CN205257790U - Fixed high -low leg handle portal crane - Google Patents
Fixed high -low leg handle portal crane Download PDFInfo
- Publication number
- CN205257790U CN205257790U CN201521120181.8U CN201521120181U CN205257790U CN 205257790 U CN205257790 U CN 205257790U CN 201521120181 U CN201521120181 U CN 201521120181U CN 205257790 U CN205257790 U CN 205257790U
- Authority
- CN
- China
- Prior art keywords
- steel
- bridge
- leg
- landing leg
- girder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 59
- 239000010959 steel Substances 0.000 claims abstract description 59
- 238000003466 welding Methods 0.000 claims description 6
- 230000001154 acute effect Effects 0.000 claims description 4
- 238000009434 installation Methods 0.000 description 13
- 238000010276 construction Methods 0.000 description 7
- 239000000463 material Substances 0.000 description 3
- 239000004575 stone Substances 0.000 description 3
- 238000000034 method Methods 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 230000001133 acceleration Effects 0.000 description 1
- 238000007596 consolidation process Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009417 prefabrication Methods 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
Landscapes
- Leg Units, Guards, And Driving Tracks Of Cranes (AREA)
Abstract
Description
技术领域 technical field
本实用新型涉及一种起重装置,具体为一种固定高低腿提梁龙门吊。 The utility model relates to a lifting device, in particular to a gantry crane with fixed height and low legs.
背景技术 Background technique
随着国家公路施工步伐的不断加快,采用龙门吊提梁上桥进行架设施工技术已日益成熟。传统的龙门吊安装形式为在墩柱两侧设置龙门吊行走轨道,龙门吊跨墩安装进行提梁架设,龙门吊安装前,必须根据路面宽度、桥面设计高程、梁高等及梁体自重,选择相应跨度、起升高度和起重能力的龙门吊来满足施工要求。由于各工程路面宽度、桥面设计高程及梁体自重大小各异,且现有龙门吊数量有限,龙门吊选型过程中,能够完全满足施工要求的龙门吊可选性低。尤其针对公路梁场所在位置距离路基较远,无法利用路基运梁上桥架设,且梁场所在范围内线路布置形式为连续高墩,桥面宽度大,按常规方式选择跨墩龙门吊进行安装时设备选型难度大,而现有闲置龙门吊无满足现场要求,若新购满足该要求的龙门吊造价较高且利用率低。 With the continuous acceleration of national highway construction, the technology of erecting bridges with gantry cranes has become increasingly mature. The traditional gantry crane installation form is to set the gantry crane walking track on both sides of the pier column, and the gantry crane is installed across the pier to erect the beam. The gantry crane with lifting height and lifting capacity can meet the construction requirements. Due to the different width of road surface, design elevation of bridge deck and self-weight of girders in each project, and the limited number of existing gantry cranes, in the selection process of gantry cranes, the choice of gantry cranes that can fully meet the construction requirements is low. Especially for the location of the highway girder site is far away from the subgrade, it is impossible to use the subgrade to transport the girder to the bridge erection, and the line layout within the range of the girder site is continuous high piers, and the width of the bridge deck is large. The selection of equipment is difficult, and the existing idle gantry cranes do not meet the requirements of the site. If a new gantry crane that meets the requirements is purchased, the cost will be high and the utilization rate will be low.
发明内容 Contents of the invention
本实用新型为了解决现有梁场所在位置距离路基较远、无法利用路基运梁上桥架设、且梁场运架梁范围内线路布置形式为连续高墩而无法采用现有龙门吊的问题,提供一种新的固定高低腿提梁龙门吊。 The utility model solves the problem that the existing beam yard is far away from the roadbed, cannot use the roadbed to transport the beams and erect the bridge, and the line layout in the beam yard transportation and erection range is continuous high pier, so the existing gantry crane cannot be used. A new fixed high and low leg girder gantry crane.
本实用新型是采用如下技术方案实现的:固定高低腿提梁龙门吊,包括主梁、铺设于主梁上的钢轨和沿钢轨运行的吊装天车,其特征是主梁一端下方设置与桥面预制梁顶预埋钢板焊接的低支腿,另一端下方设置与桥下钢管桩承台焊接的高支腿,其中所述低支腿为倒三角形桁架结构,高支腿是采用分节拼装并通过法兰盘连接而成,高支腿结构包含沿纵桥向方向并且顶部互成锐角设置的两组立柱,每组立柱由沿横桥向方向平行设置的两根钢管构成,两两相邻的钢管之间由上至下间隔连有水平支撑杆,上、下水平支撑杆之间通过斜向拉杆连接。 The utility model is realized by adopting the following technical scheme: fixed high and low leg girder gantry crane, including the main girder, the steel rail laid on the main girder and the hoisting crane running along the steel rail. The low outriggers are welded with pre-embedded steel plates on the top, and the high outriggers welded with the steel pipe pile cap under the bridge are arranged under the other end, wherein the low outriggers are inverted triangular truss structures, and the high outriggers are assembled in sections and passed through The high-leg structure consists of two sets of columns arranged along the direction of the longitudinal bridge and the tops are at an acute angle to each other. Each set of columns is composed of two steel pipes arranged in parallel along the direction of the transverse bridge. The steel pipes are connected with horizontal support rods at intervals from top to bottom, and the upper and lower horizontal support rods are connected by oblique pull rods.
所述的高支腿的四根立柱顶部之间通过定位钢管连为一体,定位钢管内侧通过对拉槽钢分两层交错布置,顶部通过定位钢板焊接,此结构设计,进一步增强了高支腿顶部的结构稳定性。 The tops of the four columns of the high legs are connected as a whole by positioning steel pipes, the inner sides of the positioning steel pipes are arranged in two layers by means of double channel steel, and the tops are welded by positioning steel plates. This structural design further strengthens the height of the high legs. Structural stability at the top.
所述的桥下钢管桩承台结构包含由下至上设置的片石夯实层和混凝土浇筑承台,片石夯实层和混凝土浇筑承台内预埋有若干钢管桩,钢管桩顶部伸出混凝土浇筑承台,并且通过预埋工字钢连为一体,高支腿的四根立柱底部与预埋工字钢之间采用钢板进行满焊连接。此结构设计,保证了高支腿底部与桥下钢管桩承台的稳固连接。 The steel pipe pile cap structure under the bridge includes a stone chip tamping layer and a concrete pouring cap arranged from bottom to top, and a number of steel pipe piles are pre-embedded in the chip stone tamping layer and the concrete pouring cap, and the top of the steel pipe pile protrudes from the concrete. The cap is poured and connected as a whole through pre-embedded I-beams. The bottom of the four columns with high legs and the pre-embedded I-beams are fully welded with steel plates. This structural design ensures a stable connection between the bottom of the high leg and the steel pipe pile cap under the bridge.
采用本实用新型的结构设计,充分利用了既有的龙门吊和现有材料等资源,在原有龙门吊的基础上,现场加工、改装成型,并安装调试固定高低腿龙门吊,其中高支腿安装在桥下,低支腿安装在桥面上,低支腿与桥面预制梁顶预埋钢板采用焊接方式进行固结连接,高支腿与桥下钢管桩承台焊接相连,使得龙门吊跨度大大缩小,且低支腿高度大大降低,龙门吊稳定性大大提高,降低了龙门吊在使用过程中的安全风险;并且低支腿为倒三角形桁架结构,高支腿由顶部互成锐角设置的两组立柱构成,稳定性较强,本实用新型结构简单、设计合理、施工方便,不仅减小了龙门吊的跨度,降低了单侧支腿的高度,提高了龙门吊结构的安全性,而且降低了设备选型难度,与新购龙门吊相比,单台龙门吊节约投资约80万元以上。 The structural design of the utility model makes full use of resources such as existing gantry cranes and existing materials. On the basis of the original gantry cranes, on-site processing, refitting, and installation and debugging fix the high and low leg gantry cranes, in which the high legs are installed on the bridge. Below, the low outriggers are installed on the bridge deck, and the low outriggers are welded to the prefabricated beam top pre-embedded steel plate for consolidation connection, and the high outriggers are welded to the steel pipe pile cap under the bridge, which greatly reduces the span of the gantry crane , and the height of the low outrigger is greatly reduced, the stability of the gantry crane is greatly improved, and the safety risk during the use of the gantry crane is reduced; and the low outrigger is an inverted triangular truss structure, and the high outrigger is composed of two sets of columns set at an acute angle at the top , strong stability, the utility model is simple in structure, reasonable in design and convenient in construction, which not only reduces the span of the gantry crane, reduces the height of one side outrigger, improves the safety of the gantry crane structure, but also reduces the difficulty of equipment selection , Compared with newly purchased gantry cranes, a single gantry crane saves an investment of more than 800,000 yuan.
附图说明 Description of drawings
图1为本实用新型的结构示意图; Fig. 1 is the structural representation of the utility model;
图2为图1的侧视图; Fig. 2 is the side view of Fig. 1;
图3为图2中的局部放大图; Fig. 3 is a partial enlarged view in Fig. 2;
图4为图3的侧视图; Fig. 4 is the side view of Fig. 3;
图5为图3中A-A剖视图; Fig. 5 is A-A sectional view among Fig. 3;
图中:1-主梁;2-钢轨;3-吊装天车;4-低支腿;5-钢管;6-水平支撑杆;7-斜向拉杆;8-定位钢管;9-片石夯实层;10-混凝土浇筑承台;11-钢管桩;12-预埋工字钢。 In the figure: 1-main girder; 2-rail; 3-hoisting crane; 4-low outrigger; 5-steel pipe; 6-horizontal support rod; ; 10-concrete pouring platform; 11-steel pipe pile; 12-embedded I-beam.
具体实施方式 detailed description
固定高低腿提梁龙门吊,如图1、2所示,包括主梁1、铺设于主梁上的钢轨2和沿钢轨运行的吊装天车3,主梁一端下方设置与桥面预制梁顶预埋钢板焊接的低支腿4,另一端下方设置与桥下钢管桩承台焊接的高支腿,所述低支腿为倒三角形桁架结构,高支腿是采用分节拼装并通过法兰盘连接而成,高支腿结构包含沿纵桥向方向并且顶部互成锐角设置的两组立柱,每组立柱由沿横桥向方向平行设置的两根钢管5构成,两两相邻的钢管之间由上至下间隔连有水平支撑杆6,上、下水平支撑杆之间通过斜向拉杆7连接。 Fixed high and low leg girder gantry cranes, as shown in Figures 1 and 2, include the main girder 1, the steel rail 2 laid on the main girder, and the hoisting crane 3 running along the rail. The low leg 4 welded by the steel plate, and the high leg welded with the steel pipe pile cap under the bridge are arranged under the other end. The low leg is an inverted triangle truss structure, and the high leg is assembled in sections and passed through the flange The high outrigger structure consists of two sets of columns arranged along the longitudinal direction of the bridge and the tops are at an acute angle to each other. Each set of columns is composed of two steel pipes 5 arranged in parallel along the direction of the transverse bridge. Between two adjacent steel pipes The horizontal support rods 6 are connected at intervals from top to bottom, and the upper and lower horizontal support rods are connected by oblique pull rods 7 .
高支腿的四根立柱顶部之间通过定位钢管8连为一体,定位钢管内侧通过对拉槽钢分两层交错布置,顶部通过定位钢板焊接。 The tops of the four columns of the high legs are connected as a whole by positioning steel pipes 8, the inner sides of the positioning steel pipes are arranged in two layers by means of opposite-drawing channel steels, and the tops are welded by positioning steel plates.
桥下钢管桩承台结构包含由下至上设置的片石夯实层9和混凝土浇筑承台10,片石夯实层和混凝土浇筑承台内预埋有若干钢管桩11,钢管桩顶部伸出混凝土浇筑承台,并且通过预埋工字钢12连为一体,高支腿的四根立柱底部与预埋工字钢之间采用钢板进行满焊连接。 The structure of the steel pipe pile cap under the bridge includes a stone chip tamping layer 9 and a concrete pouring cap 10 arranged from bottom to top, and a number of steel pipe piles 11 are pre-embedded in the chip rock tamping layer and the concrete pouring cap, and the top of the steel pipe pile protrudes from the concrete The cap is poured and connected as a whole through the pre-embedded I-beam 12, and the bottom of the four columns of the high leg and the pre-embedded I-beam are connected by full welding with steel plates.
本实用新型所述的龙门吊安装时可采用以下步骤: The following steps can be adopted during installation of the gantry crane described in the utility model:
龙门吊安装基本步骤为:100t汽车吊就位—分节组装高支腿—整体吊装低支腿安装—安装高支腿—安装主梁—高支腿辅助加固材料焊接—龙门吊其他附件安装。 The basic steps of gantry crane installation are: 100t truck crane in place - segmented assembly of high outriggers - overall hoisting and low outrigger installation - installation of high outriggers - installation of main beam - welding of auxiliary reinforcement materials for high outriggers - installation of other gantry crane accessories.
1.100t汽车吊就位 1.100t truck crane in place
利用吊车架梁场地及道路,使100t汽车吊准确就位,主要用于桥下高支腿分节吊装,完成支腿拼装。 The 100t truck crane is positioned accurately by using the crane girder site and the road, which is mainly used for segmental hoisting of high outriggers under the bridge to complete the assembly of outriggers.
2.桥下高支腿安装 2. Installation of high outriggers under the bridge
1)分节组装高支腿,利用100t吊车将每节支腿逐一起吊,使用法兰将其连接为整体; 1) Assemble the high outriggers in sections, use a 100t crane to hoist each outrigger one by one, and connect them as a whole with flanges;
2)高支腿分节拼装完成后,使用100t汽车吊整体吊装至基础上方就位,支腿底部钢管与基础预埋工字钢之间采用0.67m×0.67m×40mm钢板进行满焊连接,并使用四根长2.5m,Φ外=300mm,δ=6mm钢管满焊对拉形成框架; 2) After the high outriggers are assembled in sections, use a 100t truck crane to hoist them in place above the foundation as a whole, and use 0.67m×0.67m×40mm steel plates for full welding connection between the steel pipes at the bottom of the outriggers and the pre-embedded I-beams in the foundation. And use four 2.5m long, Φ outer = 300mm, δ = 6mm steel pipes fully welded to form a frame;
3)高支腿顶部用4根Φ外=300mm,δ=6mm钢管连接成一整体,钢管内侧采用6根16b#槽钢分两层交错布置,顶部用δ=4cm钢板焊接连接; 3) The top of the high leg is connected as a whole with 4 Φ outer = 300mm, δ = 6mm steel pipes, the inner side of the steel pipes are arranged in two layers of 16b# channel steel, and the top is welded with δ = 4cm steel plate;
4)高支腿就位后使用缆风绳双侧固定。 4) After the high outriggers are in place, fix them on both sides with cable wind ropes.
3.桥面低支腿安装 3. Installation of low outriggers on the bridge deck
低支腿利用原有MG160/10-40M龙门吊单侧支腿上部进行技术改造,使用25t汽车吊起吊就位,与梁顶预埋钢板进行焊接固结连接,低支腿焊接加固后使用缆风绳双侧固定。 The low outriggers are technically transformed by using the upper part of the original MG160/10-40M gantry crane single side outriggers, hoisted in place with a 25t truck crane, and welded and consolidated with the pre-embedded steel plates on the beam top. After the low outriggers are welded and reinforced, use cable wind The rope is fixed on both sides.
4.龙门吊主梁安装 4. Installation of main girder of gantry crane
龙门吊主梁利用原有MG160/10-40M龙门吊主梁,从中间销轴断开,选其一半。龙门吊高、低支腿就位加固完毕后,使用桥下100t汽车吊与桥面25t汽车吊完成龙门吊主梁安装。 The main girder of the gantry crane uses the original MG160/10-40M gantry crane main girder, which is cut off from the middle pin and half of it is selected. After the high and low outriggers of the gantry crane are in place and reinforced, a 100t truck crane under the bridge and a 25t truck crane on the bridge deck are used to complete the installation of the main girder of the gantry crane.
5.高支腿辅助加固材料焊接 5. High leg auxiliary reinforcement material welding
高支腿竖向每隔8m分别在支腿顺桥向两根钢管之间采用Φ外=300mm,δ=6mm钢管进行焊接连接,增加龙门吊高支腿的整体刚度和稳定性。 The high outriggers are welded and connected between the two steel pipes along the bridge direction of the outriggers at vertical intervals of 8m with Φ outer=300mm, δ=6mm steel pipes to increase the overall rigidity and stability of the high outriggers of the gantry crane.
6.最后安装龙门吊所有剩余部件,包括天车,卷扬机,吊具,电器设备、操作室等辅助部件安装。 6. Finally, install all the remaining components of the gantry crane, including the installation of auxiliary components such as cranes, hoists, spreaders, electrical equipment, and operating rooms.
