CN201834176U - Tooling for underwater anchor chock modification work - Google Patents
Tooling for underwater anchor chock modification work Download PDFInfo
- Publication number
- CN201834176U CN201834176U CN2010205555988U CN201020555598U CN201834176U CN 201834176 U CN201834176 U CN 201834176U CN 2010205555988 U CN2010205555988 U CN 2010205555988U CN 201020555598 U CN201020555598 U CN 201020555598U CN 201834176 U CN201834176 U CN 201834176U
- Authority
- CN
- China
- Prior art keywords
- platform
- tooling
- anchor chock
- steel structure
- modification
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Revetment (AREA)
Abstract
The utility model relates to a tooling for underwater anchor chock modification work, which is used for replacing an anchor chock at the head part of a ship body. The tooling comprises a platform (1) with a steel structure, wherein a railing (3) is arranged at the periphery of the platform (1); two sides of the platform (1) are connected with a dock shore tackle (5) through wire cables (4); a pressing block (2), of which the weight is approximate to that of the anchor chock, is placed on one side of the platform (1); and a constructer can work, and disassemble and assemble the anchor chock on the other side of the platform. Through the adoption of the tooling, the operation time can be reduced; the production efficiency can be improved; and influence of wind wave can be avoided.
Description
(1) technical field
The utility model relates to a kind of subsea anchor platform modification frock.Be used for the replacing of hull stem anchor platform.Belong to the ship building technical field.
(2) background technology
Owing to shipowner or designing institute, anchor platform form needs to change in the ship building process.The ten or twenty ton but the anchor platform weighs, and the linear flare of hull stem is very serious, and it is extremely difficult to construct under water.Way in the past is to arrange that on the water surface floating platform is connected with boats and ships, utilizes the crane barge coordinating operation more for a long time, and any wind and wave can not be arranged during operation.This method production time is long, and production efficiency is low, the expense that also need set up floating flat-bed time and expense and use crane barge.
(3) summary of the invention
The purpose of this utility model is to overcome above-mentioned deficiency, the subsea anchor platform modification frock that provides a kind of and reduce production time, enhance productivity, be not subjected to stormy waves to influence.
The purpose of this utility model is achieved in that a kind of subsea anchor platform modification frock, comprise a steel structure platform, the outer periphery of this steel structure platform is equipped with railing, these steel structure platform both sides link to each other with a harbour shore tackle by steel rope, place and the approaching briquetting of described anchor platform weight on one side at this steel structure platform, the workmen just can carry out operation at the another side of steel structure platform, dismounting anchor platform.
The beneficial effects of the utility model are:
1, adopts special-purpose frock part construction, utilize harbour shore tackle lifting operation, not influenced by stormy waves.
2, improve production efficiency, reduced production time, guaranteed big nodes such as deliver the vessel effectively.
3, can reduce the expense of setting up floating flat-bed time and expense and use crane barge, save cost widely.
(4) description of drawings
Fig. 1 is the overall structure scheme drawing of the utility model subsea anchor platform modification frock.
Reference numeral among the figure:
(5) specific embodiment
Referring to Fig. 1, Fig. 1 is the overall structure scheme drawing of the utility model subsea anchor platform modification frock.As seen from Figure 1, the utility model subsea anchor platform modification frock, comprise a steel structure platform 1, the outer periphery of this steel structure platform 1 is equipped with railing 3, these steel structure platform 1 both sides link to each other with a harbour shore tackle 5 by steel rope 4, place and the approaching briquetting 2 of described anchor platform 6 weight on one side at this steel structure platform 1, and the workmen just can carry out operation at the another side of steel structure platform 1, dismounting anchor platform 6.
