innovative solutions to deal with issues of
cleanliness. Including such a range of people allowed the teams to think outside of the
‘usual’ parameters and get some very different perspectives and understandings of
issues. CMS also requires patients to be embedded within the process, rather than as an
‘add-on’ which has sometimes previously been the case within similar projects. The
group reported that the teams had really started to think about patients in a way that had
not perhaps done so previously.
The teams used these range of perspectives, and
- 78 -
looked outside of healthcare to private sector organisations (such as hotel chains) for
inspiration in addressing issues.
CMS was cited as having improved communication greatly amongst the teams, which is a
particular bonus within the acute care context where shift work means that the entire
team do not always have a chance to communicate with one another.
CMS also
encourages communication amongst all members of the team, not just with those that
people would usually interact with in the course of their daily role. External facilitation for
the CMS process was highlighted as being very useful by the interviewees; but
recognising that the external facilitator may not need to be entirely independent of the
organisation but not well-known to the entire team.
‘f they had a facilitator who was part of the ward, it probably wouldn’t have worked
as well’.
Although CMS was recognised as being useful, there were a few caveats raised about
the process. It takes a lot of focus and commitment from those leading the process to
make it happen successfully, particularly within an acute care context.
The process
requires the team to come together and this is not easy within the acute sector where
projects have to fight with other priorities - “no day is a good day”. Protected time is also
required to undertake CMS and this is not easy to find within acute care. Interviewees
suggested that the concept of providing protected time is anathema to the culture of
acute care, although it was recognised as being more the norm within primary care
environments. As the Matron’s Charter pilots had no funding attached there were not
extra resources available either to ‘buy’ protected time, or to implement some of the
innovative ideas suggested by the team.
Although CMS was cited as offering a good framework and starting point to focus on a
project, it was suggested that most of the concepts are not new. In fact, it was suggested
that what CMS is in practice is good project management, or a common sense way of
building teams and team capacity.
CMS was viewed as a good focus on how to
undertake a project, which is inclusive and allows issues to be looked at from a variety of
angles. The degree to which CMS in not an entirely new approach though could be
useful as people will recognise aspects of it.
- 79 -
‘When I first heard the title, I thought oh get this, you know, we’re going to get
something that’s all singing and all dancing, dynamic, new, innovative. But really
some of it is quite simple, and stuff that we already knew. I wouldn’t say I was
disappointed, because it’s a good way of structuring work, and it’s about good
project management’.
It was suggested that bringing a range of techniques together for team building and
having one specific name for this (although CMS is not a favoured option), which is
recognised and supported nationally (for example by the NHS Institute for Innovation and
Improvement) would lend the concept credibility and legitimacy more widely within the
context of the NHS.
Outcomes
One major change in practice was the production of a bed hanger which is put on the bed
of all patients when they arrive on the ward.
The teams felt that often patients’
perceptions, or fears, of cleanliness are often much worse than the situation in reality; the
bed hangers were designed to allay such fears. The bed hangers have a list of items –
for example whether the bedside cabinet has been emptied, sheets are fresh etc - which
the nurse will go through with the patient when they first arrive and check that all have
been crossed off.
‘It’s a bit like the fear of flying, the fear of cleanliness is worse than the actual level
of cleanliness itself. So by having this bed hanger, which is like a thing you have
in a hotel. It has some items on there which provide you with information leaflets
about infection, that your sheets are nice and fresh for you, that the whole area
has been checked and the bedside table has been cleaned for you and so on, and
the idea is that the nurse checks the area with this with you when you arrive. They
check the whole area and leave the leaflets … and it’s gone down really well’.
The hanger was designed with the involvement of all staff and patients and has been
reported as being a big success. The feedback was so positive that it was hoped that it
would be rolled out across the whole Trust, although there have been some difficulties
- 80 -
with this in practice. Nurses from other wards do not have the same sense of ownership
over the bed hangers and have been slightly resistant to the concept. However, some
other Trusts had also expressed interest in the innovation, and it was reported that a
private ward had introduced something similar as a result.
A ‘How was your stay?’ questionnaire has also been given to patients on the wards, and
feedback from these can then be used to address any problems or concerns raised. An
‘ideas board’ has also been introduced, where suggestions about how to improve
cleanliness and hygiene may be posted by patients, staff and visitors. As previously
stated, CMS was cited as having improved communication and team work within the
wards. Furthermore, interviewees suggested that it might have been a form of catalyst
for one of the wards which felt at a comparative disadvantage to the other at the start of
the process, having not undergone a recent refurbishment programme which the other
had. There was a degree of healthy competition between the wards, with CMS proving a
real focus point for the ward which felt at a disadvantage originally.
‘One team was quite successful, and one for varying other reasons didn’t seem to
be quite so successful, I think it’s fair to say.
The one that was the most
successful was the one that felt like it was the underdog to begin with. It was really
good to be able to see how that team really grew and blossomed, and realised that
they weren’t in this because they were a really bad team and they just weren’t
working before. They were in this because they were able to do some really good
work…People did things really differently than usual, they went above and beyond
and did things that they didn’t think were possible usually’.
Important issues and implementation difficulties
The interviewees raised the issue of who should be leading the CMS process as an
important point. Originally it had been hoped that a non-executive director (NED) would
take overall responsibility for the project, as this would have imbued the project with
legitimacy and credibility in the eyes of others within the Trust. The fact that the bed
hanger was not rolled out more widely, despite being a success, was perhaps indicative
that the project did not have sufficient high-level buy-in. However, it was recognised that
the support of a NED would not need to involve a huge amount of input, and could remain
- 81 -
as more of a sponsorship role. The CMS process requires that the members of the team
remain the ones with ‘ownership’ over the process, but that for microsystems to effect
change more widely within an organisation as part of the wider improvement process they
require some sort of official sanction.
Nonetheless, the make up of the CMS teams do need to have people involved who can
effect change. Epsom and St Helier recognised that they had been quite good in forming
teams with people who could do this and had the power to ‘make things happen’ – for
example by getting the SLA on the frequency of toilet cleaning changed.
The
personalities of those involved was also highlighted as being essential. As previously
mentioned, the CMS process needs commitment and drive to make it successful and
Epsom and St. Helier were successful in involving people who had the ‘right’ traits.
Although there was not an explicit process of selecting people with specific characteristics
in the formation of the teams, all the interviewees recognised that the results would
probably had been quite different if the make up of the teams had been different.
Important factors cited by interviewees at Epsom and St. Helier were:
̇
̇
̇
̇
̇
̇
Sponsorship of the CMS process by a higher level; somebody who can affect
changes in practice;
Strong personalities to lead the process;
External facilitation for the teams;
Protected time in order to be able to meet as teams and address issues properly;
Engagement of all levels – “no idea is a bad idea” , and;
Involvement of patients as an integral part of the process, not simply as an
additional add-on later.
Sustainability
Concerns were raised over the sustainability of CMS, and particularly CMS as a
sustainable process for ongoing service improvement. One of the sisters who lead a
CMS at Epsom and St. Helier moved on to another position and it was felt that this had
disrupted the continuity of the process. Although a number of the tools from CMS have
been embedded within the teams, there were some doubts over its long-term
- 82 -
sustainability – particularly as there is little in the way of resources attached. The patient
environmental action team programme (Peat) was given as an example of an ongoing
project which had been sustained, due to the performance targets all Hospitals have to
attain and a fund which could be bid to in order to implement certain ideas. Given the
pressures inherent within the acute sector, interviewees suggested that without national
recognition or resources to execute CMS conflicting priorities might instead win-out in
practice.
The group felt that there has been a lot of focus on this particular project due to the high
profile attached to being a pilot site, and that not every use of CMS would perhaps
receive the same focus.
‘We were in the spotlight, we were one of eight trusts that was a pilot for the NHS.
We were being looked at and we used that to our advantage didn’t we? This was
something that the NHS would be looking at us for, so our Trust needed to support
us for. So I don’t think it’s something that you would do every day, but I don’t this
it’s something that you can’t, because all of us here could. But it’s just a matter of
having that focus.’
The name ‘clinical microsystems’ was also cited as being particularly unhelpful, and
doesn’t seem to mean very much. A number of interviewees suggested that by changing
the name there might potentially be more engagement with any future uses of the
process, as the terminology was automatically quite off-putting to a number of people.
Conclusions
Epsom and St. Helier were broadly positive of the effects and processes of CMS, whilst
recognising that much of what this entails is in fact not new and is sensible team building
and project work. CMS was recognised as a good framework, or a focus for the Matron’s
Charter project. Epsom and St. Helier had fairly positive experiences of the CMS process
and have made a number of improvements within the two wards, although they had quite
different experiences of the process. CMS was cited as a good framework by which all
staff and patients could be involved within an improvement programme, although this
came at a cost of high levels of input and the need to be able to access protected time
- 83 -
which tends to be quite scarce within an acute care context.
The teams were very
positive about changes to practices they had made (such as the introduction of the bed
hanger), but were frustrated that there was not sufficient senior support to roll this out
across the Trust. Although the CMS process was thought to have changed the cultures
of the wards with respect to communication, teamwork and other practices, the ultimate
sustainability of CMS was questioned particularly due to a lack of access to resources
and coaching.
- 84 -
NORTH YORKSHIRE SMOKING CESSATION SERVICE
Introduction
The North Yorkshire Smoking Cessation service consists of quite a dispersed team, with
people based at several geographical areas around North Yorkshire. The team provides
a specialist smoking cessation service for smokers who would like to stop, and to 'stay
stopped'. The service also delivers training to health professionals on smoking cessation
interventions, and as such has a number of trained professionals associated with the
service who are based throughout North Yorkshire (for example in GP surgeries) and
provide independent advice to smokers.
The team also monitor smoking cessation
activity on behalf of the PCTs across the county. The part of the team interviewed for this
research are based in York and are one part of the wider service.
The team found out about the CMS programme whilst attending an event for a number of
smoking cessation projects. At this event there were some concerns raised about the
rates of smoking cessation which had been achieved over a wide area, and it was
suggested that a number of teams were failing to meet targets. The members of the
North Yorkshire team present felt that the day was quite negative in outlook. However, in
the afternoon there was a presentation about the Cardiac Network’s clinical microsystems
(CMS) development programme which was quite upbeat and positive. The members of
the team present felt that it had injected 'a bit of hope' into the day, and that it sounded
like a useful approach to take.
The team joined the programme in July 2005 and
attended the series of workshops which ended in March 2006.
Because the team is relatively small and has to provide a certain level of cover for the
office and telephone helpline, not all members of the team could attend the CMS
sessions at the same time. Indeed, some members were only able to attend one or two
sessions of the programme and felt that the process had been led by particular
personalities within the team. The team recognised that because the whole team had not
attended the sessions they may not have been able to fully embrace and be fully
embraced by the CMS process.
- 85 -
'I don’t think we’ve explored it as far as we can take it yet. Because we were very
limited in the numbers of people who could go, and continue to go, it’s been limited
really. It’s at an early stage, things can roll out more. There have been some
changes, but it’s something to revisit and look at again…I don’t think we’ve yet
explored all the options.'
The team suggested that because of this they are at a relatively early stage in the
process, but that they are taking the process at their own pace as is appropriate.
CMS Process
In some ways the external context had facilitated interest in the CMS process. Like most
PCTs nationally those in North Yorkshire are affected by reorganisations and financial
pressures. This has created a somewhat chaotic and unstable organisational context
around the team, and the CMS process has allowed the team to focus on their particular
services and has offered some stability.
'It came at a time within the service where there are a lot of restrictions, financial
restrictions with the PCT and things like that. You were sort of in a box in a lot of
ways with other things and it was a way you could get on and actually make
improvements with little sorts of things.'
The first thing the team did was to get staff to fill in the standard CMS questionnaire,
which was contained in the resources provided by the programme. However, they found
that given the complexities in the staffing arrangements of the team, with 12 different
people supplied by six different organisations, it proved too complex.
The team did
however undertake a questionnaire survey of patients. The first asked patients what they
thought of the service and what needed improving; as a result patients are now given
better information when their appointment details are sent through. A further patient
survey is also given at their first appointment to find out what made them attend the
appointment, and whether they will be attending their next appointment. This should give
a better understanding of the motivations for patients to attending smoking cessation
sessions, and what could be done to make them engage on a regular basis. The team
also hope to do further qualitative research in order to better understand what motivates
- 86 -
patients to use the service, and any changes that they might make to prove more
accessible.
In terms of looking at patterns, the team have mapped referral rates over a two year
period, to look at where referrals come from geographically. The team found that there
are differences in terms of the areas which patients who access the service come from,
and that there are some ‘holes’ in terms of post code areas of people who access the
service. The team can use this information in the future to try and design programmes to
get the people from these areas to engage with them. The team also looked at referrals
temporally and found, much as they had suspected, that they receive 50 per cent of their
annual activity within the first four months of the year. They have now started to look at
what mechanisms (such as flexible working, annualised hours and training periods) they
might use to maximise clinical contact in the first part of the year when the majority of
activity occurs, rather than using a fixed level across the year. The team also used the
referral patterns to look at the number of people who were re-attending, as perceptions of
re-attendance were thought to be particularly high.
From their analysis of referral
numbers the team found that in fact only six per cent were re-attending, giving them a
better understanding of the nature of their patterns and patients.
The team suggest that they had found the CMS process useful in a number of ways.
'I see it pictorially really … this it that person and they link to that person and
interact with that person and so on. Because you see people as little organisms
really and then you can see how they link to that other organism and so on. When
I’ve seen some of the demonstrations pictorially it’s really made a lot of sense, and
it’s very useful to see the system and how it all goes together.'
The team were able to make creative changes to issues they had identified, but felt that
there had perhaps not been sufficient support from higher levels of management to make
all of the ideas happen. Although the team suggested that it had been useful that higher
levels of management had not been involved in the process - and that if they had, the
process may have been less effective and people may have been unwilling to engage some sort of support or sponsorship from management may have been useful. This
would have meant that more significant changes could have been made by the team. As
- 87 -
it stands only certain levels of changes may be made and it is felt that significant changes
can not be implemented. The team also highlighted the fact that no resources had been
made available as part of the process, when access to some funding may have mean
that all of the ideas identified could have been implemented.
Outcomes
Performance data
The quantitative data provided by the site includes information on deprivation rates
(based on clients 2004 Index of Multiple Deprivation Scores), quit rates, drop out and
relapse rates at the 4 week follow up stage of the programme. The data is based on
analysis and information taken from a recent site report.
Table 1.1 provides information on the deprivation indices for four geographical areas
within North Yorkshire. Areas were ranked by their 2004 Index of Multiple Deprivation
scores and assigned to quintiles with one being the least deprived and five being the
worst.
Table 1.1: Population by IMD Quintile (5 most deprived)
Quintile
1
2
3
4
5
Total
Selby and York
68,609
57,353
39,524
42,735
61,853
270,074
Hambleton and Richmondshire
22,699
28,935
32,849
23,010
9,543
117,036
Craven, Harrogate and Rural
District
54,340
37,650
56,285
40,056
16,625
204,956
Scarborough, Whitby and Ryedale
3,237
26,004
22,835
44,033
61,006
157,115
North Yorkshire
148,885
149,942
151,493
149,834
149,027
749,181
Source: Yorkshire and Humber Public Health Observatory
Table 1.1 demonstrates that Scarborough, Whitby and Ryedale have the highest number
of people (per population) in the lower quintiles.
number of people in quintiles one and five.
Selby and York both have a high
This deprivation data was then cross
matched against outcome data collected at the four week follow up.
Figure 1.1 provides information on the percentage of clients who state that they
successfully quit smoking at the 4 week follow up by deprivation quintile.
This
demonstrates that the success rate varied between areas and that the highest
- 88 -
percentage of successful quitters tended to occur in the most deprived groups in the
population.
Figure 1.1: % of clients w ho state they successfully quit
sm oking at 4 w eek follow up
100
Selby and York
90
Hambleton and Richmondshire
80
Craven, Harrogate and Rural District
Scarbrough, Whitby and Ryedale
70
%
60
50
40
30
20
10
0
1
2
3
4
5
deprivation quintile
Table 1.2 Number of Clients succesfully quitting at 4 weeks, per 1000 population, by IMD Quintile 2005/6 (5 most deprived)
PCT (by postcode)
North Yorkshire Quintile
Total Rate
1
2
3
4
5
Selby and York
Hambleton and Richmondshire
2.7
3.3
4.1
5.9
5.2
6.3
4.0
5.6
5.9
8.9
4.3
5.7
Craven, Harrogate and Rural District
3.5
5.3
5.2
6.9
9.6
5.4
Scarborough, Whitby and Ryedale
3.7
4.4
4.6
4.9
7.8
5.9
North Yorkshire
3.1
4.8
5.3
5.3
7.2
5.2
Source: Yorkshire and Humber Public Health Observatory
Table 1.2 demonstrates the quit rates in all areas per 1000 population the data shows a
higher uptake in the more deprived groups. However, both the relapse rate and drop out
rate are higher in the more deprived groups (see figure 1.2 & 1.3 below)
Figure 1.2 shows the percentage of clients who reported that they had relapsed at the
four week follow up. This information is provided by area and deprivation quintile. The
data demonstrates that the relapse rate varied between areas and deprivation quintiles.
The lowest percent who relapsed was in the least deprived area and the highest number
in the most deprived area.
- 89 -
Figure 1.2 % of clients w ho reported they had a relapse at
the 4 w eek follow up
Selby and York
100
Hambleton and Richmondshire
90
Craven, Harrogate and Rural District
80
Scarbrough, Whitby and Ryedale
70
%
60
50
40
30
20
10
0
1
2
3
4
5
deprivation quintile
Figure 1.3 shows the percentage of clients lost to follow up. The data demonstrates that
the highest percentage of clients lost to follow up occurred in the most deprived areas.
Figure 1.3: % of clients lost to follow up after 4 w eeks
Selby and York
Hambleton and Richmondshire
Craven, Harrogate and Rural District
Scarbrough, Whitby and Ryedale
100
90
80
70
%
60
50
40
30
20
10
0
1
2
3
4
5
deprivatio quintile
The data suggests that the programme was successful for a number of patients - with
success rates for all outcomes tending to be higher in less deprived areas. The
evaluation data reported here was taken from data collected and analysed by the site
being evaluated. Therefore, it is difficult to report on the robustness of the data collected.
Having said this, the analysis provided by North Yorkshire suggests that variation may be
- 90 -
partially explained by the relatively small populations within most deprived areas and
least deprived quintiles for some areas.
Interview data
As a direct result of the CMS process, the team suggested that now they are meeting as
a full team more frequently than previously. Furthermore, these meetings are now longer
and the agendas are not quite as constrained as previously.
'Rather than trying to keep to a tight agenda, there’s been much more fluidity
because I think we were realising that we were getting frustrated, because we’d
meet together and have so much to say and so many opinions but didn’t discuss it.
So now we’ve realised we actually need to make the time.'
The team suggested that, previously, meetings had to cover a certain amount of ground
within a fairly restricted time and this meant the issues could not sometimes be fully
explored and that any additional points that arose as a result of discussions could not be
covered due to time restrictions. Therefore, the team feel that they are now better able to
discuss any issues which may arise and in more depth. Also specific target groups have
now been established around certain issues, rather than trying to involve 'everybody in
everything'.
Furthermore, although the team suggested that there were very few examples of changes
in practice, there had been a definite change of culture which they attributed to CMS.
Several respondents suggested that the culture of the team had changed from a ‘can’t do’
to a ‘can do’ culture. The team suggested that they sometimes feel quite isolated from
wider services due to the type of service they provide and where they are situated
geographically. The CMS process allowed them to change this perspective from being
quite negative to being positive, given the external context surrounding the smoking
cessation team. The team felt that the CMS process was very useful in making people
see that they are able to effect change within their organisation, that their opinions are
valued and that everybody is capable of finding solutions to difficulties and problems. In
this sense, the CMS process was identified as empowering and giving everybody a
‘voice’ within the process.
- 91 -
'I feel, from a purely personal point of view, that it’s given me a voice. Because at
the end of the day I’m the lowest grade here…but it’s made me feel that I can say
something – that I am entitled to say something. So if I don’t like something I will
say ‘why is that happening, can we not do that?’ It tends to be just little things but
it really makes you feel like you have a voice.'
The CMS process was cited as being very productive in terms of morale, particularly at a
time when there was much uncertainty in terms of the context due to PCT
reconfigurations and financial deficits.
A virtual notice-board was produced as a result of the CMS to try and keep members of
the dispersed team linked to one another. However, this notice-board was not successful
and some staff members found it very difficult to access. As a result this has now been
taken down, although there are plans for another website for the smoking cessation
service in the future.
Important issues and implementation difficulties
The CMS programme was cited as being useful as it allowed members from different
teams to share knowledge and stories about the CMS process. The other teams on the
programme with the smoking cessation team were from geographical areas outside of
York.
The team suggested that if there had been people from the same area, the
programme could have been a useful networking experience for all involved.
For
example, a fire brigade team from a different area took place in the programme. Had
they been from the same area they could perhaps have shared public information
programmes with the smoking cessation team. In this sense, the programme could have
also inadvertently had effects in terms of networking and partnership working, and in
effect ‘joining-up’ a number of the created microsytems within the wider macrosystem.
Some respondents also felt excluded by the label ‘clinical microsystems’ which they they
considered implied the need for a clinical background. Most of the team felt that perhaps
the name is not particularly useful and would not be appropriate for wider dissemination.
- 92 -
“Well, the fact that it’s got 'clinical' in front of it, I thought – this has nothing to do
with me. At the very beginning I thought, this has got absolutely nothing to do with
me, it’s this lot. But after a while I saw that it does, it involves everybody. They
need to drop the clinical bit, it puts people off.”
One of the most useful elements of the CMS process is that it involves all members of the
team, and enables people to find things about their environment that they can change to
make their lives easier. Yet, by being called clinical microsytems this may automatically
serve to exclude certain members of the team – particularly in this case when not all team
members were able to attend the initial sessions at the same time.
Important factors cited by the North Yorkshire smoking cessation team were:
̇
̇
̇
̇
̇
Sponsorship of the CMS process by a higher level; somebody who can affect
changes in practice;
Strong personalities to lead the process;
Protected time in order to be able to meet as teams and address issues properly;
Engagement of all levels, and;
Networking opportunities within the wider macrosystem.
Sustainability
In terms of sustainability, the team suggested that they do believe that CMS is
sustainable, although CMS work would not perhaps be consistently carried out on a
constant basis. The process would be likely to go through a series of peaks and troughs
in terms of activity, although it would consistently be there in the background. In this way,
one of the respondents likened the CMS process to a wave-like motion; where, a lot of
work would be done on the CMS process initially, after which relatively little work could be
done for a while until a point where an external event would prompt a re-launching or restart to the CMS process. Again, quite a bit of activity might then follow this prompt,
before it would tail off slightly before the next shift in the external environment when this
would again ignite the process.
In this way CMS was perceived as being a useful
framework for an ongoing improvement process.
- 93 -
Conclusions
The North Yorkshire Smoking Cessation team were broadly quite positive of the CMS
process.
Given the difficult external environment surrounding the team and their
perceived isolation from a number of the other services in the area the CMS process
seemed to provide a useful framing or focusing tool for the team during a time of
uncertainty. The CMS process has pulled the team together and changed the culture
somewhat and greatly improved morale. The CMS process was recognised as being
quite empowering, and not a top-down directed edict, but something that has developed
in a more local and organic way.
Although the interviewees pointed out that they had not made any ‘major’ changes to
practice as they saw it, they had collected significant amounts of data and appeared to
have a reasonable understanding of their patterns and people accessing their services.
The team also recognised that they were at a relatively early stage in terms of the
process, as they had been unable to send all members to the sessions, but that they
were taking the process at a pace defined by themselves.
This would suggest that
having gained a better understanding of their immediate context the team may be able to
make positive changes to practice in the future, at a time which is appropriate. However,
this may also mean that they need some recognition or commitment by local
management as some changes to practice may not be achievable without broader
support. It might also be useful for the team to link with other microsystems which exist in
the local area in order to make wider changes throughout the local macrosystem.
- 94 -