IDENTIFICATION OF THE UNCERTAIN EVENTS IMPACTING ON
CONSTRUCTION TIME OF SOUTH AFRICAN HIGHWAY PROJECTS
Alireza MOGHAYEDI1, and Abimbola WINDAPO2
1
Department of Construction Economics and Management, University of Cape Town,
South Africa, Email: MGHALI001@myuct.ac.za
2
Department of Construction Economics and Management, University
of Cape Town, South Africa, Email: Abimbola.Windapo@uct.ac.za
ABSTRACT
This article examines the uncertain events encountered in the construction process of
highway projects in South Africa, so as to evaluate their impact on the construction time
of such projects. The rationale for this examination stems from the view held by scholars
that highways are complex projects initiated in dynamic environments, which are often
beset by different uncertainties and a lack of appropriate evaluation of the uncertain
events that occur during the construction process. The research made use of a review of
existing literature in the area of uncertainty management and modelling in infrastructure
projects, to guide the direction of the study, brainstorming, and interviews conducted
with highway experts to identify the factors of uncertainty that impact construction time
on infrastructure projects. A simple uncertainty matrix for South African highway
projects was developed using a quantitative model and descriptive statistics. It emerged
from the study that the uncertain events that affect the construction time of highway
projects are distributed across economic, environmental, financial, legal, political, social
and technical factors. Also, it was found that each factor contains several uncertain
events, which impact on construction time differently, through a combination of the
uncertain events of the individual construction activities. Based on the findings, it can
be concluded that construction time on South African highway projects is significantly
related to the social and technical factors of uncertainties. The matrix developed will be
useful in modelling uncertainty of the cost and time of individual construction activities
in highway projects.
Keywords: construction time, highway projects, South Africa, uncertainty
1.
INTRODUCTION
Highway construction projects are subject to risks and uncertainties (Moret and
Einstein, 2016). There are various risks and uncertainties existing in highway
construction projects that affect construction performance differently. Risks have
different probabilities of occurrence that impact project performance (Walker et al.,
2003), causing schedule delays or cost overruns (Moghayedi, 2016; Chapman, 2006;
Wang and Chou, 2003; Zayed and Halpin, 2004). The number and the importance of
such events depend on the size and the complexity of the construction project
(Zavadskas et al., 2010). Highway projects are one of the most dynamic, challenging,
2146
and complex construction projects, because they are exposed to different risks (Mills,
2001). According to Flyvbjerg (2007), there is more uncertainty in highway projects
than there is in other construction projects, because of the unique features of such
projects, including complexity in the long duration of the construction, the dynamic
nature of the process, the repetitive linear nature of such projects, and the mobile nature
of the construction sites. Uncertainty affecting construction projects has long been
recognised by researchers as a major obstacle to achieving the objectives of the project,
and as a cause of low levels of productivity (Antunes and Gonzalez, 2015; Bloom, 2014;
Childerhouse and Towill, 2004; Moret and Einstein, 2016).
Uncertainty means an unknown phenomenon (Walker et al., 2003). It is associated with
the location, it is project-specific, and it has no root causes that can be generalised
(Ramanathan et al., 2012). Therefore, there is an obvious need to effectively anticipate,
identify and classify the uncertain events on different locations and projects to assess
their influence on the objectives of construction projects. Uncertainty assessment
involves identifying, evaluating and modelling various uncertain events in the
construction process of highway projects, and developing a model for quantifying the
impact of different events on the objectives of the project.
The magnitude of the influence of uncertainty can be assessed by two parameters,
namely probability of occurrence, and severity of the event (Gadd et al., 2003; ISO,
2009; Project Management Institute, 2013). Quantification of these factors with
classical methods, such as probability analysis and influence diagrams, is very difficult
(Zeng et al., 2005). Efficient applications and quantification techniques are difficult and
complex, and, furthermore, exact data are required (Winch, 2010). Unfortunately, such
data either do not exist at all or are hard to obtain. Furthermore, most of the classical
mathematical assessment methods, such as differential equations, are not able to
examine the relationship between input variables and an output variable, and they are
not well suited for uncertain problems (Youssef, 2004). Stepwise regression analysis
(SRA), on the other hand, is used in modelling to examine the strength and the direction
of the relationship between each dependent variable and an independent variable, and
the results indicate whether this relationship is statistically valid. Also, SRA is able to
estimate the value of dependent variable when the independent variables are known.
Therefore, this current research examines the uncertain events in the construction of
highway projects in South Africa, and whether there are key events that have a
significant impact on the completion time of such projects, with the aim of developing
SRA models to assess the impact of uncertainty on the completion time of highway
construction projects.
2.
LITERATURE REVIEW
The effect of uncertain events on the objectives of infrastructure projects has been
identified in several works of literature (Anderson et al., 2007; Antunes and Gonzalez,
2015; Barker and Haimes, 2009; Moret and Einstein, 2016; Renuka et al., 2014).
