[go: up one dir, main page]

CN114622569B - Pile top structure with foundation pit supporting and retaining functions and basement anti-floating function - Google Patents

Pile top structure with foundation pit supporting and retaining functions and basement anti-floating function Download PDF

Info

Publication number
CN114622569B
CN114622569B CN202210055081.XA CN202210055081A CN114622569B CN 114622569 B CN114622569 B CN 114622569B CN 202210055081 A CN202210055081 A CN 202210055081A CN 114622569 B CN114622569 B CN 114622569B
Authority
CN
China
Prior art keywords
foundation pit
wall
retaining wall
basement
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210055081.XA
Other languages
Chinese (zh)
Other versions
CN114622569A (en
Inventor
秦胜伍
张领帅
乔双双
姚靖宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jilin University
Original Assignee
Jilin University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jilin University filed Critical Jilin University
Priority to CN202210055081.XA priority Critical patent/CN114622569B/en
Publication of CN114622569A publication Critical patent/CN114622569A/en
Application granted granted Critical
Publication of CN114622569B publication Critical patent/CN114622569B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/10Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure
    • E02D31/12Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure against upward hydraulic pressure

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Piles And Underground Anchors (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

本发明涉及桩顶结构施工的技术领域,公开了兼具基坑支挡和地下室抗浮的桩顶结构,包括多个灌注桩,灌注桩的上部具有显露段,显露段形成凿除区域,显露段插设有水平植筋;凿除区域上设置有锁口梁,锁口梁中具有与锚固钢筋焊接的锁口梁钢筋,锁口梁的外侧部形成外突部;凿除区域中设有抵接在显露段的临空面的挡土墙,挡土墙内具有挡土墙钢筋,挡土墙钢筋的下端置于锁口梁内部,锚固钢筋延伸至挡土墙内部;基坑中设有地下室,地下室的外墙自下而上抵接着锁口梁,利用挡土墙临时支挡土体,保证基坑不会滑坡、塌方,锁口梁与地下室的外墙锚固连接,当地下室受到地下水浮力上浮时,锁口梁给予地下室外墙较大的反力,保证了地下室的抗浮安全性。

The invention relates to the technical field of pile top structure construction, and discloses a pile top structure with both foundation pit support and anti-floating basement, including a plurality of cast-in-situ piles, the upper part of which has exposed sections, and the exposed sections form chiseled areas, and horizontal planting bars are inserted in the exposed sections; lock beams are arranged on the chiseled areas, and the lock beams have lock beam steel bars welded with anchor reinforcement bars, and the outer sides of the lock beams form external protrusions; There is a retaining wall reinforcement in the retaining wall, the lower end of the retaining wall reinforcement is placed inside the lock beam, and the anchor reinforcement extends to the inside of the retaining wall; there is a basement in the foundation pit, and the outer wall of the basement touches the lock beam from bottom to top, and the retaining wall is used to temporarily support the retaining soil body to ensure that the foundation pit will not slide or collapse. sex.

Description

兼具基坑支挡和地下室抗浮的桩顶结构Pile top structure with foundation pit retaining and basement anti-floating

技术领域technical field

本发明专利涉及桩顶结构施工的技术领域,具体而言,涉及兼具基坑支挡和地下室抗浮的桩顶结构。The patent of the present invention relates to the technical field of pile top structure construction, in particular, it relates to a pile top structure with foundation pit support and basement anti-floating.

背景技术Background technique

一般在普通基坑工程中,通常为了节省造价,对基坑上部进行适当放坡后设置支护桩和内支撑进行支护,但是,在毗邻建筑物的基坑工程中,由于没有放坡空间,同时为了保护建筑物,避免因基坑开挖导致建筑物沉降、倾斜等变形,通常将桩顶设置于地面,这样施工的弊端是由于桩顶位于地面,没有了放坡段,因此基坑坑底以上的支护桩长度增加,由于支护桩长度较长,因此往往需要设置更多层的内支撑,才可保证基坑和坑顶建筑物安全。将桩顶设置于地面,一方面因为设置了更多的内支撑导致工程造价增加,另一方面由于基坑分层开挖分层安装内支撑,导致最终增加了施工工期。Generally, in ordinary foundation pit engineering, in order to save cost, the upper part of the foundation pit is properly sloped and then set up with supporting piles and internal supports for support. However, in the foundation pit engineering adjacent to the building, because there is no space for grading, and at the same time, in order to protect the building and avoid the deformation of the building due to the excavation of the foundation pit, the pile top is usually set on the ground. Setting more layers of internal support can ensure the safety of foundation pit and pit roof buildings. Setting the pile top on the ground, on the one hand, increases the project cost due to the installation of more internal supports, and on the other hand, due to the layered excavation of the foundation pit and the installation of internal supports layer by layer, the construction period is finally increased.

人们为了降低工程造价和加快施工工期,有时会减少一层或多层内支撑,但是这样需要将支护桩顶部锁口梁位置降低。这样,固然减少了一层内支撑或多层内支撑,但是,在施工桩顶锁口梁和内支撑期间,需要开挖至锁口梁底部,这样桩顶锁口梁上部的土方边坡处于无支护状态。这种无支护裸露状态需要待锁口梁及其上部的钢筋混凝土挡土墙施工完成后,并在待挡土墙养护达到龄期要求后对墙后回填中粗砂后,方可结束。这样,导致从桩顶开始开挖至施工锁口梁、锁口梁养护、施工桩顶挡土墙、挡土墙养护、挡土墙后回填等期间内,桩顶以上部分的边坡始终处于无支护状态,很容易发生滑坡、崩塌,导致坑顶建筑物变形。In order to reduce the project cost and speed up the construction period, people sometimes reduce one or more layers of internal support, but this requires the position of the locking beam at the top of the support pile to be lowered. In this way, although one layer of inner support or multi-layer inner support is reduced, during the construction of the pile top lock beam and the inner support, it is necessary to excavate to the bottom of the lock beam, so that the earthwork slope on the top of the pile top lock beam is in an unsupported state. This unsupported and exposed state needs to be completed after the construction of the lock beam and the reinforced concrete retaining wall above it is completed, and after the retaining wall is maintained to meet the age requirements, the wall can be backfilled with medium-coarse sand. In this way, during the period from the excavation of the pile top to the construction of the lock beam, the maintenance of the lock beam, the construction of the pile top retaining wall, the maintenance of the retaining wall, and the backfilling after the retaining wall, the slope above the pile top is always in an unsupported state, and landslides and collapses are prone to occur, resulting in deformation of the building on the pit roof.

为了保障自基坑开挖至桩顶墙后回填期间的桩顶以上基坑稳定性,目前常用的做法是采用打设钢板桩临时支护的方式,按照以下工序施工:In order to ensure the stability of the foundation pit above the pile top during the period of backfilling from the excavation of the foundation pit to the pile top wall, the current common practice is to install temporary support with steel sheet piles, and construct according to the following procedures:

1)、首先在地面施工支护桩和止水桩,桩顶位于地面以下一定深度,上部预留部分空桩,施工完成后空桩部分回填中粗砂;1) First construct the support piles and water-stop piles on the ground. The top of the piles is located at a certain depth below the ground, and some empty piles are reserved on the upper part. After the construction is completed, the empty piles are partially backfilled with medium-coarse sand;

2)、在支护桩外侧紧贴支护桩插打一排钢板桩进行临时支护;2) Insert and drive a row of steel sheet piles on the outside of the support piles close to the support piles for temporary support;

3)、然后开始向下开挖,开挖到桩头,凿除浮浆至锁口梁底部,露出锚固钢筋,然后施工锁口梁和第一道内支撑梁;3) Then start to excavate downwards, excavate to the pile head, chisel off the laitance to the bottom of the lock beam, expose the anchoring steel bars, and then construct the lock beam and the first inner support beam;

4)、施工锁口梁上部的钢筋混凝土挡土墙,待养护达到设计强度后,拔除墙后的临时钢板桩,在拔除钢板桩留下的孔洞中回填中粗砂;4) For the reinforced concrete retaining wall on the upper part of the locking beam, after the maintenance reaches the design strength, remove the temporary steel sheet pile behind the wall, and backfill the hole left by the steel sheet pile with medium coarse sand;

5)、分层开挖和施工支撑梁直至坑底。5) Layer-by-layer excavation and construction of supporting beams until the bottom of the pit.

现有技术中的工艺虽然一定程度上解决了桩顶以上基坑临时支护的问题,但是由于需要插打钢板桩,而且后期还需要拔除钢板桩,同时对拔除钢板桩后土体留下的空洞采用中粗砂回填,因此施工麻烦,施工工期较长,而且采用中粗砂回填,不能保证回填密实,导致基坑顶部侧壁土体仍旧比较松散,长期的基坑固结沉降作用很容易导致土体变形进而引起坑顶建筑物沉降或变形。Although the technology in the existing technologies solves the problem of temporary support of the foundation pit above the top of the pile, the steel plate piles need to be removed due to the need to insert the steel plate piles. At the same time, the empty sand left after the empty cave left after the steel plate pile is removed. The soil of the side wall is still relatively loose, and the long -term foundation pit solid settlement effect can easily lead to the deformation of the soil and cause the pits or deformation.

现有施工工艺形成的桩顶结构,存在施工麻烦以及不稳固的缺陷。The pile top structure formed by the existing construction technology has the defects of troublesome construction and instability.

发明内容Contents of the invention

本发明的目的在于提供兼具基坑支挡和地下室抗浮的桩顶结构,旨在解决现有技术中,桩顶结构施工麻烦以及不稳固的问题。The purpose of the present invention is to provide a pile top structure with foundation pit support and basement anti-floating, aiming to solve the problems of troublesome construction and unstable pile top structure in the prior art.

本发明是这样实现的,兼具基坑支挡和地下室抗浮的桩顶结构,包括间隔环绕在基坑周边的多个灌注桩,所述灌注桩的顶部位于地面;所述灌注桩的上部具有显露段,所述显露段朝向基坑的内侧部形成有凿除区域,所述灌注桩内部的锚固钢筋延伸至在凿除区域中,所述显露段插设有水平植筋,所述水平植筋穿过凿除区域,延伸至基坑内部;所述凿除区域上设置有锁口梁,所述锁口梁钢筋沿着所述基坑的周边布置,且抵接在凿除区域的底部;所述锁口梁中具有锁口梁钢筋,所述锁口梁钢筋与锚固钢筋焊接;所述锁口梁的外侧部朝向所述基坑的内部外扩,形成位于所述凿除区域外侧的外突部;所述显露段具有朝向所述凿除区域的临空面;所述凿除区域中设置有挡土墙,所述挡土墙抵接在所述灌注桩的显露段的临空面;所述挡土墙内具有挡土墙钢筋,所述挡土墙钢筋的下端置于锁口梁内部,所述挡土墙钢筋的上端朝上延伸,所述锚固钢筋延伸至挡土墙内部;所述基坑中设有地下室,所述地下室的外墙自下而上抵接着所述锁口梁,与所述锁口梁的外突部锚固连接。The present invention is achieved in this way. The pile top structure with both foundation pit support and basement anti-floating includes a plurality of cast-in-place piles surrounding the periphery of the foundation pit at intervals. The tops of the cast-in-place piles are located on the ground; the upper part of the cast-in-place piles has an exposed section, and the exposed section is formed with a chiseled area toward the inner side of the foundation pit. There is a lock beam, the lock beam reinforcement is arranged along the periphery of the foundation pit, and abuts against the bottom of the chiseled area; the lock beam has a lock beam steel bar, and the lock beam steel bar is welded with the anchoring steel bar; the outer part of the lock beam expands toward the inside of the foundation pit to form an outer protrusion located outside the chiseled area; the exposed section has a free surface facing the chiseled area; There is a retaining wall reinforcement in the retaining wall, the lower end of the retaining wall reinforcement is placed inside the lock beam, the upper end of the retaining wall reinforcement extends upward, and the anchor reinforcement extends to the inside of the retaining wall; a basement is provided in the foundation pit, and the outer wall of the basement is against the lock beam from bottom to top, and is anchored and connected with the outer protrusion of the lock beam.

进一步的,所述地下室的外墙内设置有外墙钢筋,所述外墙钢筋延伸出所述地下室的外墙的顶部;所述外墙钢筋由所述锁口梁的底部朝上弯曲延伸,环绕所述锁口梁的外周,与所述锁口梁绑扎锚固。Further, the outer wall of the basement is provided with outer wall reinforcement, and the outer wall reinforcement extends out of the top of the outer wall of the basement; the outer wall reinforcement is bent upward from the bottom of the lock beam, surrounds the outer circumference of the lock beam, and is bound and anchored with the lock beam.

进一步的,所述外墙钢筋封闭环绕在所述锁口梁的外周。Further, the external wall steel bars are enclosed and surrounded by the outer periphery of the lock beam.

进一步的,所述地下室包括位于所述锁口梁下方的下部结构以及位于下部结构顶部的上部结构;所述下部结构的外周形成所述外墙,所述外墙偏离所述上部结构的外周,朝向所述锁口梁布置;所述锁口梁与所述上部结构的外周之间具有间隔;所述间隔中嵌入有填充体,所述填充体内具有间隔钢筋,所述间隔钢筋的下部与所述外墙钢筋焊接,所述间隔钢筋的上部由所述锁口梁的顶部朝下弯曲延伸,环绕所述锁口梁的外周,与所述锁口梁绑扎锚固。Further, the basement includes a substructure below the lock beam and a superstructure at the top of the lower structure; the outer periphery of the lower structure forms the outer wall, and the outer wall deviates from the outer circumference of the upper structure and is arranged toward the lock beam; there is a space between the lock beam and the outer periphery of the superstructure; a filling body is embedded in the space, and a spacer bar is embedded in the spacer. The lower bend extends, surrounds the outer circumference of the lock beam, and is tied and anchored with the lock beam.

进一步的,所述挡土墙钢筋上设置有多个插块,所述插块的内端置于挡土墙内部,所述插块的外端延伸出所述挡土墙,形成嵌入段,所述嵌入段嵌入在基坑的侧壁中。Further, the reinforcing bars of the retaining wall are provided with a plurality of inserts, the inner ends of the inserts are placed inside the retaining wall, and the outer ends of the inserts extend out of the retaining wall to form embedded sections, which are embedded in the side walls of the foundation pit.

进一步的,所述嵌入段具有朝上布置的上端面以及朝下布置的下端面,沿朝向基坑侧壁的延伸方向,所述嵌入段的上端面朝下倾斜布置,所述嵌入段的下端面朝下倾斜布置。Further, the embedded section has an upwardly arranged upper end surface and a downwardly arranged lower end surface, along the extension direction toward the side wall of the foundation pit, the upper end surface of the embedded section is arranged inclined downward, and the lower end surface of the embedded section is arranged inclined downward.

进一步的,所述嵌入段的下端面朝下倾斜的角度小于所述嵌入段的上端面朝下倾斜的角度。Further, the angle at which the lower end of the embedded section slopes downward is smaller than the angle at which the upper end of the embedded section slopes downward.

进一步的,所述嵌入段的内端部设置有定位槽,多个所述插块之间缠绕连接钢筋,所述连接钢筋嵌入在所述嵌入段的定位槽中,所述连接钢筋在多个插块之间形成网状结构;所述连接钢筋贴附在所述显露段的临空面与挡土墙的外侧面之间。Further, the inner end of the embedded section is provided with a positioning groove, and connecting steel bars are wound between a plurality of the inserts, and the connecting steel bars are embedded in the positioning grooves of the embedded section, and the connecting steel bars form a network structure between the multiple inserting blocks; the connecting steel bars are attached between the free surface of the exposed section and the outer surface of the retaining wall.

进一步的,所述嵌入段的上端面设置有倒拉刺,所述倒拉刺的下端连接在所述嵌入段的上端面,所述倒拉刺的上端背离基坑的侧壁倾斜延伸,且所述倒拉刺的上端与嵌入段的上端面之间具有倒拉间隔。Further, the upper end surface of the embedded section is provided with a barb, the lower end of the barb is connected to the upper end surface of the embedded section, the upper end of the barb extends obliquely away from the side wall of the foundation pit, and there is an inverted space between the upper end of the barb and the upper end surface of the embedded section.

进一步的,所述灌注桩之间设置有止水桩,所述止水桩的侧部与相邻的灌注桩的侧部镶嵌连接为一体。Further, water-stop piles are arranged between the cast-in-situ piles, and the side parts of the water-stop piles are inlaid and connected with the side parts of adjacent cast-in-situ piles as a whole.

与现有技术相比,本发明提供的兼具基坑支挡和地下室抗浮的桩顶结构,利用灌注桩凿除出来的凿除区域,施工形成挡土墙临时支挡土体,保证基坑不会滑坡、塌方,同时,凿除区域的锚固钢筋延伸至挡土墙内部,挡土墙抵接着灌注桩的临空面,挡土墙与灌注桩形成稳固的支挡结构;当逐层向上施工地下室时,将顶部支撑梁以及下层支撑梁梁割除,保留锁口梁,锁口梁与地下室的外墙锚固连接,当地下室受到地下水浮力上浮时,锁口梁给予地下室外墙较大的反力,保证了地下室的抗浮安全性。Compared with the prior art, the pile top structure provided by the present invention has both foundation pit support and basement anti-floating. The chiseled area excavated by cast-in-place piles is used to form a temporary retaining wall for construction to ensure that the foundation pit will not slide and collapse. At the same time, the anchor reinforcement in the chiseled area extends to the inside of the retaining wall, and the retaining wall is in contact with the empty surface of the cast-in-place pile. The beams are cut off, and the lock beams are retained, which are anchored to the outer wall of the basement. When the basement is buoyed by the buoyancy of the groundwater, the lock beams will give a large counter force to the basement outer walls, ensuring the safety of the basement against floating.

附图说明Description of drawings

图1是本发明提供的在基坑周边施工灌注桩的剖切示意图;Fig. 1 is the cut-away schematic diagram of construction cast-in-place pile around foundation pit provided by the present invention;

图2是本发明提供的在灌注桩的显露段形成凿除区域的剖切示意图;Fig. 2 is a cutaway schematic diagram of forming a chiseled area at the exposed section of the cast-in-place pile provided by the present invention;

图3是本发明提供的形成锁口梁、顶部支撑梁及挡土墙的剖切示意图;Fig. 3 is the sectional schematic view that forms lock mouth beam, top support beam and retaining wall provided by the present invention;

图4是本发明提供的开挖基坑并施工地下室的剖切示意图;Fig. 4 is the sectional schematic diagram of excavating foundation pit provided by the present invention and constructing basement;

图5是本发明提供的灌注桩、挡土墙、锁口梁以及顶部支撑梁连接的剖切示意图;Fig. 5 is a cutaway schematic diagram of the connection of cast-in-situ piles, retaining walls, lock beams and top support beams provided by the present invention;

图6是本发明提供的灌注桩的显露段、挡土墙、锁口梁以及顶部支撑梁之间的钢筋连接示意图;Fig. 6 is a schematic diagram of the reinforcement connection between the exposed section of the cast-in-place pile, the retaining wall, the lock beam and the top support beam provided by the present invention;

图7是本发明提供的锁口梁与地下室的外墙抵接的连接示意图;Fig. 7 is a schematic diagram of the connection between the locking beam provided by the present invention and the outer wall of the basement;

图8是本发明提供的外墙钢筋与锁口梁缠绕的主视示意图;Fig. 8 is a schematic front view of the winding of the external wall reinforcement provided by the present invention with the locking beam;

图9是本发明提供的间隔钢筋与锁口梁缠绕的主视示意图;Fig. 9 is a schematic front view of the winding of spaced steel bars and lock beams provided by the present invention;

图10是本发明提供的插块的主视示意图。Fig. 10 is a schematic front view of the plug provided by the present invention.

具体实施方式Detailed ways

为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.

以下结合具体实施例对本发明的实现进行详细的描述。The implementation of the present invention will be described in detail below in conjunction with specific embodiments.

本实施例的附图中相同或相似的标号对应相同或相似的部件;在本发明的描述中,需要理解的是,若有术语“上”、“下”、“左”、“右”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此附图中描述位置关系的用语仅用于示例性说明,不能理解为对本专利的限制,对于本领域的普通技术人员而言,可以根据具体情况理解上述术语的具体含义。In the drawings of this embodiment, the same or similar symbols correspond to the same or similar components; in the description of the present invention, it should be understood that if the orientation or positional relationship indicated by the terms "upper", "lower", "left", "right" etc. is based on the orientation or positional relationship shown in the accompanying drawings, it is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, so the terms describing the positional relationship in the drawings are only for illustrative purposes and cannot be used. It is understood as a limitation on this patent, and those of ordinary skill in the art can understand the specific meanings of the above terms according to specific situations.

参照图1-10所示,为本发明提供的较佳实施例。Referring to Figures 1-10, it is a preferred embodiment of the present invention.

兼具基坑支挡和地下室抗浮的桩顶结构,包括间隔环绕在基坑周边的多个灌注桩100,灌注桩100的顶部位于地面;灌注桩100的上部具有显露段101,显露段101朝向基坑的内侧部形成有凿除区域102,灌注桩100内部的锚固钢筋103延伸至在凿除区域102中,显露段101插设有水平植筋104,水平植筋104穿过凿除区域102,延伸至基坑内部。The pile top structure with both foundation pit support and basement anti-floating includes a plurality of cast-in-place piles 100 surrounding the foundation pit at intervals. The tops of the cast-in-place piles 100 are located on the ground; the upper part of the cast-in-place piles 100 has an exposed section 101, and the exposed section 101 is formed with a chiseled area 102 toward the inner side of the foundation pit. The anchoring steel bars 103 inside the cast-in-place piles 100 extend to the chiseled area 102, and the exposed section 101 is inserted with horizontal planting bars 104 , the horizontal planting bar 104 passes through the chiseled area 102 and extends to the inside of the foundation pit.

凿除区域102上设置有锁口梁200,锁口梁200沿着基坑的周边布置,且抵接在凿除区域102的底部;锁口梁200中具有锁口梁钢筋,锁口梁钢筋与锚固钢筋103焊接;锁口梁200的外侧部朝向基坑的内部外扩,形成位于凿除区域外侧的外突部。A lock beam 200 is arranged on the chisel area 102, and the lock beam 200 is arranged along the periphery of the foundation pit, and abuts against the bottom of the chiseling area 102; the lock beam 200 has a lock beam steel bar, and the lock beam steel bar is welded with the anchoring steel bar 103; the outer side of the lock beam 200 expands toward the inside of the foundation pit, forming an outer protrusion located outside the chiseling area.

显露段101具有朝向凿除区域102的临空面;凿除区域102中设置有挡土墙300,挡土墙300抵接在灌注桩100的显露段101的临空面;挡土墙300内具有挡土墙钢筋,挡土墙钢筋的下端置于锁口梁200内部,挡土墙钢筋的上端朝上延伸,锚固钢筋103延伸至挡土墙300内部;基坑中设有地下室500,地下室500的外墙自下而上抵接着所述锁口梁200,与锁口梁200的外突部锚固连接。The exposed section 101 has an empty surface facing the chiseled area 102; the chiseled area 102 is provided with a retaining wall 300, and the retaining wall 300 abuts against the air surface of the exposed section 101 of the cast-in-situ pile 100; the retaining wall 300 has a retaining wall reinforcement, the lower end of the retaining wall reinforcement is placed inside the lock beam 200, the upper end of the retaining wall reinforcement extends upwards, and the anchor reinforcement 103 extends to the inside of the retaining wall 300 A basement 500 is provided in the foundation pit, and the outer wall of the basement 500 abuts against the lock beam 200 from bottom to top, and is anchored and connected with the outer protrusion of the lock beam 200 .

上述提供的兼具基坑支挡和地下室抗浮的桩顶结构,利用灌注桩100凿除出来的凿除区域102,在凿除区域102形成挡土墙300临时支挡土体,保证基坑不会滑坡、塌方,同时,凿除区域102的锚固钢筋103延伸至挡土墙300内部,挡土墙300抵接着灌注桩100的临空面,挡土墙300与灌注桩100形成稳固的支挡结构;锁口梁200与地下室500的外墙锚固连接,当地下室500受到地下水浮力上浮时,锁口梁200给予地下室500外墙较大的反力,保证了地下室500的抗浮安全性。The above-mentioned pile top structure provided with both foundation pit support and basement anti-floating uses the excavated area 102 excavated by cast-in-place piles 100 to form a temporary retaining wall 300 in the excavated area 102 to ensure that the foundation pit will not landslide or collapse. The pile 100 forms a stable supporting structure; the lock beam 200 is anchored to the outer wall of the basement 500, and when the basement 500 is buoyantly lifted by the groundwater, the lock beam 200 gives a relatively large reaction force to the outer wall of the basement 500, ensuring the safety of the basement 500 against floating.

本实施例还提供了上述兼具基坑支挡和地下室抗浮的桩顶结构的施工方法,包括以下施工步骤:This embodiment also provides a construction method for the above-mentioned pile top structure with both foundation pit support and basement anti-floating, including the following construction steps:

1)、在毗邻建筑物的基坑周边地面施工多个环绕基坑周边间隔布置的灌注桩100,所述灌注桩100的顶部位于地面;1), constructing a plurality of cast-in-place piles 100 arranged at intervals around the periphery of the foundation pit on the ground around the foundation pit adjacent to the building, and the tops of the cast-in-situ piles 100 are located on the ground;

可以采用钻机钻孔,形成灌注桩孔,安装钢筋笼,并浇筑混凝土至设计桩顶位置,然后待灌注桩100养护达到设计强度后方可继续开挖;Drilling rigs can be used to form cast-in-situ pile holes, steel cages are installed, and concrete is poured to the designed pile top position, and then the excavation can only be continued after the cast-in-situ piles 100 are cured to reach the design strength;

2)、由地面向下开挖基坑,直至待施工锁口梁200的位置,在开挖过程中,灌注桩100具有显露出来的显露段101,也就是说,在开挖基坑的过程中,随着土体的挖掘,灌注桩100顶部部分会显露出来,形成显露段101;2) Excavate the foundation pit from the ground until the position of the locking beam 200 to be constructed. During the excavation process, the cast-in-place pile 100 has an exposed section 101, that is to say, during the excavation of the foundation pit, with the excavation of the soil, the top part of the cast-in-place pile 100 will be exposed, forming the exposed section 101;

将灌注桩100的显露段101朝向基坑的内侧部的混凝土凿除,形成凿除区域102,灌注桩100内部的锚固钢筋103显露在凿除区域102中;相当于将灌注桩100的显露段101的部分凿除混凝土,但是,被凿除部分中的锚固钢筋103保留着;The exposed section 101 of the cast-in-situ pile 100 is chiseled away towards the inner side of the foundation pit to form a chiseled area 102, and the anchoring steel bar 103 inside the cast-in-place pile 100 is exposed in the chiseled area 102; it is equivalent to chiseling out the concrete of the exposed section 101 of the cast-in-situ pile 100, but the anchoring steel bar 103 in the chiseled part remains;

3)、将凿除区域102的锚固钢筋103调至竖直状,在灌注桩100的显露段101水平钻孔,形成水平孔,在水平钻孔中插入水平植筋104,水平植筋104穿过凿除区域102,延伸至基坑内部;3), adjust the anchoring reinforcement 103 in the chiseled area 102 to a vertical shape, drill horizontally at the exposed section 101 of the cast-in-situ pile 100, form a horizontal hole, insert a horizontal planting bar 104 in the horizontal borehole, and the horizontal planting bar 104 passes through the chiseled area 102, and extends to the inside of the foundation pit;

4)、绑扎锁口梁钢筋,锁口梁钢筋与凿除区域102的锚固钢筋103焊接,,锁口梁钢筋与锚固钢筋103则连接为一体;锁口梁钢筋沿着所述基坑的周边布置,且抵接在凿除区域102的底部;绑扎支撑梁钢筋,支撑梁钢筋横跨基坑,且支撑梁钢筋的端部与水平植筋104焊接;在锁口梁钢筋及支撑梁钢筋的外部支模浇筑混凝土,形成锁口梁200以及顶部支撑梁201,锁口梁200的外侧部朝向所述基坑的内部外扩,形成位于凿除区域102外侧的外突部;4), binding the lock beam reinforcement, the lock beam reinforcement is welded with the anchor reinforcement bar 103 in the chiseled area 102, and the lock beam reinforcement bar and the anchor reinforcement bar 103 are then connected as one; the lock beam reinforcement is arranged along the periphery of the foundation pit, and abuts against the bottom of the excavation area 102; the support beam reinforcement is bound, the support beam reinforcement spans the foundation pit, and the end of the support beam reinforcement is welded with the horizontal planting bar 104; Concrete is poured in the external formwork to form the lock beam 200 and the top support beam 201, and the outer side of the lock beam 200 expands toward the inside of the foundation pit to form an outer protrusion located on the outside of the chiseled area 102;

5)、灌注桩100的显露段101具有朝向所述凿除区域102的临空面;在凿除区域102中绑扎竖直布置的挡土墙钢筋,挡土墙钢筋的下端置于锁口梁200内部,挡土墙钢筋的上端朝上延伸,在挡土墙钢筋的外部支模浇筑混凝土,形成挡土墙300,挡土墙300抵接在灌注桩100的显露段101的临空面,锚固钢筋103延伸至挡土墙300内部。5), the exposed section 101 of the cast-in-place pile 100 has a free surface facing the chiseled area 102; in the chiseled area 102, the vertically arranged retaining wall reinforcement is bound, the lower end of the retaining wall reinforcement is placed inside the lock beam 200, the upper end of the retaining wall reinforcement extends upwards, and concrete is cast outside the retaining wall reinforcement to form a retaining wall 300, and the retaining wall 300 abuts against the exposed section 1 of the cast-in-place pile 100 01, the anchoring steel bar 103 extends to the interior of the retaining wall 300.

6)、朝下开挖基坑,并施工下层支撑梁,直至开挖至基坑的底部;6) Excavate the foundation pit downwards, and construct the lower support beams until the bottom of the foundation pit is excavated;

7)、在基坑的底部朝上施工地下室500,并依序割除下层支撑梁以及顶部支撑梁201,地下室500的外墙自下而上抵接着锁口梁200,与锁口梁200的外突部锚固连接。7) Build the basement 500 upwards at the bottom of the foundation pit, and cut off the lower support beams and the top support beams 201 in sequence. The outer wall of the basement 500 abuts the lock beam 200 from bottom to top, and is anchored and connected with the outer protrusion of the lock beam 200.

利用灌注桩100凿除出来的凿除区域102,施工形成挡土墙300临时支挡土体,保证基坑不会滑坡、塌方,同时,凿除区域102的锚固钢筋103延伸至挡土墙300内部,挡土墙300抵接着灌注桩100的临空面,挡土墙300与灌注桩100形成稳固的支挡结构;当逐层向上施工地下室500时,将顶部支撑梁201以及下层支撑梁梁割除,保留锁口梁200,锁口梁200与地下室500的外墙锚固连接,当地下室500受到地下水浮力上浮时,锁口梁200给予地下室500外墙较大的反力,保证了地下室500的抗浮安全性。Utilize cast-in-place pile 100 to chisel out area 102, construct and form retaining wall 300 to temporarily support retaining soil body, guarantee that foundation pit will not landslide, collapse, meanwhile, the anchoring steel bar 103 of chiseling area 102 extends to retaining wall 300 inside, retaining wall 300 abuts against the free surface of cast-in-place pile 100, retaining wall 300 and cast-in-place pile 100 form a stable supporting structure; when building basement 500 layer by layer, the top The support beams 201 and the lower support beams are cut off, and the lock beams 200 are retained. The lock beams 200 are anchored and connected to the outer wall of the basement 500. When the basement 500 is buoyed up by the buoyancy of the groundwater, the lock beams 200 give a relatively large reaction force to the outer walls of the basement 500, ensuring the anti-floating safety of the basement 500.

兼具基坑支挡和地下室抗浮的桩顶结构,融合灌注桩100以上部分基坑支护结构和后期地下室500抗浮,兼具灌注桩100以上部分基坑支护和地下室500抗浮两种功能。The pile top structure with both foundation pit support and basement anti-floating, integrates the foundation pit support structure of more than 100 piles and the later basement 500 anti-floating, and has two functions of foundation pit support of more than 100 piles and basement 500 anti-floating.

地下室500的外墙内设置有外墙钢筋503,外墙钢筋503延伸出地下室500的外墙的顶部;外墙钢筋503由锁口梁200的底部朝上弯曲延伸,环绕锁口梁200的外周,与锁口梁200绑扎锚固。The outer wall of the basement 500 is provided with an outer wall steel bar 503, and the outer wall steel bar 503 extends out of the top of the outer wall of the basement 500;

这样,使得地下室500的外墙与锁口梁200之间的结构更为稳固一体化,进一步保证地下室500的抗浮安全性。In this way, the structure between the outer wall of the basement 500 and the lock beam 200 is more stable and integrated, further ensuring the anti-floating safety of the basement 500 .

外墙钢筋503封闭环绕在锁口梁200的外周。The external wall steel bar 503 is closed and surrounds the outer periphery of the lock beam 200 .

地下室500包括位于锁口梁200下方的下部结构502以及位于下部结构502顶部的上部结构501;下部结构502的外周形成上述的外墙,外墙偏离上部结构501的外周,朝向锁口梁200布置,锁口梁200与所述上部结构501的外周之间具有间隔203。The basement 500 includes a substructure 502 below the lock beam 200 and a superstructure 501 at the top of the substructure 502; the outer periphery of the lower structure 502 forms the above-mentioned outer wall, and the outer wall deviates from the outer periphery of the upper structure 501 and is arranged toward the locking beam 200, and there is a gap 203 between the locking beam 200 and the outer periphery of the upper structure 501.

在间隔203中绑扎间隔钢筋204,间隔钢筋204的下部与外墙钢筋503焊接,间隔钢筋204的上部由锁口梁200的顶部朝下弯曲延伸,环绕锁口梁200的外周,与锁口梁200绑扎锚固;在间隔中浇筑混凝土,形成嵌入在间隔203中的填充体。Bind spaced steel bars 204 in the space 203, the lower part of the spaced steel bar 204 is welded with the external wall steel bar 503, and the top of the spaced steel bar 204 is bent downward from the top of the lock beam 200, and surrounds the outer circumference of the lock beam 200, and is tied and anchored with the lock beam 200; concrete is poured in the space to form a filling body embedded in the space 203.

这样,通过在间隔203中绑扎间隔钢筋204,施工成型嵌入在间隔203中的填充体,且间隔钢筋204与外墙钢筋503焊接形成一体,同时,间隔钢筋204朝下弯曲环绕锁口梁200的外周,使得填充体与锁口梁200形成一体。In this way, by binding the spacer bars 204 in the spacer 203, the filling body embedded in the spacer 203 is constructed and formed, and the spacer bar 204 is welded with the external wall steel bar 503 to form an integral body.

另外,间隔钢筋204与外墙钢筋503的弯曲环绕锁口梁200方向相反,可以施加给锁口梁200自上及自下的抵接力,使得地下室500的外墙及填充体分别自上及自下与锁口梁200形成一体,三者之间以锁口梁200为中间过渡稳固连接在一体。In addition, the spacer reinforcement bars 204 and the outer wall reinforcement bars 503 bend around the lock beam 200 in opposite directions, and can exert a contact force on the lock beam 200 from above and below, so that the outer wall and filling body of the basement 500 form an integral body with the lock beam 200 from above and below, respectively, and the three are firmly connected together with the lock beam 200 as the intermediate transition.

挡土墙钢筋上设置有多个插块,插块的内端置于挡土墙300内部,插块的外端延伸出挡土墙300,形成嵌入段706,嵌入段706嵌入在基坑的侧壁中。这样,挡土墙300不仅与灌注桩100形成为一体,且挡土墙钢筋的插块嵌入基坑的土体中,可以将挡土墙300与基坑的土体形成一体,且给基坑的土体施加朝外的压力,更好避免基坑出现滑坡或塌方的问题。The reinforcing bars of the retaining wall are provided with a plurality of inserting blocks, the inner ends of the inserting blocks are placed inside the retaining wall 300, and the outer ends of the inserting blocks extend out of the retaining wall 300 to form an embedded section 706, which is embedded in the side wall of the foundation pit. In this way, the retaining wall 300 is not only integrated with the cast-in-situ pile 100, but also the inserts of the reinforcing bars of the retaining wall are embedded in the soil of the foundation pit, so that the retaining wall 300 and the soil of the foundation pit can be integrated, and the soil of the foundation pit is exerted outward pressure, so as to better avoid landslides or landslides in the foundation pit.

嵌入段706具有朝上布置的上端面704以及朝下布置的下端面705,沿朝向基坑侧壁的延伸方向,嵌入段706的上端面704朝下倾斜布置,嵌入段706的下端面705朝下倾斜布置。这样,整个嵌入段706朝下倾斜弯曲布置,当嵌入段706插入在基坑的土体中后,可以自上而下锚固土体,避免基坑土体给予挡土墙300额外的冲击力,更好的支护基坑。The embedded section 706 has an upwardly arranged upper end surface 704 and a downwardly arranged lower end surface 705. Along the extension direction toward the side wall of the foundation pit, the upper end surface 704 of the embedded section 706 is arranged inclined downward, and the lower end surface 705 of the embedded section 706 is arranged inclined downward. In this way, the entire embedding section 706 is inclined and bent downward. When the embedding section 706 is inserted into the soil of the foundation pit, it can anchor the soil from top to bottom, avoiding the extra impact force of the foundation pit soil on the retaining wall 300 and better supporting the foundation pit.

嵌入段706的下端面705朝下倾斜的角度小于嵌入段706的上端面704朝下倾斜的角度,这样,嵌入段706使得嵌入段706可以更好的锚固土体。The angle at which the lower end surface 705 of the embedded section 706 inclines downward is smaller than the angle at which the upper end surface 704 of the embedded section 706 inclines downward. In this way, the embedded section 706 enables the embedded section 706 to better anchor the soil.

嵌入段706的内端部设置有定位槽703,在多个插块之间缠绕连接钢筋,连接钢筋嵌入在嵌入段706的定位槽703中,连接钢筋在多个插块之间形成网状结构;当浇筑好挡土墙300后,连接钢筋贴附在显露段101的临空面与挡土墙300的外侧面之间。The inner end of the embedded section 706 is provided with a positioning groove 703, and the connecting steel bar is wound between multiple inserts. The connecting steel bar is embedded in the positioning groove 703 of the embedded section 706, and the connecting steel bar forms a network structure between the multiple inserting blocks;

通过连接钢筋与多个嵌入段706的定位槽703的缠绕连接,连接钢筋形成网状结构,这样,多个嵌入段706则通过连接钢筋形成整体结构,且网状结构的连接钢筋抵接着在显露段101的临空面,增强多个嵌入段706形成整体与土体的锚固稳固性,当挡土墙300支护的土体出现局部冲击时,由于多个嵌入段706通过连接钢筋形成整体结构,从而多个嵌入段706不会出现局部脱离土体的现象。Through the winding connection between the connecting steel bars and the positioning grooves 703 of the multiple embedded sections 706, the connecting steel bars form a network structure. In this way, the multiple embedded sections 706 form an integral structure through the connecting steel bars, and the connecting steel bars of the network structure are abutted against the air surface of the exposed section 101 to enhance the anchoring stability of the whole and the soil formed by the multiple embedded sections 706. The embedding section 706 will not be partially detached from the soil.

嵌入段706的上端面设置有倒拉刺701,倒拉刺701的下端连接在嵌入段706的上端面704,倒拉刺701的上端背离基坑的侧壁倾斜延伸,且倒拉刺701的上端与嵌入段706的上端面704之间具有倒拉间隔702。The upper end surface of the embedded section 706 is provided with an inverted thorn 701, the lower end of the inverted thorn 701 is connected to the upper end surface 704 of the embedded section 706, and the upper end of the inverted thorn 701 extends obliquely away from the side wall of the foundation pit, and there is an inverted interval 702 between the upper end of the inverted thorn 701 and the upper end surface 704 of the embedded section 706.

这样,通过形成倒拉刺701,使得嵌入段706可以与土体之间锚固更为稳固,且倒拉刺701与嵌入段706的上端面之间具有倒拉间隔702,土体会嵌入到倒拉间隔702中,这样,嵌入段706与土体之间则形成多处嵌入锚固,使得嵌入段706与土体之间连接更为稳固。In this way, by forming the inverted thorns 701, the embedded section 706 can be more firmly anchored to the soil, and there is an inverted interval 702 between the inverted thorns 701 and the upper end surface of the embedded section 706, and the soil will be embedded in the inverted interval 702. In this way, multiple embedded anchors are formed between the embedded section 706 and the soil, making the connection between the embedded section 706 and the soil more stable.

