DE19715773A1 - Rail network operating safety method - Google Patents
Rail network operating safety methodInfo
- Publication number
- DE19715773A1 DE19715773A1 DE19715773A DE19715773A DE19715773A1 DE 19715773 A1 DE19715773 A1 DE 19715773A1 DE 19715773 A DE19715773 A DE 19715773A DE 19715773 A DE19715773 A DE 19715773A DE 19715773 A1 DE19715773 A1 DE 19715773A1
- Authority
- DE
- Germany
- Prior art keywords
- belay
- devices
- rail
- rail network
- belay devices
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
- 238000000034 method Methods 0.000 title claims abstract description 21
- 230000005540 biological transmission Effects 0.000 claims description 6
- 230000006870 function Effects 0.000 claims description 2
- 230000015572 biosynthetic process Effects 0.000 claims 1
- 230000001960 triggered effect Effects 0.000 description 5
- 238000010276 construction Methods 0.000 description 4
- 239000000654 additive Substances 0.000 description 3
- 230000000996 additive effect Effects 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 230000003213 activating effect Effects 0.000 description 1
- 230000001419 dependent effect Effects 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 230000001627 detrimental effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000011156 evaluation Methods 0.000 description 1
- 230000003137 locomotive effect Effects 0.000 description 1
- 230000035484 reaction time Effects 0.000 description 1
- 230000000630 rising effect Effects 0.000 description 1
- 230000015607 signal release Effects 0.000 description 1
- 230000011664 signaling Effects 0.000 description 1
- 238000010408 sweeping Methods 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
- 238000012549 training Methods 0.000 description 1
- 238000004804 winding Methods 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B61—RAILWAYS
- B61L—GUIDING RAILWAY TRAFFIC; ENSURING THE SAFETY OF RAILWAY TRAFFIC
- B61L15/00—Indicators provided on the vehicle or train for signalling purposes
- B61L15/0092—Memory means reproducing during the running of the vehicle or vehicle train, e.g. smart cards
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B61—RAILWAYS
- B61L—GUIDING RAILWAY TRAFFIC; ENSURING THE SAFETY OF RAILWAY TRAFFIC
- B61L23/00—Control, warning or like safety means along the route or between vehicles or trains
- B61L23/34—Control, warning or like safety means along the route or between vehicles or trains for indicating the distance between vehicles or trains by the transmission of signals therebetween
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B61—RAILWAYS
- B61L—GUIDING RAILWAY TRAFFIC; ENSURING THE SAFETY OF RAILWAY TRAFFIC
- B61L25/00—Recording or indicating positions or identities of vehicles or trains or setting of track apparatus
- B61L25/02—Indicating or recording positions or identities of vehicles or trains
- B61L25/025—Absolute localisation, e.g. providing geodetic coordinates
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B61—RAILWAYS
- B61L—GUIDING RAILWAY TRAFFIC; ENSURING THE SAFETY OF RAILWAY TRAFFIC
- B61L2205/00—Communication or navigation systems for railway traffic
- B61L2205/04—Satellite based navigation systems, e.g. global positioning system [GPS]
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Train Traffic Observation, Control, And Security (AREA)
Abstract
Description
Die Erfindung betrifft ein Verfahren zur Sicherung des Zugleit betriebes eines Schienennetzes nach dem Oberbegriff des An spruches 1, sowie ein Sicherungsgerät zur Durchführung dieses Verfahrens nach dem Oberbegriff des Anspruches 10.The invention relates to a method for securing the train control operation of a rail network according to the preamble of the An saying 1, as well as a belay device for performing this Method according to the preamble of claim 10.
Zur Erhöhung der Sicherheit von Bahnstrecken ist es notwendig, neben den bereits existierenden Sicherheitsvorrichtungen weite re Sicherheitsvorkehrungen zu treffen. Die vorliegende Erfin dung ist dabei vor allem auf die Sicherung des Zugleitbetriebes von Schienennetzen gerichtet, d. h. auf die Sicherung gegen Kollisionen von Schienenfahrzeugen untereinander und mit son stigen Hindernissen oder Gefahrenstellen, wie beispielsweise Baustellen und Bahnübergängen. Eine automatische Sicherung des Zugleitbetriebes ist insbesondere deshalb erstrebenswert, da Kollisionen von Schienenfahrzeugen mit anderen Schienenfahr zeugen oder mit sonstigen Hindernissen in der Regel mit Perso nenschäden und hohen Sachschäden verbunden sind.To increase the safety of railway lines, it is necessary in addition to the existing safety devices re safety precautions. The present inven The main focus is on securing train control operations directed by rail networks, d. H. on securing against Collisions of rail vehicles with each other and with son obstacles or danger spots, such as Construction sites and level crossings. An automatic backup of the Train control mode is particularly desirable because Collisions of rail vehicles with other rail vehicles testify or with other obstacles usually with personal damage and high property damage.
Ein solches Sicherungssystem ist beispielsweise aus der DE-A1 44 34 861 bekannt. Die Druckschrift offenbart eine Anord nung, bei der Schienenfahrzeuge und potentielle Hindernisse mit GPS (Global Positioning System)-Empfängern ausgestattet sind, die jeweils mit einer Funkstation verbunden sind, welche zyk lisch Standortinformationen und Identifikationssignale aus senden. Die Funkstationen sind weiter mit Auswerteeinheiten verbunden, die bei Empfang einer Standortinformation die Ent fernung vom eigenen Standort bestimmen und bei Unterschreiten einer vorgegebenen Mindestentfernung ein Warnsignal ausgeben oder eine Warnstrategie einleiten. Such a security system is, for example, from the DE-A1 44 34 861 known. The document discloses an arrangement with rail vehicles and potential obstacles GPS (Global Positioning System) receivers are equipped which are each connected to a radio station, which zyk location information and identification signals send. The radio stations are still with evaluation units connected, the Ent Determine distance from your own location and if it falls below give a warning signal at a specified minimum distance or initiate a warning strategy.
Bei der genannten Anordnung wird aus den Standortinformationen jeweils die direkte, der Luftlinie entsprechende Entfernung zweier Funkstationen ermittelt. Bei bestimmten Streckenführun gen von Schienennetzen ist es deshalb möglich, daß vom System ein Warnsignal ausgegeben wird, obwohl ein Zusammenstoß ausge schlossen ist, also keine Gefährdung vorliegt. Diese Situation ist beispielsweise gegeben, wenn sich die Schienenfahrzeuge auf zwei voneinander getrennten Bahnstrecken bewegen, die an einer bestimmten Stelle in einem geringeren Abstand zueinander ver laufen als die vorgegebene Mindestentfernung der Warnsignal auslösung.With the arrangement mentioned, the location information becomes in each case the direct distance as the crow flies two radio stations determined. For certain routes rail networks, it is therefore possible that the system a warning signal is issued even though a collision has occurred is closed, i.e. there is no danger. This situation is given, for example, when the rail vehicles are on move two separate railway lines, which on one certain point at a closer distance to each other run as the predetermined minimum distance of the warning signal release.
Aufgabe der vorliegenden Erfindung ist es deshalb, ein Ver fahren zur Sicherung des Zugleitbetriebes eines Schienennetzes vorzusehen, bei welchem der oben genannte Nachteil nicht mehr auftritt, und das Auslösen eines Warnsignals nur bei einer tatsächlich drohenden Gefahrensituation erfolgt.The object of the present invention is therefore a Ver drive to ensure the control of a rail network to provide, in which the above-mentioned disadvantage no longer occurs, and the triggering of a warning signal only at one danger situation is actually imminent.
Diese Aufgabe wird durch ein Verfahren mit den kennzeichnenden Merkmalen des Anspruchs 1 sowie durch ein Sicherungsgerät nach Anspruch 10 gelöst. Vorteilhafte Ausgestaltungen und Weiterbil dungen der Erfindung sind Gegenstand der Unteransprüche.This task is accomplished through a process with the characteristic Features of claim 1 and by a belay device Claim 10 solved. Advantageous refinements and training Applications of the invention are the subject of the dependent claims.
Gemäß der vorliegenden Erfindung berechnen die Sicherungsgeräte die für das Vorliegen einer Gefahrensituation entscheidende Entfernung entlang des Streckenverlaufs des Schienennetzes zu den anderen Sicherungsgeräten des Schienennetzes und berück sichtigen zudem das Vorhandensein bzw. Nicht-Vorhandensein möglicher Begegnungspunkte zwischen den Sicherungsgeräten. Das erfindungsgemäße Sicherungssystem ist dabei als additive Maß nahme zu den bisher angewandten Sicherheitsvorkehrungen vor gesehen.According to the present invention, the belay devices calculate the decisive factor for the existence of a dangerous situation Distance along the route of the rail network the other belay devices in the rail network and back also visualize the existence or non-existence possible meeting points between the belay devices. The Security system according to the invention is an additive measure to the safety precautions previously used seen.
Ein bevorzugtes Ausführungsbeispiel der vorliegenden Erfindung wird im folgenden anhand der beiliegenden Zeichnung näher be schrieben. Darin zeigen:A preferred embodiment of the present invention will be in the following with reference to the accompanying drawing wrote. In it show:
Fig. 1 ein Blockschaltbild eines Systems zur Durchführung des erfindungsgemäßen Verfahrens; Figure 1 is a block diagram of a system for performing the method according to the invention.
Fig. 2 ein erstes Beispiel eines Streckenverlaufes; Fig. 2 shows a first example of a track path;
Fig. 3 ein zweites Beispiel eines Streckenverlaufes; Fig. 3 shows a second example of a track path;
Fig. 4 ein drittes Beispiel eines Streckenverlaufes; und Fig. 4 shows a third example of a track path; and
Fig. 5 ein Beispiel eines Streckenverlaufes in einer Be triebsstelle eines Schienennetzes. Fig. 5 shows an example of a route in a Be operating point of a rail network.
Zunächst soll die prinzipielle Funktionsweise des erfindungs gemäßen Sicherungssystems erklärt werden. Das Sicherungssystem soll additiv zu den üblichen Sicherungssystemen Zugmeldebetrieb und Zugleitbetrieb eingesetzt werden. Durch den additiven Einsatz zu üblichen Sicherungssystemen muß das erfindungsgemäße Sicherungssystem nicht notwendigerweise den signaltechnisch sicheren Grundsätzen im Sinne der MÜ 8004 entsprechen. Das im folgenden beschriebene zusätzliche Sicherungssystem gewähr leistet gegenüber einem völlig neuen signaltechnisch sicheren Zugleitverfahren eine schnelle, unbürokratische und kostengün stige Einführbarkeit bei bundeseigenen und nicht bundeseigenen Bahnen.First, the principle of operation of the invention according to the security system. The security system is intended to be additive to the usual security systems for train detection and train control mode can be used. Through the additive Use according to conventional security systems must be the inventive Security system not necessarily the signaling comply with safe principles in the sense of MÜ 8004. That in guarantee the following described additional security system compared to a completely new signal technology Train control procedure a fast, unbureaucratic and inexpensive permanent introduction to federal and non-federal Tracks.
Jedes Schienenfahrzeug, das in einem bestimmten Zeitraum auf dem betrachteten Schienennetz eingesetzt wird, wird mit einem Sicherungsgerät ausgerüstet. Zusätzliche Installationen entlang des Schienennetzes sind nicht notwendig. Die Sicherungsgeräte lassen sich schnell und einfach auf den verschiedenen Schienen fahrzeugen installieren, wobei die modulare Konzeption des erfindungsgemäßen Systems den Installationsaufwand verringert und die Aufrüstungsmöglichkeiten erhöht.Any rail vehicle that is on in a given period of time the rail network under consideration is used with a Belay device equipped. Additional installations along of the rail network are not necessary. The belay devices can be quickly and easily on the various rails install vehicles, the modular design of the System according to the invention reduces the installation effort and increased the upgrade options.
Für ein Schienennetz wird zunächst die Anzahl der benötigten Sicherungsgeräte festgelegt. Dann werden die Daten über die jeweilige Streckenkarte des Schienennetzes auf alle vorgesehe nen Sicherungsgeräte überspielt. Die Daten sind dabei bei spielsweise in einem Textfile im ASCII-Format abgespeichert.For a rail network, the number of required is first Belay devices set. Then the data on the respective route map of the rail network on all provided belay devices dubbed. The data are included for example saved in a text file in ASCII format.
Das erfindungsgemäße Sicherungssystem ist für Streckenverläufe mit Nebenbahnstrecken gemäß den Fig. 2 bis 5 ausgelegt. Fig. 2 zeigt dabei ein Beispiel einer einfachen Nebenbahn strecke 8, Fig. 3 ein Beispiel einer verschlungenen Nebenbahn strecke 8 und Fig. 4 ein Beispiel eines Nebenbahn-Schienennet zes 8, die bzw. das jeweils von der Hauptstrecke 12 abzweigt bzw. in die Hauptstrecke 12 einmündet. In Fig. 5 ist der Streckenverlauf 9 in einer Betriebsstelle, beispielsweise einem Bahnhof, dargestellt. Die möglichen Begegnungspunkte, wie bei spielsweise Weichen, zweier Schienenfahrzeuge sind jeweils durch Kreise 17 markiert, und die Endpunkte der Nebenbahnstrec ken 8, 9 sind jeweils mit dem Bezugszeichen 11 gekennzeichnet.The safety system according to the invention is designed for routes with branch lines according to FIGS. 2 to 5. Fig. 2 shows an example of a simple branch line 8 , Fig. 3 shows an example of a winding branch line 8 and Fig. 4 shows an example of a branch rail network 8 , which branches off from the main line 12 or in the Main route 12 opens. In FIG. 5, the route 9 is shown in an operating location, such as a train station. The possible meeting points, such as switches, for example, two rail vehicles are each marked by circles 17 , and the end points of the branch lines 8 , 9 are each identified by the reference number 11 .
Vor der Inbetriebnahme des Sicherungssystems muß jedes Siche rungsgerät zunächst die Bahnstrecke 8, 9, 12, auf der es einge setzt werden soll, einlernen. Das Einlernen einer Bahnstrecke funktioniert so, daß ein Sicherungsgerät auf eine Streckenfahrt (Testfahrt oder planmäßige Fahrt) mitgenommen wird und dabei die Streckenkoordinaten mit Hilfe des GPS (Global Positioning System)-Systems 5 aufzeichnet. Mögliche Begegnungsstellen 17 zweier Schienenfahrzeuge (Weichen) werden beispielsweise per Knopfdruck als solche abgespeichert. Hierbei sollte es für den Benutzer des Sicherungssystems möglich sein, die Weichenbe zeichnung und die Betriebsstelle einer solchen Begegnungsstelle 17 einzugeben. Dies kann beispielsweise über einen mitgeführten und mit dem Sicherungsgerät verbundenen Laptop-Computer gesche hen.Before commissioning the security system, each hedging device must first learn the railway line 8 , 9 , 12 on which it is to be inserted. The teaching of a railroad track works in such a way that a safety device is taken on a trip (test run or scheduled trip) and records the track coordinates using the GPS (Global Positioning System) system 5 . Possible meeting points 17 of two rail vehicles (switches) are saved as such, for example, at the push of a button. It should be possible for the user of the security system to enter the switch designation and the operating point of such a meeting point 17 . This can happen, for example, via a laptop computer carried and connected to the security device.
Bei dem oben beschriebenen Einlernvorgang des Systems tauschen die Sicherungsgeräte zudem ihre Senderkennungen aus, so daß jedes Sicherungsgerät weiß, welcher andere Sender bzw. welches andere Sicherungsgerät sich noch auf der jeweiligen Bahnstrecke 8, 9, 12 befinden kann. In the system learning process described above, the belay devices also exchange their transmitter identifiers, so that each belay device knows which other transmitter or which other belay device can still be located on the respective rail route 8 , 9 , 12 .
Wenn auf einer Bahnstrecke n Sicherungsgeräte vorgesehen und eingelernt sind, kann von diesen n eingelernten Sicherungs geräten eine beliebige Anzahl in Betrieb sein. Das Zuschalten weiterer Sicherungsgeräte aus dem eingelernten Pool von n Gerä ten ist jederzeit und an jedem Ort möglich.If n belay devices are provided on a railway line and are trained, can be learned from these n safety any number of devices. Switching on additional belay devices from the learned pool of n devices is possible anytime and anywhere.
Fig. 1 zeigt nun das Blockschaltbild eines Sicherungsgerätes für den Zugleitbetrieb wie es zur Durchführung des erfindungs gemäßen Verfahrens benötigt wird. Fig. 1 now shows the block diagram of a belay device for train control operation as it is required to carry out the method according to the Invention.
Das Herzstück der verwendeten Sicherungsgeräte ist eine Rechen einheit bzw. ein Bordrechner 1. In dem Bordrechner 1 ist als Textfile die jeweilige Streckenkarte mit den Begegnungsstellen 17 in einem nichtflüchtigen Speicher eingespeichert. Während des Einsatzes auf der Bahnstrecke 8, 9, 12 ermittelt das Siche rungsgerät ständig, beispielsweise satellitengestützt mit Hilfe eines GPS-Systems 5 seine aktuelle Position. Die jeweiligen neuesten ermittelten Positionsdaten werden im Positionsspeicher 2 des Sicherungsgerätes abgespeichert, bis sie wieder durch eine neuere GPS-Positionsbestimmung überschrieben werden.The heart of the belay devices used is a computing unit or an on-board computer 1 . The respective route map with the meeting points 17 is stored in a non-volatile memory in the on-board computer 1 as a text file. During use on the railway line 8 , 9 , 12, the belay device continuously determines its current position, for example satellite-assisted using a GPS system 5 . The respective latest determined position data are stored in the position memory 2 of the belay device until they are overwritten again by a more recent GPS position determination.
Kann ein GPS-Signal 5 zeitweise nicht empfangen werden, bei spielsweise weil das Schienenfahrzeug einen Tunnel durchfährt, dann approximiert die Recheneinheit 1 die aktuelle Position des Schienenfahrzeugs aus der letzten GPS-Poitionsbestimmung, der Geschwindigkeit des Schienenfahrzeugs, der eingelesenen Strec kenkarte und der seit der letzten Positionsbestimmung vergange nen Zeit.If a GPS signal 5 cannot be received at times, for example because the rail vehicle travels through a tunnel, then the computing unit 1 approximates the current position of the rail vehicle from the last GPS position determination, the speed of the rail vehicle, the route map read in and since the last position determination elapsed.
Jedes Sicherungsgerät ist mit einem Sender 3 ausgestattet, der die Informationssignale des Sicherungsgerätes an die anderen Sicherungsgeräte aussendet. Die Funkanlage dieses Sicherungs systems beruht vorteilhafterweise auf den gleichen Prinzipien, Frequenzen und Sendeleistungen wie der herkömmliche Zugleit funk. Damit entfallen viele aufwendige Prozeduren und Vorkeh rungen zur Erlangung einer neuen Sendeerlaubnis. Die Daten werden ferner vorteilhafterweise über den gleichen Kanal über tragen, über den auch der Zugleit-Sprechfunk geführt wird.Each belay device is equipped with a transmitter 3 , which sends the information signals from the belay device to the other belay devices. The radio system of this security system is advantageously based on the same principles, frequencies and transmission powers as the conventional Zugleit radio. This eliminates many complex procedures and precautions to obtain a new transmission permit. The data is also advantageously transmitted over the same channel over which the Zugleit voice radio is conducted.
Der Sender 3 übermittelt seine Informationssignale entsprechend der Anzahl n der auf der betrachteten Strecke eingelernten Sicherungsgeräte an die anderen Sicherungsgeräte. Dazu wird der Sender 3 von der Systemuhr, die über den Empfang eines DCF-Signals 4 ständig neu abgestimmt wird, getriggert. Ist das DCF-Signal 4 zeitweise nicht verfügbar, muß die innere System uhr der Sicherungsgeräte über einen genügend genauen Lauf verfügen.The transmitter 3 transmits its information signals corresponding to the number n of the safety devices taught in on the route under consideration to the other safety devices. For this purpose, the transmitter 3 is triggered by the system clock, which is constantly re-tuned by receiving a DCF signal 4 . If the DCF signal 4 is temporarily not available, the internal system clock of the belay devices must have a sufficiently precise run.
Sind auf einer Bahnstrecke n Sicherungsgeräte eingelernt, sendet das Sicherungsgerät Nr. i jede i-te Sekunde ab dem Beginn einer vollen Minute, wobei i < n ist. Jeder Sender 3 hat damit ein Sendeintervall von 60/n Sekunden. Der Beginn einer vollen Minute wird von der inneren Systemuhr des Sicherungs gerätes übernommen. Weiter beginnt jedes Sicherungsgerät seinen Sendevorgang immer zu Beginn einer vollen Sekunde und das nächste Sicherungsgerät sendet zu Beginn der nächsten vollen Sekunde. Damit ist ein genügend großer Abstand der Informa tionssignale gewährleistet und für das Senden der Informations signale ist ausreichend Zeit vorhanden.If n belay devices are learned on a railway line, belay device no. I sends every i-th second from the beginning of a full minute, where i <n. Each transmitter 3 thus has a transmission interval of 60 / n seconds. The start of a full minute is taken over by the internal system clock of the belay device. Furthermore, each belay device always starts its transmission at the beginning of a full second and the next belay device sends at the beginning of the next full second. This ensures a sufficiently large distance between the information signals and there is sufficient time for the information signals to be sent.
Funklöcher im Zugleitbetrieb sind bei dem hier vorgestellten Sicherungssystem deshalb nicht von Bedeutung, weil zwei Sender 3 bzw. zwei Sicherungsgeräte, die sich zu nahe kommen, sich auf jeden Fall sicher empfangen können.Radio holes in train control mode are not important in the security system presented here, because two transmitters 3 or two security devices that come too close can definitely receive each other safely.
Ein Informationssignal enthält üblicherweise Daten bezüglich der Gerätenummer, der aktuellen Position und einer Prüfziffer des jeweiligen Sicherungsgerätes.An information signal usually contains data regarding the device number, the current position and a check digit of the respective belay device.
Neben dem Sender 3 enthält jedes Sicherungsgerät auch einen Empfänger 6. Die Empfänger 6 müssen alle Sender 3 der auf der Bahnstrecke eingelernten Sicherungsgeräte verstehen können. Die Recheneinheit 1 erhält über den Empfänger 6 ständig die aktuel len Positionen der anderen auf der betrachteten Bahnstrecke 8, 9, 12 eingelernten Sicherungsgeräte, die zu diesem Zeitpunkt eingeschaltet sind. Zusätzlich zu den aktuellen Positionen werden auch die Kennungen der anderen Sicherungsgeräte empfan gen, d. h. Informationen darüber, um welches Schienfahrzeug oder welche andere Gefahrenquelle es sich bei den anderen Siche rungsgeräten handelt.In addition to the transmitter 3 , each belay device also contains a receiver 6 . The receivers 6 must be able to understand all the transmitters 3 of the belay devices that have been trained on the railway line. The computing unit 1 constantly receives the current positions of the other safety devices which have been taught in on the track section 8 , 9 , 12 that are switched on at this time via the receiver 6 . In addition to the current positions, the identifiers of the other belay devices are also received, ie information about which rail vehicle or which other source of danger the other belay devices are.
Die Recheneinheit 1 vergleicht die Positionen der anderen Sicherungsgeräte mit der eigenen Position hinsichtlich des Abstandes entlang der Streckenkarte. Außerdem wird geprüft, ob zwischen der eigenen Position und der Position des nächstgele genen anderen Sicherungsgerätes noch Begegnungsstellen 17 lie gen.The computing unit 1 compares the positions of the other security devices with its own position with regard to the distance along the route map. In addition, it is checked whether there are still meeting points 17 between the own position and the position of the nearest other belay device.
Durch das System werden die Entfernungen der eingeschalteten Sicherungsgeräte zueinander bestimmt, wobei nicht die direkte Luftlinien-Entfernung ausschlaggebend ist. Die Sicherungsgeräte können sich nur auf Positionen entlang dem eingelernten Strec kenverlauf bewegen, deshalb werden von den Sicherungsgeräten auch die Entfernungen entlang dem Streckenverlauf bestimmt. Damit ist sichergestellt, daß das Sicherungssystem auch bei Nebenbahnstrecken 8, 9 funktioniert, die beispielsweise Kehr tunnel aufweisen oder beliebig verschlungen angelegt sind.The system determines the distances of the activated safety devices to each other, whereby the direct air line distance is not decisive. The belay devices can only move to positions along the learned route, which is why the belay devices also determine the distances along the route. This ensures that the security system also works on branch lines 8 , 9 , which have, for example, a sweeping tunnel or are designed to be intertwined as desired.
Wird der minimal zulässige Abstand zweier Schienenfahrzeuge bzw. zweier Sicherungsgeräte unterschritten, wird ein Alarm 7 ausgelöst. Die minimale zulässige Entfernung zweier Schienen fahrzeuge errechnet sich aus den Parametern Streckenhöchstge schwindigkeit, streckenübliche Zuglast und dem Gefälle der Bahnstrecke in den jeweils ungünstigsten Kombinationen, so daß nach einem Alarm ein sicheres Halten zweier gegenläufiger Schienenfahrzeuge gewährleistet ist. Zu diesem Minimalwert wird im allgemeinen noch ein Sicherheitswert hinzugerechnet, damit sich eine mögliche Verzögerung bei der Alarmauslösung nicht schädlich auswirkt. Diese minimal zulässige Entfernung wird manuell eingegeben und dann zusammen mit dem Datensatz mit den Streckeninformationen beispielsweise über einen Laptop-Computer in das Sicherungsgerät eingegeben.If the minimum permissible distance between two rail vehicles or two belay devices is undershot, an alarm 7 is triggered. The minimum permissible distance between two rail vehicles is calculated from the parameters line speed, line load and the gradient of the railway line in the most unfavorable combinations, so that after an alarm a safe hold of two opposing rail vehicles is guaranteed. A safety value is generally added to this minimum value, so that a possible delay in triggering the alarm does not have a detrimental effect. This minimum permissible distance is entered manually and then entered together with the data record with the route information, for example via a laptop computer, into the security device.
Das erfindungsgemäße Sicherungssystem sieht zwei verschiedene Alarme vor: "Wachsamkeit" bei einer bevorstehenden Zugbegegnung und "Notalarm" bei einem drohenden Zusammenstoß.The security system according to the invention sees two different ones Alerts before: "Vigilance" at an upcoming train encounter and "emergency alarm" in the event of an impending collision.
Der Alarm "Wachsamkeit" wird ausgelöst, wenn der Abstand zwi schen zwei beliebigen Sicherungsgeräten auf der betrachteten Bahnstrecke die minimal zulässige Entfernung unterschreitet, und wenn gleichzeitig im Streckenverlauf zwischen den beiden Sicherungsgeräten eine Begegnungsstelle 17 liegt. Damit wird sichergestellt, daß bei ordnungsgemäßen Begegnungen von Schie nenfahrzeugen der Triebfahrzeugführer auf die bevorstehende Kreuzung oder Überholung aufmerksam gemacht wird, ohne daß gleich eine Notbremsung des Schienenfahrzeugs provoziert wird.The "vigilance" alarm is triggered when the distance between any two belay devices on the railway line under consideration falls below the minimum permissible distance, and when a meeting point 17 is located between the two belay devices at the same time. This ensures that in the event of proper encounters between rail vehicles, the driver is made aware of the upcoming crossing or overhaul without provoking emergency braking of the rail vehicle.
Der "Notalarm" wird ausgelöst, wenn der Abstand zwischen zwei beliebigen Sicherungsgeräten auf der betrachteten Bahnstrecke die minimal zulässige Entfernung zweier Schienenfahrzeuge unterschreitet, und wenn gleichzeitig zwischen den beiden Sicherungsgeräten keine Begegnungsstelle 17 liegt. Fährt ein Schienenfahrzeug an einer Ausweich- oder Kreuzungsstelle im Versagensfall weiter ohne den Gegenzug oder den überholdenden Zug abzuwarten, geht der Alarm "Wachsamkeit" sofort in den "Notalarm" über.The "emergency alarm" is triggered when the distance between any two belay devices on the railway line under consideration falls below the minimum permitted distance between two rail vehicles, and when there is no meeting point 17 between the two belay devices at the same time. If a rail vehicle continues to drive at an alternate or crossing point in the event of a failure without waiting for the return train or the overtaking train, the "Vigilance" alarm immediately changes to the "Emergency alarm".
Es wird von der Auflösung des GPS-Systems 5 abhängen, ob die Begegnungsstellen 17 als Punkte oder als Zonen zu definieren sind. Bei einer zu groben Auflösung und der Wahl von Begeg nungspunkten gibt es einen "Notalarm", wenn zwei Schienenfahr zeuge auf zwei parallelen Bahnstrecken nebeneinander stehen oder fahren. In diesem Fall müssen Begegnungszonen definiert werden. It will depend on the resolution of the GPS system 5 whether the meeting points 17 are to be defined as points or as zones. If the resolution is too coarse and the meeting points selected, there is an "emergency alarm" if two rail vehicles stand or run next to each other on two parallel railway lines. In this case, encounter zones must be defined.
Zur Signalisierung der beiden Alarmstufen sind vorteilhafter weise zwei verschiedenartige Warnsignalgeber vorhanden. Alle Alarme sollten akustisch und optisch signalisiert werden.To signal the two alarm levels are more advantageous as two different types of warning signal present. All Alarms should be signaled acoustically and optically.
Nach Möglichkeit sollten bei der Alarmstufe "Wachsamkeit" die Begegnungsstellen 17, die zwischen den beiden alarmierenden Sicherungsgeräten liegen, in einem Display benannt werden, vorteilhafterweise mit ihrer Betriebsstelle und ihrer genauen Bezeichnung (Beispiel: Bahnhof Sulzbach, Weiche 3).Whenever possible, at the "vigilance" alarm level, the meeting points 17 that lie between the two alarming security devices should be named on a display, advantageously with their operating point and their exact description (example: Sulzbach station, turnout 3).
Ferner ist es vorteilhaft, daß bei einem "Notalarm" sofort auf das Triebfahrzeug des Schienenfahrzeugs eingewirkt werden kann. Dies kann beispielsweise durch die Aktivierung eines Magnetven tils in der Hauptluftleitung mittels einem Aktorenrelais ge schehen. Damit wird das Auslösen einer Notbremsung unabhängig von der menschlichen Reaktionszeit des Triebfahrzeugführers.It is also advantageous that immediately in the event of an "emergency alarm" the locomotive of the rail vehicle can be affected. This can be done, for example, by activating a magnetic circuit tils in the main air line using an actuator relay happen. The triggering of an emergency braking is thus independent on the driver's human reaction time.
Als weitere Einrichtung des Sicherungssystems können Protokoll einrichtungen an jedem Sicherungsgerät vorgesehen sein. Diese Protokolleinrichtungen zeichnen die korrekten Gerätefunktionen und die abgegebenen Alarme über einen gewissen Zeitraum von beispielsweise zwölf Stunden hinweg auf. Die Protokollierung kann dabei beispielsweise nach dem FIFO-Prinzip durchgeführt werden.As a further facility of the security system, protocol facilities may be provided on each belay device. This Protocol devices draw the correct device functions and the alarms given over a period of time from for example, for twelve hours. The logging can be carried out for example according to the FIFO principle will.
Neben den Sicherungsgeräten, die in den Schienenfahrzeugen eines Schienennetzes installiert werden, können auch ortsfest eingerichtete Sicherungsgeräte vorgesehen werden. Diese orts festen Sicherungsgeräte messen nach dem oben beschriebenen Prinzip die Entfernungen zu den verkehrenden Sicherungsgeräten und lösen bei unterschreiten eines Mindestabstandes ein Alarm signal oder einen Aktor aus.In addition to the belay devices used in the rail vehicles of a rail network can also be installed stationary installed belay devices are provided. These places Fixed belay devices measure according to the above Principle the distances to the circulating belay devices and trigger an alarm when the distance falls below a minimum signal or an actuator.
So kann zum Beispiel durch ein ortsfestes Sicherungsgerät an einem unbesetzten Haltepunkt eine Ansage "Vorsicht am Bahn steig" ausgelöst werden. Ein solches Sicherungsgerät sendet selbst keine Position zu den anderen, auf der Bahnstrecke unterwegs befindlichen Sicherungsgeräten, da von ihm ja keine Gefährdung der Zugfahrt ausgeht.For example, using a stationary belay device an unoccupied stop an announcement "Caution on the train rising ". Such a belay device sends no position to the others themselves on the railway belay devices on the go, since none of them Endangerment of the train journey.
Ferner können beispielsweise an Baustellen solche ortsfesten Sicherungsgeräte für die Dauer der Arbeiten installiert werden. Diese Sicherungsgerate senden auch selbst ihre Positionssignale an die anderen Sicherungsgeräte, so daß sowohl die Arbeiter an der Baustelle vor einem herannahenden Schienenfahrzeug als auch der Triebfahrzeugführer vor einer Baustelle gewarnt werden kann. In diesem Fall wird vom Sicherungsgerät im Schienenfahr zeug nur der Alarm "Wachsamkeit" ausgelöst, auch wenn keine Begegnungsstelle zwischen den beiden Sicherungsgeräten liegt. Zu diesem Zweck enthält das Signal des ortsfesten Sicherungs gerätes eine entsprechende Information, die von der Rechenein heit der anderen Sicherungsgeräte entsprechend verarbeitet wird.Furthermore, such can be stationary at construction sites Belay devices can be installed for the duration of the work. These belay devices also send their position signals themselves to the other belay devices, so that both the workers the construction site in front of an approaching rail vehicle as well the driver is warned of a construction site can. In this case, the belay device is used for rail travel only the "vigilance" alarm is triggered, even if none Meeting point between the two belay devices. For this purpose, the signal contains the fixed fuse appropriate information from the computer of the other belay devices processed accordingly becomes.
Es soll noch darauf hingewiesen werden, daß durch den Begriff Streckenkarte im Sinne dieser Beschreibung sowohl eine einfache Strecke ohne Begegnungsstellen oder weitere Gefahrenstellen als auch ein verzweigtes Streckennetz eines Schienennetzes mit Be gegnungsstellen, Weichen, Kreuzungen, Bahnhöfen und dergleichen gemeint sein kann.It should be noted that the term Route map in the sense of this description is both a simple one Route without meeting points or other danger points as also a branched route network of a rail network with loading junction points, switches, crossings, train stations and the like can be meant.
Claims (10)
- - die Schienenfahrzeuge und Gefahrenstellen des Schienen netzes jeweils mit einem Sicherungsgerät ausgestattet werden,
- - die Sicherungsgeräte der Schienenfahrzeuge in regelmäßi gen Zeitabständen ihre aktuelle Position bestimmen,
- - die Sicherungsgeräte in regelmäßigen Zeitabständen In formationssignale an die anderen Sicherungsgeräte aus senden, und
- - die Sicherungsgeräte entsprechend den empfangenen Infor
mationssignalen die jeweiligen Entfernungen zu den ande
ren Sicherungsgeräten berechnen,
dadurch gekennzeichnet,
daß in den Sicherungsgeräten eine Streckenkarte des Schie nennetzes abgespeichert wird,
daß die Sicherungsgeräte die Entfernungen zu den anderen Sicherungsgeräten entlang der Schienenverbindung des Schie nennetzes berechnen, und
daß die Sicherungsgeräte abhängig von der so berechneten Entfernung zu den anderen Sicherungsgeräten und abhängig von dem Vorhandensein bzw. Nicht-Vorhandensein eines Be gegnungspunktes zwischen den Sicherungsgeräten ein Warn signal (7) ausgeben.
- - The rail vehicles and danger points of the rail network are each equipped with a safety device,
- - the belay devices of the rail vehicles determine their current position at regular intervals,
- - Send the belay devices at regular intervals in formation signals from the other belay devices, and
- - the belay devices calculate the respective distances to the other belay devices according to the information signals received, characterized in that
that a route map of the rail network is stored in the security devices,
that the belay devices calculate the distances to the other belay devices along the rail connection of the rail network, and
that the belay devices issue a warning signal ( 7 ) depending on the distance to the other belay devices thus calculated and depending on the presence or absence of a meeting point between the belay devices.
- - einem Sender (3) zum Aussenden von Informationssignalen,
- - einem Empfänger (6) zum Empfangen von Informationssigna len von anderen Sicherungsgeräten des Schienennetzes,
- - einem Positionsdetektor (2) zur Ermittlung der aktuellen Position des Sicherungsgeräts,
- - einer Recheneinheit (1), und
- - einem Warnsignalgeber (7) zur Ausgabe von Warnsignalen,
dadurch gekennzeichnet,
daß die Recheneinheit (1) einen Speicher zum Einspeichern der Streckenkarte des Schienennetzes und ein Programm zum Berechnen der Entfernungen zu den anderen Sicherungsgeräten entlang des Streckenverlaufs des Schienennetzes enthält.
- - a transmitter ( 3 ) for transmitting information signals,
- - A receiver ( 6 ) for receiving information signals from other security devices in the rail network,
- - a position detector ( 2 ) for determining the current position of the belay device,
- - A computing unit ( 1 ), and
- a warning signal transmitter ( 7 ) for outputting warning signals, characterized in that
that the computing unit ( 1 ) contains a memory for storing the route map of the rail network and a program for calculating the distances to the other security devices along the route of the rail network.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19715773A DE19715773A1 (en) | 1997-04-16 | 1997-04-16 | Rail network operating safety method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19715773A DE19715773A1 (en) | 1997-04-16 | 1997-04-16 | Rail network operating safety method |
Publications (1)
Publication Number | Publication Date |
---|---|
DE19715773A1 true DE19715773A1 (en) | 1998-10-22 |
Family
ID=7826614
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE19715773A Withdrawn DE19715773A1 (en) | 1997-04-16 | 1997-04-16 | Rail network operating safety method |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE19715773A1 (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2000071402A1 (en) * | 1999-05-25 | 2000-11-30 | Bernard Douet | Method and system for automatically detecting or monitoring the position of at least one guided vehicle |
WO2002064415A1 (en) * | 2001-02-13 | 2002-08-22 | Ge-Harris Railway Electronics, Llc | Advanced communication-based vehicle control method |
WO2009087121A1 (en) * | 2008-01-08 | 2009-07-16 | Siemens Aktiengesellschaft | Method for collision warning and collision warning system |
WO2010127958A1 (en) * | 2009-05-07 | 2010-11-11 | Siemens Aktiengesellschaft | Method and apparatus for determining the position of rail-bound vehicles |
CN114834504A (en) * | 2022-05-12 | 2022-08-02 | 株洲中车特种装备科技有限公司 | Rail vehicle anti-collision method and device |
-
1997
- 1997-04-16 DE DE19715773A patent/DE19715773A1/en not_active Withdrawn
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2000071402A1 (en) * | 1999-05-25 | 2000-11-30 | Bernard Douet | Method and system for automatically detecting or monitoring the position of at least one guided vehicle |
WO2002064415A1 (en) * | 2001-02-13 | 2002-08-22 | Ge-Harris Railway Electronics, Llc | Advanced communication-based vehicle control method |
AU2002242170B2 (en) * | 2001-02-13 | 2007-08-09 | Ge Transportation Systems Global Signaling, Llc | Advanced communication-based vehicle control method |
WO2009087121A1 (en) * | 2008-01-08 | 2009-07-16 | Siemens Aktiengesellschaft | Method for collision warning and collision warning system |
WO2010127958A1 (en) * | 2009-05-07 | 2010-11-11 | Siemens Aktiengesellschaft | Method and apparatus for determining the position of rail-bound vehicles |
CN114834504A (en) * | 2022-05-12 | 2022-08-02 | 株洲中车特种装备科技有限公司 | Rail vehicle anti-collision method and device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
AT410531B (en) | METHOD AND SYSTEM FOR AUTOMATIC DETECTION OR MONITORING THE POSITION OF AT LEAST ONE RAIL VEHICLE | |
DD292880A5 (en) | CONTROL SYSTEM FOR THE SEQUENCE OF MULTIPLE RAILWAYS ON A NETWORK | |
WO2021121854A1 (en) | Method and monitoring system for determining a position of a rail vehicle | |
WO2019243341A1 (en) | Flexible train safety system | |
EP0704366A1 (en) | Arrangement for protecting railway tracks | |
DE2628905A1 (en) | TRAIN SECURITY AND CONTROL SYSTEM | |
WO1999067117A2 (en) | Method for reducing data in railway operation | |
EP3795451B1 (en) | Method for locating a vehicle on a station provided for the vehicle stopping | |
DE102005042218A1 (en) | Railway collision warning system, carried in the rail vehicle, has a transceiver to transmit and receive data packets of other trains for the control unit to determine collision risks together with its own data unit | |
DE19715773A1 (en) | Rail network operating safety method | |
WO2007082799A1 (en) | Method and device for train sequence protection | |
EP3105102B1 (en) | Method and device for standstill monitoring in rail vehicles | |
EP4124540A1 (en) | Method and device for operating a driving lock for a track-bound vehicle | |
EP4116170A1 (en) | Method for operating a train control system | |
DE19749697A1 (en) | Railway operations controller | |
DE4433177C1 (en) | Method and device for warning people in the track area | |
DE4425969C1 (en) | Warning system for persons in path of approaching train | |
DE2205368C3 (en) | Device for point-by-point train control and information transfer between rail vehicles and the route | |
DE102017202453A1 (en) | Display system for a vehicle-mounted arrangement | |
DE102020206005A1 (en) | Driving operation arrangement and method for controlling a rail vehicle | |
DE2223413B2 (en) | CONTROL DEVICE FOR VEHICLES | |
DE3502115C2 (en) | Control device for central signal box | |
DE2848984C2 (en) | ||
DE19936988C1 (en) | Method for locating a rail vehicle | |
EP3577005B1 (en) | Display of secondary signal devices and safety device of a railway vehicle |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
8139 | Disposal/non-payment of the annual fee |