Occurrence of uncertain events in highway construction projects is greater than in other
construction projects, due to the unique features of such projects, including complexity,
the long duration of the construction, the dynamic nature of the process, the repetitive
linear nature of such projects, and the mobile nature of the construction sites (Flyvbjerg,
2007). Due to the peculiar nature of uncertainty, there is a need to identify and classify
the uncertain events and their factors, using the breakdown structure and the risk and
uncertainty management process to assess their impact.
2147
One of the most comprehensive studies in the field of uncertainty factors identification
was conducted by Aziz and Abdel-Hakam (2016). They explored 293 disruptive events
as delay causes of road construction projects in Egypt under 15 major groups. Another
noteworthy study was conducted by Odediran and Windapo (2017). They identified 81
risks in African construction markets under five major factors, namely political, social,
economic/financial, procurement, and design and construction. Similarly, Assaf and AlHejji (2006) evaluated 73 uncertain events that cause delays in different types of large
construction projects in Saudi Arabia under the following factors: project, owner,
contractor, design, materials, equipment, labour, and external.
After an extensive review of literature in the field of risk and uncertainty in construction
projects, the seven uncertainty-related factors most common to researchers in the field
were identified. They are presented in Table 1.
Table 1: Proposed uncertainty factors
Factor
Description
Sources
Economic
Issues or concerns associated
with the macroeconomic impact
of the community and the
region in which the construction
project is to be located
Banaitiene and Banaitis, 2012;
Dey, 2001; Iyer and Jha, 2005;
Kuo and Lu, 2013; Saqib et al.,
2008; Tah and Carr, 2000;
Wang and Yuan, 2011;
Zavadskas et al., 2010
Environmental Issues associated with the
environmental
problems,
concerns
and
activities
confronting the project
Banaitiene and Banaitis, 2012;
Ehsan et al., 2010; Iyer and Jha,
2005; Saqib et al., 2008; Tah
and Carr, 2000; Wang and
Yuan, 2011
Financial
Issues or concerns associated
with the financing of the
project. Several researchers
emphasise
financial
uncertainties as one of the
important factors affecting
infrastructure project outcomes
Banaitiene & Banaitis, 2012;
Bunni, 2003; Dey, 2001; Ehsan,
Mirza, Alam, & Ishaque, 2010;
Fang, Marle, Zio, & Bocquet,
2012; Saqib, Farooqui, & Lodi,
2008; Shen, Wu, & Ng, 2001;
Taghipour, Seraj, Hassani, &
Kheirabadi, 2015; Tah & Carr,
2000; Zayed, Amer, & Pan,
2008
Legal
Issues or concerns associated Bunni, 2003; Shen et al., 2001;
with the significant legal Zou et al., 2007
consequences that flow from
legal actions attributable to the
project
Political
Issues or concerns associated
with the local, regional and
national political and regulatory
situation
confronting
the
project. Various researchers
identify political uncertainty as
a major factor affecting the
2148
Baloi
and
Price,
2003;
Banaitiene and Banaitis, 2012;
Dey, 2001; Ehsan et al., 2010;
Iyer and Jha, 2005; Saqib et al.,
2008; Taghipour et al., 2015;
performance of infrastructure Tah and Carr, 2000; Zavadskas
projects.
et al., 2010; Zayed et al., 2008
Social
Issues or concerns associated Kuo and Lu, 2013; Saqib et al.,
with the social and cultural 2008; Wang and Yuan, 2011;
impacts of the community and Zavadskas et al., 2010
the region in which the
construction project is to be
located
Technical
Issues or concerns associated
with the technology used in the
project
by
different
stakeholders
during
construction
Banaitiene and Banaitis, 2012;
Bunni, 2003; Dey, 2001;
Dikmen et al., 2007; Ehsan et
al., 2010; Fang et al., 2012;
Mahendra et al., 2013; NietoMorote and Ruz-Vila, 2011;
Saqib et al., 2008; Shen et al.,
2001; Tah and Carr, 2000;
Wang and Yuan, 2011;
Zavadskas et al., 2010; Zayed et
al., 2008
Through a review of the literature, a list of uncertain events that impact on the
completion time of construction projects was compiled. These events were analysed
and ranked according to the number of times cited. The top 20 uncertain events cited in
the literature which were adapted to the current study are listed in Table 2.
Table 2: Top 20 uncertain events cited in the literature
Dey (2001)
Assaf and Al-Hejji (2006)
Technical
Zou et al. (2007)
Availability
of skilled
labour
Saqib et al. (2008)
Technical
Zayed et al. (2008)
Inaccurate
management
or supervision
Ehsan et al. (2010)
Technical
Nieto-Morote and Ruz-Vila (2011)
Availability
of materials
Kuo and Lu (2013)
Environmental
Fang et al. (2012)
Weather
Banaitiene and Banaitis (2012)
Factor
Mahendra et al. (2013)
Marzouk and El-Rasas (2014)
Taghipour et al. (2015)
Aziz and Abdel-Hakam (2016)
Santoso and Soeng (2016)
Odediran and Windapo (2017)
Adam et al. (2017)
Event
2149
Total
16
15
14
14
Health &
safety
Technical
Materials
delivery
Technical
Construction
methods
Technical
Availability
of equipment
Technical
Cash flow
difficulties
(contractor
finance)
Financial
Design,
drawings,
specifications,
and samples
Technical
Incompetent
contractor/
subcontractor
Technical
Low level of
productivity
Technical
Payment
delays
Financial
Planning and
scheduling of
project by
contractor
Technical
Difficulty of
schedule
Technical
Lack of
capital by
owner
Financial
Change order
(change in the
scope of the
project)
Technical
Legal/
industrial
disputes
between
various
parties in the
construction
project
Legal
Communication/
coordination
between
construction
parties
Technical
Fluctuation of
prices of
Economic
13
12
12
12
12
11
10
10
10
10
9
9
2150
8
9
8
8
materials
and/or
equipment
It can be seen from Table 2 that the most cited uncertain events are technical-related.
To verify the existence of these uncertain events in highway construction projects in
South Africa, the research conducted further investigations. The methods used are
presented in the following section.
3.
RESEARCH METHODOLOGY
The study made use of a sequential mixed-methods research approach in identifying the
uncertain events and their main factors and assessing the impact of uncertainties on the
completion time of highway construction projects in South Africa. Brainstorming
sessions were held with six highway experts who have more than 25 years of experience
in South African highway construction projects. The highway expert panel reviewed
and modified the uncertain events identified in the literature to appropriately reflect the
events occurring on South African highway construction projects. The expert panel also
grouped these events into seven uncertainty factors, as seen in Table 1.
A survey questionnaire was designed on a five-point linguistic Likert-scale form to
assess the impact size of confirmed uncertain events in highway construction projects
in South Africa. The questionnaire was administered to 32 highway project managers
with a minimum of 20 years of experience in the South African construction industry,
to rate the probability of occurrence and the severity of each uncertainty on the
completion time of a highway project.
4.
DATA ANALYSIS
To evaluate the effect of uncertainties on construction time of highway projects using
collected data on the probability of occurrence and the severity of uncertainties from
the six highway experts, the ISO (International Standards Organization) 31000 impact
matrix was utilised (ISO, 2009). The ISO (2009) defined the impact size of an event as
a function of the probability of occurrence and the severity of that event should it occur.
Table 3 shows the probability of occurrence and the severity as two input variables, and
relevant impact size as the output variable.
2151
Table 3: Impact size matrix
Probability of occurrence
Severity
4.1
Insignificant Minor
Moderate Major
Catastrophic
(1)
(3)
(5)
(7)
(9)
Rare (.1)
Minimal
Minimal
Low
Low
Moderate
Unlikely (.3)
Minimal
Low
Moderate Moderate High
Possible (.5)
Low
Moderate Moderate High
High
Likely (.7)
Low
Moderate High
High
Extreme
Almost
certain (.9)
Moderate
High
Extreme
Extreme
High
Developing a stepwise regression model
The main objective of this study is to quantitatively analyse and assess the impact of
uncertainties on completion time of highway construction projects, through numerical
analysis of the uncertainty variables. Stepwise regression analysis (SRA) is an extension
of multiple regression analysis. The SRA model is a mathematical model used in
estimating the relationship between a dependent variable and independent variables,
with a strong mathematical background. SRA models have been used extensively in
different areas of construction management, particularly assessing risk and uncertainty,
assessing the critical factors affecting cost performance of Ethiopian public construction
projects (Sinesilassie et al., 2018), modelling the construction risk ratings and
estimating contingencies in highway projects (Diab et al., 2017), identifying the success
factors for public-private partnership projects in Korea (Yun et al., 2015), evaluating
project risks in Iran (Ebrat and Ghodsi, 2014), evaluating the risk factors leading to cost
overruns in highway construction projects in Australia (Creedy et al., 2010), analysing
the risk perception of build-operate-transfer road project participants in India (Thomas
et al., 2003), developing models to forecast the actual construction cost and time
(Skitmore and Ng, 2003), and designing a multivariate analysis to build project success
factors in Hong Kong (Chan et al., 2001).
The impact size of uncertain events as the dependent variable is a function of two
independent variables (probability of occurrence, and severity) of relative uncertainty
(ISO, 2009), as shown in Equation 1.
𝑈𝑛𝑐𝑒𝑟𝑡𝑎𝑖𝑛𝑡𝑦 𝑖𝑚𝑝𝑎𝑐𝑡𝑖 = 𝑎𝑖 𝑝 + 𝑏𝑖 𝑠 + 𝑟𝑖
(Equation 1)
Where ri is a constant value. ai and bi represent regression coefficients of the independent
variables.
Because each input variable can have a low correlation with the output variable, the
SRA model was used in this study. Table 4 presents the values of the correlation
coefficients.
2152
Table 4: Correlation coefficients among the input and output variables
Probability
Severity
Impact
Probability 1
Severity
0
1
Impact
0.685061
0.685061
1
Table 4 shows the low correlation between the independent variables and the dependent
variable.
The general SRA model for impact size, based on the impact size matrix in Table 3, has
been developed to predict the impact size of each uncertainty on cost and time of
highway construction projects. The SRA model test details are shown in Table 5.
Table 5: Regression test details
Regression statistics
Multiple R
0.968822
R-squared
0.93861607
Adjusted Rsquared
0.93303571
Standard error 0.31622777
Coefficient
Standard
error
t-statistic
P-value
Intercept
0.18
0.170294
1.056996
0.301982
Probability
2.9
0.223607
12.96919
8.82E-12
Severity
0.29
0.022361
12.96919
8.82E-12
Table 5 reveals that the correlation value (R-Squared) of the model is close to 1, and
the P-value is very low (<0.05). The very low P-value indicates the statistically
significant relationship of each independent variable to the dependent variable of the
model, and the closeness of the R-value to 1 verifies the close fit of the estimated output
model to real data. The developed stepwise regression analysis model for general
uncertainty impact size is outlined in Equation 2.
𝑈𝑛𝑐𝑒𝑟𝑡𝑎𝑖𝑛𝑡𝑦 𝑖𝑚𝑝𝑎𝑐𝑡 = 2.9 × 𝑝 + 0.29 × 𝑠 + 0.18
(Equation 2)
Similar steps were repeated to develop the SRA models for each uncertainty impact on
construction time of highway projects. To assess the optimum impact size of each
uncertainty, the optimum values of two independent variables (probability of
occurrence, and severity of event) are identified using sensitivity analysis, and are
inserted to develop the SRA models. For instance, the maximum probability of
occurrence (0.6625) and severity (5) value of event weather were inserted to develop
the SRA model (Y = 0.2915 + 2.9728p + 0.27905s), and the estimated impact size of
this uncertainty (3.66) on the completion time of highway construction projects. The
2153
impact sizes of all identified uncertainties on the completion time of highway
construction projects were estimated and ranked. Table 6 presents the top 20 events
with significant impact size on construction time of highway projects, from a ranking
perspective.
Table 6: Top 20 uncertain events with significant impact size on construction time of
highway projects
Code Event
Probability of Severity Impact
Rank
occurrence
of event size
TG11 Latent ground conditions
0.84375
8.3125 4.94
1
TCS6 Inaccurate time and cost estimation
0.79375
8.3125 4.78
2
3
TG5
Inadequate planning and scheduling of
project by contractor
0.8125
7.6875
SO4
Rehabilitation of affected people
0.78125
7.8125 4.66
4
PL3
Human-made disaster (war, protest,
strike, etc.)
0.8125
7.4375
5
SO5
Disease (HIV, Ebola, etc.)
0.70625
6.8125 4.19
6
TG9
Change order by owner (scopes and
specifications)
0.73125
6.4375
7
TG4
Difficulty of schedule
0.55625
7.75
4.00
8
0.64375
5.5625 3.84
9
10
TCR5 Rework due to contractor errors
4.72
4.66
4.16
EN2
Natural disasters (earthquake, floods,
hurricane, etc.)
0.4125
7.9375
SO3
Social and cultural impacts
0.76875
4.375
3.81
11
TT1
Obsolete technology
0.58125
6.1875 3.78
12
LE9
Problem in dispute settlement due to law 0.625
5.6875 3.78
13
TCR4
Management or supervision of project by
0.66875
contractor
5.5
14
TL1
Low level of productivity
0.725
4.625
3.75
15
0.56875
6.1875 3.75
16
17
TM2 Materials delivery
3.81
3.78
TCS4
Design, drawings, specifications, and
samples
0.675
5.1875
PL1
Political situation
0.64375
5.6875 3.72
18
TCS3 Frequent design changes
0.60625
5.8125 3.72
19
TM3 Bad quality of materials
0.61875
5.5
20
3.75
3.72
It can be seen from Table 6 that the top three uncertain events, based on estimated
impact on completion time of highway construction projects, from a ranking
perspective, are latent ground conditions (4.94), inaccurate time and cost estimation
(4.78), and inadequate planning and scheduling (4.72). Likewise, latent ground
2154
conditions and inaccurate time and cost estimation are two uncertain events with
catastrophic consequences.
To evaluate the SRA models’ performance, the root-mean-square error (RMSE), the
mean absolute percentage error (MAPE), and the R-squared of 76 developed assessment
models were calculated. The results for the top 20 events in South Africa are presented
in Table 5.
Table 5: Performance evaluation of the SRA models for the top 20 events
Code
Model
P-value
R-squared
RMSE MAPE
TG11
Y = 2.9897 + 1.604p +
0.071255s
2.21e-10
0.784
0.244
0.0638
TCS6
Y = 1.3931 + 1.9967p +
0.21694s
1.01e-07
0.671
0.249
0.0481
TG5
Y = 0.89851 + 2.3235p +
0.25137s
3.56e-08
0.694
0.261
0.0533
SO4
Y = 0.5412 + 2.6448p +
0.26225s
7.5e-09
0.725
0.262
0.0537
PL3
Y = 0.80427 + 2.7748p +
0.21478s
3.7e-09
0.738
0.255
0.0518
SO5
Y = 0.064987 + 2.9907p +
0.29509s
2.85e-12
0.84
0.245
0.0521
TG9
Y = 0.88561 + 2.6217p +
0.21025s
2.1e-08
0.705
0.252
0.0556
TG4
Y = 0.88358 + 2.4275p +
0.22789s
2.21e-08
0.703
0.248
0.0557
TCR5
Y = 0.97812 + 2.1685p +
0.26421s
1.05e-06
0.613
0.237
0.0553
EN2
Y = 1.2336 + 2.0528p +
0.21823s
6.52e-07
0.626
0.251
0.0621
SO3
Y = 1.4539 + 1.8779p +
0.20912s
1.74e-07
0.658
0.24
0.0571
TT1
Y = 0.68305 + 2.7031p +
0.24679s
3.56e-09
0.739
0.259
0.0664
LE9
Y = 0.52521 + 2.481p +
0.29985s
1.55e-07
0.661
0.253
0.0628
TCR4
Y = 1.2381 + 2.0753p +
0.21005s
1.52e-07
0.661
0.253
0.0632
TL1
Y = 0.75 + 2.3438p + 0.28125s 2.25e-08
0.703
0.286
0.0729
TM2
Y = 0.98332 + 2.0923p +
0.25482s
0.68
0.257
0.0660
6.62e-08
2155
TCS4
Y = 0.92489 + 2.6345p +
0.20179s
3.96e-08
0.691
PL1
Y = 0.80167 + 2.2434p +
0.25897s
1.08e-08
0.718
TCS3
Y = 0.92834 + 2.1309p +
0.25781s
2.62e-08
0.7
TM3
Y = 0.24167 + 3.1541p +
0.27735s
1.54e-10
0.789
0.253
0.0635
0.251
0.0618
0.259
0.0669
0.248
0.0620
The small value of errors (RMSE and MAPE) and P-values (p<.01) proved the
reliability and statistical significance of all the developed models. However, the fit of
the estimated values to real data varies from 0.442 to 0.954. Fifty-two of the developed
models have a strong fit (r>0.7), 22 models have a moderate fit (.5<r<.7), and two of
the models have a low fit to the real data (Moore and Kirkland, 2007).
Furthermore, the estimated impact size of uncertain events was classified into five
groups, namely extreme, high, moderate, low, and minimal (see Table 7).
Table 7: Impact size groups
Group
Impact Events
size
Extreme
I ≥4
Latent ground conditions; inaccurate time and cost estimation;
inadequate planning and scheduling of project by contractor;
rehabilitation of affected people; human-made disaster; disease;
change order by owner; difficulty of schedule
High
3≤I<4
Rework due to contractor errors; natural disasters; social and
cultural impacts; obsolete technology; problem in dispute
settlement due to law; management or supervision of project by
contractor; low level of productivity; materials delivery; design,
drawings, specifications, and samples; political situation;
frequent design changes; bad quality of materials; security; new
technology adoption; corruption; remote location cost;
availability of skilled workers; availability of materials; change
order; delays in decision-making; weather; right of way
acquisition; payment delays; fluctuation of prices of materials
and/or equipment; health & safety; financing by contractor,
cultural heritage issues; inaccurate investigation of construction
site; monopoly of material and/or equipment suppliers; low
efficiency of equipment; unreliable supplier of material; lack of
technical staff; mistakes in design and/or specifications;
encroachment problems; lack of capital by owner; poor quality
of workmanship; planning and scheduling of project by
contractor; frequent change of subcontractors; contract failure –
new contract establishment cost; terrain or topographical;
construction methods; lack of technical staff; ineffective delay
penalties;
poor
communication/coordination
between
construction parties
2156
Moderate 2≤I<3
Absenteeism of labour; incompetent contractor/subcontractor;
legal/industrial disputes between various parties in the
construction project; changes in government regulations and
laws; inadequate monitoring and supervision; poor financial
control; type of contract; availability of equipment; deficient
documentation; contractual claim; late delivery of equipment;
personal conflicts among labour; lack of experience in the line
of work; lack of experience in design and supervision;
fluctuation in foreign exchange rate; high cost of materials
and/or equipment; high tender price; changing of bankers’
policy for loans; high cost of labour; saturated market;
difficulties in importing equipment and materials
Low
1≤I<2
Slow mobilisation of equipment; tax and/or legal fees; size of
contract
Minimal
1<I
NONE
Key: I = impact size
Table 7 groups the uncertain events identified in South African highway projects, based
on their estimated impact on the completion time of projects.
5.
DISCUSSION OF FINDINGS
The current study modelled the existing uncertain events in South African highway
construction projects using stepwise regression analysis (SRA) to assess their impact
on the completion time of such projects. Impact assessment of uncertain events is
essential to prevent delays on the project before signs of delay begin to appear.
Comparison of the top 20 uncertain events from the literature review (see Table 2) with
the 20 events with the highest estimated impact in South Africa (see Table 3) revealed
that only seven events from this list are common with the top 20 cited events (inadequate
planning and scheduling of project by contractor (3rd), change order by owner (7th),
difficulty of schedule (8th), management or supervision of project by contractor (14th),
low level of productivity (15th), materials delivery (16th), and design, drawings,
specifications, and samples (17th)). The other 13 most-cited events are found to impact
the construction time of highway projects differently (availability of skilled workers
(25th), availability of materials (26th), weather (29th), payment delays (31st),
fluctuation of prices of materials and/or equipment (32nd), health & safety (33rd),
financing by contractor (34th), lack of capital by owner (43rd), construction methods
(49th), poor communication/coordination between construction parties (52nd),
incompetent contractor/subcontractor (54th), legal/industrial disputes between various
parties in the construction project (55th), and availability of equipment (60th)).
The study found that more than 70% of identified events impact on the completion time
of highway construction projects. The results presented in Table 7 revealed that eight
uncertain events (10.5%) have an extreme impact on completion time of highway
projects, 44 events (57.9%) have a high impact, 21 events (27.6%) have a moderate
impact, and three events (4%) have a low impact on construction time of highway
projects. This is evidence of the fact that the completion time of highway construction
projects in South Africa is very sensitive to uncertain events. These results are
consistent with those of previous studies. For instance, Adam et al. (2017), Assaf and
Al-Hejji (2006), Aziz and Abdel-Hakam (2016), Baloi and Price (2003), Fang et al.
(2012), Taghipour et al. (2015), Zayed et al. (2008), and Zou et al. (2007) also found
2157
that latent ground conditions was a key uncertain event impacting the construction time
of projects.
Also, the SRA model results indicate that inaccurate time and cost estimation,
inadequate planning and scheduling, changes to specifications, and difficulty of
schedule are the other four technical uncertain events that extremely affect completion
time of construction projects. These technical events were also identified in previous
studies (Assaf and Al-Hejji, 2006; Aziz and Abdel-Hakam, 2016; Bunni, 2003; Ehsan
et al., 2010; Gosling et al., 2012; Huang et al., 2002; Mahendra et al., 2013; Marzouk
and El-Rasas, 2014; Saqib et al., 2008; Zou et al., 2007). Human-made disaster and
disease emerged from the study as two political and social uncertain events with
extreme impact on construction projects in South Africa, which is consistent with the
findings of studies conducted by Aziz and Abdel-Hakam (2016), Marzouk and El-Rasas
(2014), and Odediran and Windapo (2017) in South Africa and Egypt.
6.
CONCLUSION
The current study adds to existing knowledge of construction management by including
an extensive literature review in the field of uncertainty in construction projects, it
established the uncertain events and uncertainty factors through brainstorming by a
highway expert panel, and it verified the probability of occurrence and severity of 20
events through gathering data from highway construction experts. A significant number
of the uncertainties were related to social and political factors. Therefore, it is
recommended that the companies pursuing highway construction in African countries
should seriously consider the social and political risks, along with the technical events,
when involved in this market. The study also developed stepwise regression analysis
models to assess the impact of each event on the completion time of highway
construction projects, and it classified these events into five groups, based on their
estimated impact.
This study is relevant to both practitioners and researchers. It provides practitioners with
a simple and straightforward tool to assess and prioritise the impact of uncertain events
on highway construction projects, and it provides researchers with a qualitative and
quantitative methodology and a mathematical model for use in evaluating the effect of
uncertain events on highway construction projects in South Africa. The SRA was used
in assessing the impact of uncertain events on highway construction completion time,
due to the fact that the model has a strong mathematical background and has been
employed in assessing risk and uncertainty in the field of construction management.
The study found the SRA model to be a reliable and statistically significant method for
assessing uncertainty on construction projects. However, the accuracy of the estimated
impact of some of the models is low. Therefore, to accurately estimate the impact of
these events, the study recommends using a systematic fuzzy inference system, such as
an adaptive neuro-fuzzy inference system (ANFIS).
The detailed analysis and estimated outputs from this research should be used as a
platform and a benchmark for future studies in highway construction in South Africa.
This platform should be utilised for estimating the duration of highway construction
projects accurately, by assessing the uncertain events that impact on the completion
time of each construction activity.
2158
7.
ACKNOWLEDGEMENTS
Funding from the National Research Foundation (NRF) towards this research is hereby
acknowledged. Opinions expressed, and conclusions arrived at, are those of the authors,
and are not necessarily to be attributed to the NRF.
This article was language-edited by a freelance language editor, Anthony Sparg. He has
edited several academic journal articles in the field of construction management. He has
an MA cum laude in African Languages (isiXhosa), an MA cum laude in Linguistics,
and a Higher Diploma in Education.
8.
REFERENCES
Adam, A., Josephson, P.-E.B. and Lindahl, G. (2017). Aggregation of factors causing
cost overruns and time delays in large public construction projects: Trends and
implications. Engineering, Construction and Architectural Management, 24(3),
393–406.
Anderson, S.D., Molenaar, K.R. and Schexnayder, C.J. (2007). Guidance for cost
estimation and management for highway projects during planning,
programming, and preconstruction (Vol. 574). Washington, DC: Transportation
Research Board.
Antunes, R. and Gonzalez, V. (2015). A production model for construction: A
theoretical framework. Buildings, 5(1), 209–228.
Assaf, S.A. and Al-Hejji, S. (2006). Causes of delay in large construction projects.
International Journal of Project Management, 24(4), 349–357.
Aziz, R.F. and Abdel-Hakam, A.A. (2016). Exploring delay causes of road construction
projects in Egypt. Alexandria Engineering Journal, 55(2), 1515–1539.
Baloi, D. and Price, A.D.F. (2003). Modelling global risk factors affecting construction
cost performance. International Journal of Project Management, 21(4), 261–
269.
Banaitiene, N. and Banaitis, A. (2012). Risk management in construction projects. In:
N. Banaitiene (ed.). Risk management―current issues and challenges (pp. 429–
448).
London:
InTech
Open
Science.
Available
at:
http://cdn.intechopen.com/pdfs-wm/38973.pdf
Barker, K. and Haimes, Y.Y. (2009). Assessing uncertainty in extreme events:
Applications to risk-based decision making in interdependent infrastructure
sectors. Reliability Engineering & System Safety, 94(4), 819–829.
Bloom, N. (2014). Fluctuations in uncertainty. Journal of Economic Perspectives,
28(2), 153–176.
Bunni, N.G. (2003). Risk and insurance in construction. 2nd ed. London: Routledge.
Chan, A.P.C., Ho, D.C.K. and Tam, C.M. (2001). Design and build project success
factors: Multivariate analysis. Journal of Construction Engineering and
Management, 127(2), 93–100.
Chapman, C. (2006). Key points of contention in framing assumptions for risk and
uncertainty management. International Journal of Project Management, 24(4),
303–313.
2159
Childerhouse, P. and Towill, D.R. (2004). Reducing uncertainty in European supply
chains. Journal of Manufacturing Technology Management, 15(7), 585–598.
Creedy, G.D., Skitmore, M. and Wong, J.K.W. (2010). Evaluation of risk factors
leading to cost overrun in delivery of highway construction projects. Journal of
Construction Engineering and Management, 136(5), 528–537.
Dey, P.K. (2001). Decision support system for risk management: A case study.
Management Decision, 39(8), 634–649.
Diab, M.F., Varma, A. and Panthi, K. (2017). Modeling the construction risk ratings to
estimate the contingency in highway projects. Journal of Construction
Engineering and Management, 143(8), 04017041.
Dikmen, I., Birgonul, M. T., & Han, S. (2007). Using fuzzy risk assessment to rate cost
overrun risk in international construction projects. International Journal of
Project Management, 25(5), 494-505.
Ebrat, M. and Ghodsi, R. (2014). Construction project risk assessment by using
adaptive-network-based fuzzy inference system: An empirical study. KSCE
Journal of Civil Engineering, 18(5), 1213–1227.
Ehsan, N., Mirza, E., Alam, M. and Ishaque, A. (2010). Notice of retraction: Risk
management in construction industry. Proceedings of the 3rd IEEE
International Conference on Computer Science and Information Technology
(ICCSIT). 9–11 July. Chengdu, China.
Fang, C., Marle, F., Zio, E. and Bocquet, J.-C. (2012). Network theory-based analysis
of risk interactions in large engineering projects. Reliability Engineering &
System Safety, 106, 1–10.
Flyvbjerg, B. (2007). Policy and planning for large-infrastructure projects: Problems,
causes, cures. Environment and Planning B: Urban Analytics and City Science,
34(4), 578-597.
Gadd, S., Keeley, D. and Balmforth, H. (2003). Good practice and pitfalls in risk
assessment. Research Report 151. Sheffield: Health & Safety Laboratory.
Gosling, J., Naim, M. and Towill, D. (2012). Identifying and categorizing the sources
of uncertainty in construction supply chains. Journal of Construction
Engineering and Management, 139(1), 102–110.
Huang, J., Negnevitsky, M. and Nguyen, D.T. (2002). A neural-fuzzy classifier for
recognition of power quality disturbances. IEEE Transactions on Power
Delivery, 17(2), 609–616.
International Organization for Standardization. (2009).
management—principles and guidelines. Geneva: ISO.
31000:2009.
Risk
Iyer, K., & Jha, K. (2005). Factors affecting cost performance: evidence from Indian
construction projects. International Journal of Project Management, 23(4), 283295.
Kuo, Y.-C. and Lu, S.-T. (2013). Using fuzzy multiple criteria decision making
approach to enhance risk assessment for metropolitan construction projects.
International Journal of Project Management, 31(4), 602–614.
2160
Mahendra, P.A., Pitroda, J.R. and Bhavsar, J.J. (2013). A study of risk management
techniques for construction projects in developing countries. International
Journal of Innovative Technology and Exploring Engineering (IJITEE), 3(5),
139–142.
Marzouk, M.M. and El-Rasas, T.I. (2014). Analyzing delay causes in Egyptian
construction projects. Journal of Advanced Research, 5(1), 49–55.
Mills, A. (2001). A systematic approach to risk management for construction.
Structural Survey, 19(5), 245–252.
Moghayedi, A. (2016). Improving Critical Path Method (CPM) by applying safety
factor to manage delays. Scientia Iranica. Transaction A, Civil Engineering,
23(3), 815.
Moore, D. S., & Kirkland, S. (2007). The basic practice of statistics (Vol. 2): WH
Freeman New York.
Moret, Y. and Einstein, H.H. (2016). Construction cost and duration uncertainty model:
Application to high-speed rail line project. Journal of Construction Engineering
and Management, 142(10), 05016010.
Nieto-Morote, A. and Ruz-Vila, F. (2011). A fuzzy approach to construction project
risk assessment. International Journal of Project Management, 29(2), 220–231.
Odediran, S.J. and Windapo, A.O. (2017). Risk-based entry decision into African
construction markets: A proposed integrated model. Built Environment Project
and Asset Management, 8(1), 91–111.
Project Management Institute. (2013). A guide to the project management body of
knowledge: PMBOK guide. Newtown Square, PA: PMI.
Ramanathan, C., Narayanan, S. and Idrus, A.B. (2012). Construction delays causing
risks on time and cost - a critical review. Construction Economics and Building,
12(1), 37–57.
Renuka, S., Umarani, C. and Kamal, S. (2014). A review on critical risk factors in the
life cycle of construction projects. Journal of Civil Engineering Research,
4(2A), 31–36.
Santoso, D.S. and Soeng, S. (2016). Analyzing delays of road construction projects in
Cambodia: Causes and effects. Journal of Management in Engineering, 32(6),
05016020.
Saqib, M., Farooqui, R.U. and Lodi, S.H. (2008). Assessment of critical success factors
for construction projects in Pakistan. Proceedings of the First International
Conference on Construction in Developing Countries (ICCIDC-1), “Advancing
and Integrating Construction Education, Research & Practice”. 4–5 August.
Karachi, Pakistan.
Shen, L.Y., Wu, G.W.C. and Ng, C.S.K. (2001). Risk assessment for construction joint
ventures in China. Journal of Construction Engineering and Management,
127(1), 76–81.
Sinesilassie, E.G., Tabish, S.Z.S. and Jha, K.N. (2018). Critical factors affecting cost
performance: A case of Ethiopian public construction projects. International
Journal of Construction Management, 18(2), 108–119.
2161
Skitmore, R.M. and Ng, S.T. (2003). Forecast models for actual construction time and
cost. Building and Environment, 38(8), 1075–1083.
Taghipour, M., Seraj, F., Hassani, M.A. and Kheirabadi, S.F. (2015). Risk analysis in
the management of urban construction projects from the perspective of the
employer and the contractor. International Journal of Organizational
Leadership, 4(4), 356–373.
Tah, J.H.M. and Carr, V. (2000). A proposal for construction project risk assessment
using fuzzy logic. Construction Management and Economics, 18(4), 491–500.
Thomas, A.V., Kalidindi, S.N. and Ananthanarayanan, K. (2003). Risk perception
analysis of BOT road project participants in India. Construction Management
and Economics, 21(4), 393–407.
Walker, W.E., Harremoës, P., Rotmans, J., Van der Sluijs, J.P., Van Asselt, M.B.A.,
Janssen, P. and Krayer von Krauss, M. P. (2003). Defining uncertainty: A
conceptual basis for uncertainty management in model-based decision support.
Integrated Assessment, 4(1), 5–17.
Wang, M.-T. and Chou, H.-Y. (2003). Risk allocation and risk handling of highway
projects in Taiwan. Journal of Management in Engineering, 19(2), 60–68.
Wang, J., and Yuan, H. (2011). Factors affecting contractors’ risk attitudes in
construction projects: Case study from China. International Journal of Project
Management, 29(2), 209-219.
Winch, G. M. (2010). Managing construction projects: An information processing
approach. 2nd ed. Chichester: Wiley.
Youssef, O.A.S. (2004). Combined fuzzy-logic wavelet-based fault classification
technique for power system relaying. IEEE Transactions on Power Delivery,
19(2), 582–589.
Yun, S., Jung, W., Han, S.H. and Park, H. (2015). Critical organizational success factors
for public private partnership projects – a comparison of solicited and
unsolicited proposals. Journal of Civil Engineering and Management, 21(2),
131–143.
Zavadskas, E.K., Turskis, Z. and Tamošaitiene, J. (2010). Risk assessment of
construction projects. Journal of Civil Engineering and Management, 16(1), 33–
46.
Zayed, T., Amer, M. and Pan, J. (2008). Assessing risk and uncertainty inherent in
Chinese highway projects using AHP. International Journal of Project
Management, 26(4), 408–419.
Zayed, T.M. and Halpin, D.W. (2004). Quantitative assessment for piles productivity
factors. Journal of Construction Engineering and Management, 130(3), 405–
414.
Zeng, J., An, M. and Chan, A. H. C. (2005). A fuzzy reasoning decision making
approach based multi-expert judgement for construction project risk analysis.
Proceedings of the 21st Annual Conference of the Association of Researchers in
Construction Management (ARCOM). 7–9 September. SOAS, University of
London.
2162
Zou, P.X.W., Zhang, G. and Wang, J. (2007). Understanding the key risks in
construction projects in China. International Journal of Project Management,
25(6), 601–614.
2163