Claims (1)
1. subsea anchor platform modification frock, it is characterized in that described frock comprises a steel structure platform (1), the outer periphery of this steel structure platform (1) is equipped with railing (3), this steel structure platform (1) both sides link to each other with a harbour shore tackle (5) by steel rope (4), at this steel structure platform (1) one side place a briquetting (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010205555988U CN201834176U (en) | 2010-09-30 | 2010-09-30 | Tooling for underwater anchor chock modification work |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010205555988U CN201834176U (en) | 2010-09-30 | 2010-09-30 | Tooling for underwater anchor chock modification work |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201834176U true CN201834176U (en) | 2011-05-18 |
Family
ID=44004273
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010205555988U Expired - Fee Related CN201834176U (en) | 2010-09-30 | 2010-09-30 | Tooling for underwater anchor chock modification work |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201834176U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103192950A (en) * | 2012-01-09 | 2013-07-10 | 江苏新世纪造船有限公司 | Method for designing anchor base of unbalanced anchor with large holding power |
CN103626088A (en) * | 2012-08-26 | 2014-03-12 | 江苏雄宇重工科技股份有限公司 | Marine work platform |
CN112061341A (en) * | 2020-08-13 | 2020-12-11 | 沪东中华造船(集团)有限公司 | Tilting bucket tool and using method thereof |
-
2010
- 2010-09-30 CN CN2010205555988U patent/CN201834176U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103192950A (en) * | 2012-01-09 | 2013-07-10 | 江苏新世纪造船有限公司 | Method for designing anchor base of unbalanced anchor with large holding power |
CN103192950B (en) * | 2012-01-09 | 2015-12-02 | 江苏新世纪造船有限公司 | The anchor platform design of high holding power overbalance anchor |
CN103626088A (en) * | 2012-08-26 | 2014-03-12 | 江苏雄宇重工科技股份有限公司 | Marine work platform |
CN112061341A (en) * | 2020-08-13 | 2020-12-11 | 沪东中华造船(集团)有限公司 | Tilting bucket tool and using method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111232140B (en) | Floating offshore wind power foundation structure with additional net cage | |
CN101417693B (en) | Oceanography engineering module integral hoisting method | |
CN101492140B (en) | Aluminum alloy catamaran whole-boat afloat process | |
CN101804849B (en) | Construction program of semi-submersible platform for offshore oil and gas development | |
CN101581086B (en) | Positioning riprapping method for constructing island breakwater of artificial island | |
CN103981846A (en) | Pile positioning semi-submersible offshore dredging engineering ship | |
CN101850831A (en) | A hoisting method for the general section of the living area of a large-scale ocean-going offshore platform | |
CN101870435B (en) | Overturned hoisting method for helicopter platform | |
CN201834176U (en) | Tooling for underwater anchor chock modification work | |
CN103883273A (en) | Method for utilizing two cranes on saturation diving support vessel to mount vertical pipe | |
CN106005266B (en) | Wave piercing buoy structure and buoy system | |
CN102923261A (en) | A bottom-mounted offshore wind turbine installation barge | |
CN216961162U (en) | Platform integrating self-submerged culture net cage and floating wind turbine generator | |
CN201530463U (en) | Three-buoyant offshore engineering vessel | |
CN104002931A (en) | U-shaped offshore engineering installation vessel and jacket topside module installation method | |
CN102219047A (en) | Device and method of salvaging underwater mooring system in muddy seabed | |
CN201745721U (en) | Special installation vessel for marine intertidal wind power generating set | |
CN201961506U (en) | Suspension type boarding tower | |
CN105539740A (en) | Wharf boarding ladder of FLNG barge | |
CN104164885A (en) | Caisson towing method | |
CN209852529U (en) | Offshore mobile platform crude oil export high holding power anchor and double-cable mooring system | |
CN219635447U (en) | Ball-like type offshore floating type photovoltaic floating body structure | |
CN201633915U (en) | Welded type air pipe head | |
CN202966598U (en) | A new type of bottom-mounted offshore wind turbine installation barge | |
CN215860611U (en) | Floating type offshore wind turbine foundation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |