STATE OF THE ART GROUTING FOR POST-TENSIONED STRUCTURES
Paul Wymer 1and Marcel Poser 2
ABSTRACT
In 1985, a failure of a post-tensioned bridge in the UK brought about a complete review of grouting
associated with post-tensioned structures. There were some special circumstances that contributed to
the failure but the European market embarked on a total review of grouting procedures including
materials, equipment and techniques. Over the ensuing two decades, the European and US markets
have introduced various guides to best practice and there are now provisional European Standards in use
to accompany the new mandatory European Technical Approval protocols for post-tensioning systems.
These guides and codes pay particular attention to durability and a large amount of research has resulted
in new grout formulations, special additives, bleed water analysis and best practice execution.
While all of this has been going on, the NZ market has continued with its use of the grouting requirements
as specified by NZS 3109 and there are some significant differences between the NZ standard and latest
European and Australian practices. The local market has not experienced problems as have been
encountered overseas and it would appear that there have been no drivers to make changes. However,
in recent times, some NZ specifications have included reference to certain aspects of the European
protocols – with respect to testing for flow time, bleed and volume change. This presents a dilemma as
only parts of the European codes are being referenced and there are some conflicts when trying to
adhere to the local hybrid specifications.
This paper will outline the state of the art practices now commonly in use in Europe and compare them to
the practices in New Zealand. It will cover reasons for the new codes, mix design, testing, special
equipment and techniques including execution by specialists. It does not intend to try to cover all the
detail associated with grout design and execution procedures because these are extensively covered in
many recognised publications. However, it will highlight key aspects of state of the art grouting and direct
readers to other documents. The paper will conclude with some suggestions on appropriate measures
that might be adopted for the New Zealand market place.
INTRODUCTION
The principal objectives of grouting in a posttensioning application are:
•
•
Protect the prestressing steel from corrosion
by completely surrounding it in an alkaline
environment and filling all cavities with
grout.
Provide the necessary bond between the
prestressing steel and the concrete structure
member in bonded applications.
When looking at corrosion protection for bonded
tendons as a whole, grout is a key element. This
is the last protection layer in the fight to prevent
corrosion and to improve durability. For
unbonded systems, soft filling materials such as
grease and wax or plastic sheathing fulfill this
function. Cementitious grout provides excellent
protection for prestressing steel, thanks to the
highly alkaline environment which passivates it
against corrosion. All the analysis demonstrates
that the vast majority of post-tensioned
structures have behaved satisfactorily –
1
2
demonstrating excellent durability of the posttensioning tendons with, at the very least, good
design principles and best practice installation
techniques. However, enough deficiencies were
found to prompt a review of the quality of the
grout specified for use – but most of all, of the
grouting practice itself.
In the early projects carried out using posttensioning technology, durability was not a
concern – in the sense that it was considered an
intrinsic feature of the technology itself – just as
with reinforced concrete. Practical experience in
the last few decades has demonstrated this
belief to have been ill founded and has forced a
more holistic consideration of durability – as a
problem relating not only to the post-tensioning
system in isolation, but also to the concrete
structure as a whole.
With the introduction of the multilayer protection
strategy, protection against corrosion is provided
by a combination of features in any design –
waterproofing, dense impermeable concrete,
sealed ducts and good quality grouts. The
Managing Director, BBR Contech, New Zealand
Managing Director, BBR VT International Ltd, Switzerland
erstwhile design principles have been refocused
to improve durability – and items such as
waterproofing, drainage, concrete cover and
concrete quality are taking a higher profile. In
the case of post-tensioning, this has been
provided with a first protective barrier against
corrosion – namely, grout. The second
protective barrier is provided by the duct.
Commonly used metal corrugated or smooth
ducts do not necessarily constitute permanent
corrosion protection. So, to mitigate the risks,
the sealing of the ducts – and the entire tendon
– has been improved, and the use of plastic
ducts has been introduced for some
applications.
It is well documented that better quality of
grouting materials and of on site grouting
activities are a small additional cost to the owner
compared to the consequences of poor or
improper grouting.
Quality grouting is achieved through:
•
•
•
•
•
Careful selection of the based materials
comprising cement, water and admixtures
Consistency in the grout properties by a
high level of quality control
Use of appropriate mix design and mixing
procedures adapted to the specific
materials, environment and equipment
Trials to test grout systems for any particular
set of factors
Execution of grouting on site by qualified
personnel following approved method
statements
The
Concrete
Institute
of
Australia
Recommended
Practice
Grouting
of
Prestressing Ducts (2007) sums up by saying
“While a good grout mix is a necessity, it is not a
guarantee for successful grouting. Successful
grouting needs proper preparation, execution
and supervision of works by qualified and well
trained personnel.”
guidelines and standards now seen in other
parts of the world. Section 8.8 of NZS 3109 is a
little over 1 page in length covering the full range
of grouting requirements. Other international
guideline documents cover the topic in anything
ranging from 16-50 pages. This is representative
of the importance placed on this component of
work
and
the
extensive
international
development over the past 15 years with respect
to material selection, testing, execution of work
and qualification and training of staff. Key
aspects of the New Zealand grouting standards
are:
•
•
•
Materials – Type GP cement with approved
additives to improve workability or reduce
water content.
Flow time – in accordance with Section 3 of
NZS3112:Part 4 and between 18-22
seconds unless an admixture is added and
then flow time may be reduced to 15
seconds
Bleeding – Determined in accordance with
Section 4 of NZS 3112:Part 4 and shall not
exceed 2% of the initial volume 3 hours after
mixing. Bleed water shall be re-absorbed
after 24 hours.
A simple test usually
performed in a calibrated vertical glass tube.
This is a test relating solely to the grout with
no other reference to how prestressing
strand may influence the tracking or
“wicking” of grout inside a tube or duct.
This is basically the requirement for what has
typically been termed “common grout.” There
are some other fairly general requirements
relating to plant, procedures and safety but all of
this is included in another 2 pages in NZS 3109.
The additional designer-provided specifications
add to these standard requirements and typically
cover off more detail associated with specific
material requirements, compressive strength,
equipment capability, grouting pressures,
temperature controls and venting of air/bleed
water.
CURRENT NEW ZEALAND PRACTICE
The detail relating to the testing noted above is
quite basic and not further outlined in this paper.
Common grouts mixed and pumped using basic
equipment can quite readily attain the
characteristics required in New Zealand
standard specifications.
The base requirement for grout is commonly
sourced from Section 8.8 of NZS 3109:1997.
This is usually supplemented by project
specifications which provide further detail on
grouting equipment and methodologies specific
to the application. It is probably worth putting
this into context with the more common
More recently, there has been recognition in
New Zealand that enhanced grout designs
should be utilised to ensure post-tensioned
structures are more durable. The key driver to
this was presumably to provide a grout which
had less bleed water – with less tendency to
bleed, there would be less free water in the
With all of this in mind, let us consider some of
the detail associated with grouting practice in
New Zealand.
grout to create problems. A new requirement
was seen to be entering specifications whereby
the quantity of bleeding of water and air from the
grout should be determined in accordance with
fib Bulletin 20 Guide to good practice: Grouting
of tendons in prestressed concrete (2002). The
intentions were very sound, but the reality was
that common grouts cannot satisfy the
requirements and the reference to bleed limits
alone means that all of the other important
information relating to material selection, quality
control, trials and execution by qualified people
was essentially omitted. In many respects, the
stipulation that a grout achieve a lower bleed
limit would do little more in ensuring that the
grout would perform its primary functions of
providing corrosion protection to the strand and
effective bond to the concrete. These things can
all be looked at in isolation but this will not raise
the bar for grouting (or for enhanced durability in
our structures) unless all of the components are
addressed collectively. This is not a profound
observation – it is simply restating the original
objective of the international working groups that
formed to improve the durability and long-term
performance of structures comprising grouted
post-tensioned tendons.
It was also determined that many conflicts
existed when omitting other aspects of the fib
document i.e. the grouts that may be able to be
designed to achieve the low bleed may not be
able to be pumped by the same equipment. A
wider understanding of the changes to grouting
protocols was required and this means a closer
look at the detailed changes introduced into
current international practice.
INTERNATIONAL GROUTING PRACTICE
Grouting is no different to any other engineering
activity – the nature of the codes and guidelines
are quite specific to the geographic location and
the peculiarities of the market. As such, there
are documents that exist in UK, France,
European Union (a normalising approach for all
of Europe), USA and Australia. No doubt there
are many others but these do not come to light
in the NZ market very often.
The European and USA documents all stemmed
from the problems discovered in the 1980’s and
early 1990’s. The content of the documentation
does deal with a total solution approach and the
material covered typically includes:
•
Introduction and scope – an outline of the
importance of grouting to durability and how
the revised document deals with all aspects
of grouting design and execution.
•
•
•
•
•
Design detailing – covers ducting and
connectors, grout inlets, vents and caps
Grout materials and mix design – cement,
admixtures, water, performance criteria
Testing – testing regime, suitability tests,
acceptance tests, pre-approvals
Grout production and grouting operations –
equipment, batching and mixing, grouting
methodologies and requirements for special
grouting procedures
Personnel and training – qualification and
training of personnel including verification of
experience and approval by regulatory
bodies
These documents do not reference these
sections as mutually exclusive – they all work
together to provide a compliant grouting system
to meet the primary objective of delivering a
durable concrete structure.
Even though available international documents
have different geographic markets, they are all
very similar in their themes. Having said this,
they also have slightly different testing criteria
and this is the reason that selecting isolated
sections for use in New Zealand is not
necessarily a productive way forward.
Each of the main items is elaborated on below.
It is not possible to cover the detail of each but
the main points are highlighted. The first item is
chosen to be the testing as this is the main
driver behind finding a grout which will primarily
comply.
Testing
The general testing regime is to ensure
suitability of the grout and this may involve
proving tests (either in a laboratory or on site),
suitability tests (generally on site) and
acceptance tests (on site). Additionally, some
countries require system type testing with
approvals given by regulatory authorities.
Proving tests are usually detailed for special
projects and are designed to verify grout
performance and the completeness of the filling
of the ducts, particularly at anchorages and high
points where air voids may form. In addition to
all the regular testing, proving tests also involve
physical dissection and examination of the trial
ducts and anchorages to verify compliance.
Some countries require prestressing systems to
undergo rigorous testing with independent
certification, which may include grouting.
Figure 1 depicts proving tests being performed
on some large tendons and tendon inspection to
confirm that strands are completely grouted.
The simple vertical tube test is illustrated in
Figure 2. The presence of this strand provides a
passage for any bleed water to rise to the
surface. A vertical or inclined tube test may be
carried out and the inclined test is essentially a
larger-scale test which further replicates the use
of multiple strands and orientation of a tendon in
practice.
single 12.7mm
dia. strand
tube approx.
1000mm high
tube
60-80mm dia.
Figure 2: Vertical wick induced bleed test
Figure 1: Full scale proving test and inspection
Suitability tests are carried out on site and
include testing strength, bleeding, volume
change, fluidity (flow time), density and
sedimentation and demonstrating compliance
with the specified limits.
It is extremely
important that the same equipment is used for
suitability tests as is to be used for the project
grouting.
The inclined tube test is illustrated in Figure 3.
There is ongoing development with regard to the
inclined tube test as it is recognised that it is
more difficult to conduct and a simple vertical
test may be representative and more applicable
for site conditions.
Acceptance testing is routinely carried out on all
projects
during
grouting
operations
to
demonstrate compliance and consistency with
the project requirements and to confirm that the
required durability can be achieved. The testing
includes strength, density, bleeding, volume
change and fluidity.
For obvious reasons, the key area of interest
from a materials performance perspective is the
bleed test. Experience has shown that the
starting point for demonstrating compliance with
international grouting standards is the bleed test
and the compliance threshold is now set at a
level 0.3% in most documents (compared with
the NZ Standard threshold of 2%). The new
protocols have also introduced a “wick induced”
bleed test to replicate the wick action created by
prestressing strand which is present in the duct.
Figure 3: Inclined tube bleed test
The dilemma with this overall testing regime is
that there are many different forms of wickinduced bleed tests and the actual grout testing
is very sensitive to the particular requirements of
each test.
A summary table is shown in Figure 4 to
illustrate the different types of test which exist in
various standards and guidelines.
Test Method
Cylinder Dia.
(mm)
Cylinder
Height
(mm)
Strand
Bleed
Volume Change
European Standard prEN 445:2007
Grout for Prestressing Tendons – Test
Methods
60-80
1000
Single 900mm length
Dia. not specified
< 0.3%
(at 3 hrs)
-1 to +5%
(prEN447:2007)
fib Bulletin 20, 2002
60-100
1500
Multiple 16mm dia.
to fill approx 30% of
cross sectional area
of duct
< 0.3%
(at 3 hrs)
-0.5 to +5%
Federal Highway Administration
ASTM C940 Modified
800ml in a graduated
measuring cylinder
Single 12.7mm
strand x 500mm
0.0%
(at 3 hrs)
0.0% to 0.1% at 24
hours
< +0.2% at 28 days
Concrete Institute of Australia
Recommended Practice: Grouting of
Prestressing Ducts, 2007
ASTM C940 Modified
Similar to
ASTM C940
Modified
Approx
1000mm
15.2mm single
strand x 1000mm
< 0.5%
< 2% at 3 hours
BBR Grouting training manual
60-80
1000
Single 900mm
< 0.3%
-0.5 to +5%
Figure 4: Grout “Wick Induced” Bleed Test - Comparison of Test Methods
As previously noted, NZS 3109 does not require
a wick induced test and hence the compliance
criteria are drastically different. Grouting trials in
New Zealand have shown that common grouts
will not comply with the bleed thresholds for any
of the wick tests shown in Figure 4. Trials have
also shown that there is significant variation in
the results when using fib Bulletin 20 wick
requirements which require multiple strands to
be inserted into the testing tube – as opposed to
other tests which only require single strands.
There are mixes which will pass the bleed test
using the single strand but will not pass the test
when multiple strands are used.
It is significant to note that the Concrete Institute
of Australia Recommended Practice document
places the bleeding threshold at 0.5% as
opposed to 0.3% and additionally nominates a
vertical tube test.
The document provides
specific commentary on this point and outlines
that the requirement of a maximum of 0.5%
bleed is achievable consistently on site. We can
read into this that perhaps the 0.3% threshold
was considered to be too much of a change, not
necessarily required for the Australian
environment and not able to be consistently
achieved on site.
The tests for strength, volume change, fluidity,
sedimentation and density are all relatively
similar to what has been seen previously in New
Zealand and no further detail is included in this
paper. Information on these tests can be readily
accessed from the reference documents as
noted at the end of this paper.
Design Detailing
There is a greater tendency to specifically detail
the requirements for ducts, grout inlets and
outlets, vents and caps. Documents deal with
both steel and plastic ducts and make reference
to the diameter of duct, nature of corrugations
and pressure ratings for couplings, inlets, outlets
and vents. These details have obviously been
developed based on experience so that the
guidelines can be followed to maximise the
performance of the grout when it is injected.
They do not override any project specification
but would certainly demonstrate what is
considered to be best practice.
Personnel
involved with this type of work are expected to
be suitably qualified and familiar with the
detailing for these items.
Grout Materials and Mix Design
The base materials include cement, admixtures
and water. Cement used for grouting should be
ordinary Portland cement consistent with local
standards. Chloride and sulphate constituent
limits are usually stipulated and the cement must
not contain any substances harmful to
prestressing strand.
With the stringent thresholds stipulated for
bleed, there are usually tighter controls on the
type of admixtures used. Admixtures would
usually include plasticisers, stabilisers and
retarding agents which improve:
• flowability for given W/C ratio
• elimination of bleed water
•
•
•
prevention of segregation in high pressure
grouting
retarding of the setting of grout
ensuring stability of the grout
Only well proven admixtures should be used and
these would obviously be subject to rigorous
testing as part of the proving, suitability and
project or system approval process.
The mix design is very much performance based
and is required to produce a grout which has
high bleed resistance, low shrinkage and high
fluidity.
Grouts must comply with the
performance requirements relating to strength,
bleeding, volume change and fluidity as
specified so trials, pre-approvals, equipment and
trained personnel all link integrally with the
chosen mix design. There is a greater emphasis
on new generation or “special” grouts and these
are most likely to involve pre-bagged and
proprietary products. The nature of the new
international grouting guidelines would appear to
place common grouts out of contention for most
post-tensioning work.
If a filtered down
specification was considered, then common
grouts may be able to comply although this is
not the trend seen in the documents reviewed.
prescriptive procedures for how this should be
best carried out and under what circumstances.
It is quite a shift in philosophy to have such
detailed guidelines for this aspect of the grouting
work but the organisations involved in preparing
this information obviously determined that it was
vitally important to prescribe the requirements.
In this way, all grouting operations could be
benchmarked to a certain standard and there
would be little left open to interpretation. It
actually makes it easier for personnel involved in
grouting operations to be trained and certified
and there is a fairly standard set of guidelines to
abide by. Clients can also benefit because they
can apply pre-approval processes based on
universal and industry regulated best practice.
Having said of all of this, the only way that the
recommended practices can be effective is for
supervising engineers and other regulatory
bodies to check that the guidelines are being
adhered to and demand verification of
compliance. This takes the process to a new
level where there has to be evidence of
compliance and practitioners have to be
experienced, trained with systems pre-approved
and certified by regulatory bodies.
Grout Production and Grouting Operations
Personnel and Training
It would be fair to say that the international
documentation relating the actual mixing and
injection of grout has been compiled based on
experience and the best practice to employ to
mitigate problems in almost every situation that
might be encountered. This same voice of
experience clearly espouses that grouting is a
critical post-tensioning activity that must be
carried out under supervision of a qualified posttensioning supervisor and include personnel
who are appropriately trained and experienced.
All of the international best practice documents
have an underlying and openly stated theme
that grouting of post-tensioning ducts needs
proper execution by appropriately trained
personnel with supervision of works by qualified
and experienced people. Assurance of the
quality of grout can only be achieved by
experienced, well qualified and trained
personnel.
As such, the qualification and
training of grouting personnel is of prime
importance. Many of the main post-tensioning
companies operate training/QA schemes and in
some countries there are certification schemes
in force.
The requirements for mixing and pumping, type
of equipment, back-up equipment, grouting
procedures, grouting pressures and trouble
shooting is very prescriptive as there is a known
expectation of how grouting operations should
be carried out. There is little left to chance and
the grouting procedure section of most
guidelines
and
recommended
practice
documents reads more like an operations
manual than a code.
There are also procedures recommended for
special grouting applications such as would be
used for vertical tendons or long horizontal
tendons.
In some cases vacuum grouting
techniques are stipulated and there are again
Certification schemes are very much in force in
Europe under the new post-tensioning system
protocols and certification of post-tensioning
system suppliers is a mandatory requirement
and requires a European Technical Approval
(ETA).
In conjunction with post-tensioning
system ETA’s is an inseparable requirement that
these certified systems are installed by
approved post-tensioning specialists which
employ suitably qualified personnel.
These same initiatives are now filtering into
Australia. With respect to grouting alone, the
Concrete Institute of Australia Recommended
Practice Grouting of Prestressing Ducts defines
the roles of a post-tensioning supervisor and in
some states formal approval of such personnel
is required from the state road authority. This
reflects the trends in Europe and reinforces the
emphasis being placed on the training,
experience and certification of skilled specialists.
•
•
•
RECOMMENDATIONS FOR NEW ZEALAND
The basic codes for grouting of post-tensioned
structures in New Zealand are now quite old and
international experience has shown that certain
aspects of these older codes are now outdated
and arguably inadequate for producing the most
durable structures into the future. The New
Zealand
environment
is
arguably
less
aggressive than those found in Europe and the
USA but the desire to design and construct more
durable structures in no less prevalent.
Designers in New Zealand are starting to
introduce new requirements into specifications
to take the latest thinking into account but this
may need a more structured and detailed
approach to ensure that all aspects of the
revised grouting practice are considered.
The two relevant international documents of
interest would appear to be fib Bulletin 20 (2002)
and
Concrete
Institute
of
Australia
Recommended Practice for Grouting of
Prestressing Ducts (2007).
From a code
perspective, the draft European Standards
prEN445, 446 and 447 should also be
considered as key documents.
Summary suggestions for advancing New
Zealand practice in this direction would include:
•
•
•
Assemble a working group to examine the
requirements
of
the
Australian
Recommended Practice document with a
view to adopting this as a best practice
guide for NZ projects. This group should
also evaluate whether the European
Standards prEN445, 446 and 447 should be
adopted.
Identify the aspects of these documents
which may conflict with NZS 3109 and
prepare an industry standard addendum to
correct these. This would include a check of
the codes which are cross referenced to
Australian and American Standards to
ensure consistency.
Prepare standard revisions to the guidelines
to amend any specific reference to
approvals required from Australian Road
Authorities.
•
Examine the case for pre-approving grouting
systems and the level of qualification and
certification that would apply to relevant
personnel involved in grouting.
Determine the types of projects or structures
that these guidelines might be applicable to.
Consult
with
industry
to
discuss
implementation of these recommendations
and determine a timeframe for adopting
them as industry recommendations.
Liaise with NZ Concrete Society as a
possible vehicle to seek industry comment
and disseminate information. The same
types of industry organisations in other parts
of the world appear to have played key roles
in
coordinating
developments
and
implementing changes.
The steps as noted above would necessarily
involve consultation with bridge designers and
Transit at an early stage so that requirements
could be integrated with the Transit Bridge
Manual and any future bridge projects as
deemed appropriate.
CONCLUSIONS
Whilst no single protection layer will guarantee
durability, a good quality grout and good
grouting practice are of prime importance for the
robustness of any post-tensioning installation.
Grout can provide excellent protection for posttensioned structures – even more than any other
protection layer. But it needs to be recognised
as a total approach which is well understood by
all related parties with appropriate training. The
current method of utilising the existing NZ
Standard and adding to this with isolated
extracts from more recent international
documents for materials testing (bleed only) is
not considered the most effective way of
achieving more durable structures.
Early
workshop studies conducted in Europe focused
on a total solution approach with input from a
wide cross section of the post-tensioning
industry. Nothing has changed in this regard
and it is more imperative than ever that the
adoption of new designs, materials, testing
regimes and execution techniques be well
understood by the people carrying out the work.
We don’t need to reinvent the wheel in New
Zealand – there is a high level of appropriate
documentation and experience available for our
use. In many respects, the changes initiated in
the UK in the 1990’s and subsequently adopted
in other parts of the world takes the form of
licensed building practitioners – something that
New Zealand has embarked upon in some areas
of the industry. This type of work was
recognised as something which demanded a
high level of training and expertise and as such
the practitioners and methods of application
needed to be approved and qualified. To what
extent are we prepared to adopt this and to what
extent are we prepared to risk the future
durability of our structures by not adopting this?
A partial uptake on the recommended practice in
this field will surely only result in partial success
at best. Most countries around the world are
recognising the value and importance in abiding
with best practice guidelines and the critical
nature of having a full understanding of the
whole process – there is a strong case to
suggest that it’s time to pay more attention to
them here.
•
European Committee for Standardisation.
2003. Workshop Agreement CWA 14646
January 2003: Requirements for the
installation of post-tensioning kits for
prestressing of structures and qualification
of the specialist company and its personnel.
•
European Organisation for Technical
Approvals. 2002. ETAG 013 Guideline for
European Technical Approval of posttensioning Kits for Prestressing of concrete
Structures. June 2002.
•
International Federation for Structural
Concrete (fib) 2002. fib Bulletin 20 Guide to
good practice – Grouting of tendons in
prestressed concrete: July 2002.
•
European Committee for Standardisation.
EN934-4:2001 Admixtures for concrete,
water and grout.
•
American
Post-tensioning
Institute.
Guidelines Specification for Grouting of
Post-tensioned Structures: 2001.
REFERENCES
•
Concrete Institute of Australia. 2007.
Recommended
Practice
Grouting
of
Prestressing Ducts.
•
European Standard 2007. prEN445:2007
Grout for prestressing tendons – Test
methods.
•
European Standard 2007. prEN446:2007
Grout for prestressing tendons – Grouting
procedures.
•
Standards New Zealand. 1997. Concrete
Construction. NZS3109:1997
•
European Standard 2007. prEN447:2007
Grout for prestressing tendons – Basic
requirements.
UK Concrete Society. 1996. Technical
Report TR47: Durable Post-tensioned
Concrete Bridges
•
UK Concrete Society. 1996. Concrete
magazine feature “A moratorium lifted”
November/December:1996
•
•
BBR VT International Ltd. Grouting Training
Manual. 2007