工程实例: Engineering example:
铜陵长江公铁大桥路基接线LJ03标梁场位于安徽省芜湖市无为县高沟镇境内,T梁场位于线路里程K23+700右侧,负责K22+871.562~K25+426.562段共882片T梁预制、架设以及桥面系施工,目前制梁、架梁及桥面系施工任务已全部顺利完成。为满足T梁桥梁运梁上桥,申请人在现有龙门吊资源不能满足现场施工需求的情况下,采用了本实用新型所述的龙门吊,有效的利用了现有资源,并缩短了桥梁运输距离,达到了预期效果。 Tongling Changjiang Highway-Railway Bridge subgrade junction LJ03 beam field is located in Gaogou Town, Wuwei County, Wuhu City, Anhui Province. The T-beam field is located on the right side of the line mileage K23+700, responsible for the prefabrication of 882 pieces of T-beams in the section K22+871.562~K25+426.562 , erection, and bridge deck system construction. At present, the beam making, beam erection and bridge deck system construction tasks have all been successfully completed. In order to meet the requirement of transporting the girders on the T-beam bridge, the applicant adopted the gantry crane described in the utility model under the condition that the existing gantry crane resources could not meet the on-site construction requirements, which effectively utilized the existing resources and shortened the bridge transportation distance , achieved the desired effect.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201521120181.8U CN205257790U (en) | 2015-12-30 | 2015-12-30 | Fixed high -low leg handle portal crane |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201521120181.8U CN205257790U (en) | 2015-12-30 | 2015-12-30 | Fixed high -low leg handle portal crane |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205257790U true CN205257790U (en) | 2016-05-25 |
Family
ID=55999331
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201521120181.8U Expired - Fee Related CN205257790U (en) | 2015-12-30 | 2015-12-30 | Fixed high -low leg handle portal crane |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205257790U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107311047A (en) * | 2017-08-18 | 2017-11-03 | 中冶建工集团有限公司 | The steel box-girder lift structure and method for improving of large span bondbeam |
CN109024306A (en) * | 2018-07-31 | 2018-12-18 | 中国铁建大桥工程局集团有限公司 | Mountain terrain place Gao Dun rides pier formula door frame bridge lifting construction method |
CN111776957A (en) * | 2020-06-30 | 2020-10-16 | 中建一局集团建设发展有限公司 | Gantry crane with height-adjustable supporting legs and construction method thereof |
CN112125160A (en) * | 2020-08-19 | 2020-12-25 | 北京市政路桥股份有限公司 | Vertical beam lifting method for high and large fixed-point portal frame |
-
2015
- 2015-12-30 CN CN201521120181.8U patent/CN205257790U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107311047A (en) * | 2017-08-18 | 2017-11-03 | 中冶建工集团有限公司 | The steel box-girder lift structure and method for improving of large span bondbeam |
CN109024306A (en) * | 2018-07-31 | 2018-12-18 | 中国铁建大桥工程局集团有限公司 | Mountain terrain place Gao Dun rides pier formula door frame bridge lifting construction method |
CN111776957A (en) * | 2020-06-30 | 2020-10-16 | 中建一局集团建设发展有限公司 | Gantry crane with height-adjustable supporting legs and construction method thereof |
CN112125160A (en) * | 2020-08-19 | 2020-12-25 | 北京市政路桥股份有限公司 | Vertical beam lifting method for high and large fixed-point portal frame |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100441779C (en) | Bridge construction method for air prefabrication and translation in place | |
CN101781878B (en) | Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof | |
CN104631333B (en) | Arch bridge needle beam, stringer and floorings cast-in-place construction travelling bridge and method | |
CN110387822B (en) | Cast-in-situ bent cap assembly type steel pipe support and construction method thereof | |
CN105625195A (en) | Novel SCC construction-method moving hanging basket for corrugated steel webs and construction method of hanging basket | |
CN107841953B (en) | High-altitude oblique crossing Liang Doupo side span cast-in-situ section construction support and construction method | |
CN207244447U (en) | Movable hanging basket for steel-concrete composite bridge | |
CN205257790U (en) | Fixed high -low leg handle portal crane | |
CN102605717A (en) | Pier-top longitudinal support scaffolding method | |
CN107905114A (en) | A kind of construction method of large span Successive interference cancellation | |
CN108396630A (en) | The big box-beam structure of precast concrete with the connection of wet seam direction across bridge | |
CN107401125B (en) | Traveling device of mobile trolley and using method | |
JP2010031607A (en) | Construction method for grade separation | |
CN210049103U (en) | High-grade high-speed highway bracket spanned by large-span cast-in-place box girder | |
CN114319079B (en) | Double-deck steel bridge girder falling structure and girder falling method for highway bridge and railway bridge | |
CN204662929U (en) | A kind of cross-line walking fence operation device | |
CN207987749U (en) | Ride cable-styled erection crane | |
CN102619335A (en) | Construction method of large-height small-sized cast-in-place concrete beam slab | |
CN202017181U (en) | Falsework for constructing steel and concrete combined beam crossing over conventional route and arranged parallel to existing line | |
CN110552294B (en) | Reverse girder erection construction platform of bridge girder erection machine and construction method thereof | |
CN111851307A (en) | Construction method of large-span prefabricated corrugated web composite box girder transport frame | |
CN112211112A (en) | Steel box girder installation method adopting double-guide-girder erection machine on existing bridge | |
CN111705682A (en) | A construction method and equipment for demolition and reconstruction of superstructure of widened bridge across electrified railway | |
CN208328660U (en) | The U-shaped girder construction of the Two bors d's oeuveres of combined bridge | |
CN117488647A (en) | Combined beam suitable for upper and lower two-layer steel truss web rods of overhead in urban area and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160525 |