在毗邻建筑物的基坑周边地面施工多个环绕基坑周边间隔布置的止水桩400,灌注桩100的顶部位于地面;止水桩400的侧部与相邻的灌注桩100的侧部镶嵌连接为一体。On the ground around the foundation pit adjacent to the building, a plurality of water-stop piles 400 arranged at intervals around the periphery of the foundation pit are constructed. The tops of the cast-in-place piles 100 are located on the ground;

在毗邻建筑物附近需要开挖时,在开挖前首先施工灌注桩100和灌注桩100之间的止水桩400,灌注桩100一般为钢筋混凝土钻孔灌注桩100,止水桩400一般为高压旋转喷射注浆桩,灌注桩100和止水桩400相互咬合组合为兼具支护和止水双重功能的支护桩结构,同时,后期地下室500和锁口梁200锚固在一起,当地下室500受到地下水浮力上浮时,灌注桩100本身的抗拔力可保证地下室500结构不会上浮变形或破坏。When excavation is required near the adjacent buildings, the water-stop pile 400 between the cast-in-place pile 100 and the cast-in-place pile 100 is constructed first before excavation. The cast-in-place pile 100 is generally a reinforced concrete bored pile 100, and the water-stop pile 400 is generally a high-pressure rotary jet grouting pile. Together, when the basement 500 floats up under the buoyancy of the groundwater, the pullout resistance of the cast-in-place pile 100 can ensure that the structure of the basement 500 will not be deformed or damaged.

本实施例中,待灌注桩100养护达到设计强度要求后,在相邻的灌注桩100之间钻孔施工高压旋喷的止水桩400,然后待止水桩400养护达到设计强度后方可继续开挖。In this embodiment, after the cast-in-situ piles 100 are cured to meet the design strength requirements, the high-pressure rotary jetting water-stop piles 400 are drilled between adjacent cast-in-place piles 100, and then the excavation can be continued after the water-stop piles 400 are maintained to reach the design strength.

以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present invention shall be included within the protection scope of the present invention.

Claims (3)

1. The pile top structure with foundation pit supporting and retaining functions and basement anti-floating functions is characterized by comprising a plurality of filling piles which are arranged around the periphery of a foundation pit at intervals, wherein the tops of the filling piles are positioned on the ground; the upper part of the cast-in-place pile is provided with an exposure section, a chiseling area is formed at the exposure section towards the inner side part of the foundation pit, the anchoring steel bars inside the cast-in-place pile extend into the chiseling area, the exposure section is inserted with horizontal steel bar planting, and the horizontal steel bar planting passes through the chiseling area and extends into the foundation pit; the chiseling area is provided with locking beams which are arranged along the periphery of the foundation pit and are abutted to the bottom of the chiseling area; the locking port beam is internally provided with a locking port beam steel bar, and the locking port beam steel bar is welded with the anchoring steel bar; the outer side part of the locking port beam expands outwards towards the interior of the foundation pit to form an outer protruding part positioned at the outer side of the chiseled-out area; the exposed section has a free face facing the chiseled area; a retaining wall is arranged in the chiseling area and is abutted against the free surface of the exposed section of the cast-in-place pile; the retaining wall is internally provided with retaining wall steel bars, the lower ends of the retaining wall steel bars are arranged in the locking port beams, the upper ends of the retaining wall steel bars extend upwards, and the anchoring steel bars extend into the retaining wall; the foundation pit is internally provided with a basement, and the outer wall of the basement is abutted against the locking port beam from bottom to top and is connected with the outer protruding part of the locking port beam in an anchoring manner;
an outer wall reinforcing steel bar is arranged in the outer wall of the basement, and extends out of the top of the outer wall of the basement; the outer wall reinforcing steel bars are bent upwards from the bottom of the fore shaft beam, encircle the periphery of the fore shaft beam and are bound and anchored with the fore shaft beam;
the basement comprises a lower structure positioned below the fore shaft beam and an upper structure positioned at the top of the lower structure; the outer periphery of the lower structure forms the outer wall, and the outer wall deviates from the outer periphery of the upper structure and is arranged towards the fore shaft beam; a space is arranged between the fore shaft beam and the periphery of the upper structure; a filling body is embedded in the space, a spacing steel bar is arranged in the filling body, the lower part of the spacing steel bar is welded with the outer wall steel bar, the upper part of the spacing steel bar is bent downwards from the top of the fore shaft beam, surrounds the periphery of the fore shaft beam and is bound and anchored with the fore shaft beam;
the outer wall steel bars are enclosed and encircle the periphery of the locking port beam; the direction of the bending surrounding locking beams of the spacing steel bars and the outer wall steel bars is opposite;
the retaining wall reinforcing steel bar is provided with a plurality of inserting blocks, the inner ends of the inserting blocks are arranged in the retaining wall, the outer ends of the inserting blocks extend out of the retaining wall to form embedded sections, and the embedded sections are embedded into the side walls of the foundation pit;
the inner end part of the embedded section is provided with a positioning groove, connecting steel bars are wound among the plurality of inserting blocks, the connecting steel bars are embedded into the positioning groove of the embedded section, and a net-shaped structure is formed among the plurality of inserting blocks by the connecting steel bars; the connecting steel bars are attached between the free surface of the exposed section and the outer side surface of the retaining wall;
the embedded section is provided with an upper end face which is arranged upwards and a lower end face which is arranged downwards, the upper end face of the embedded section is arranged downwards in an inclined manner along the extending direction towards the side wall of the foundation pit, and the lower end face of the embedded section is arranged downwards in an inclined manner;
the upper end face of embedding section is provided with the back and draws thorn, the lower extreme of back draws thorn is connected the up end of embedding section, the upper end of back draws thorn deviates from the lateral wall slope extension of foundation ditch, just have the back and draw the interval between the upper end of back drawing thorn and the up end of embedding section.
2. The pile top structure with foundation pit support and basement anti-floating as claimed in claim 1, wherein the angle of downward inclination of the lower end surface of the embedded section is smaller than the angle of downward inclination of the upper end surface of the embedded section.
3. The pile top structure with foundation pit support and basement anti-floating functions as claimed in claim 1, wherein water stop piles are arranged between the filling piles, and the side parts of the water stop piles are connected with the side parts of the adjacent filling piles in an inlaid mode.
CN202210055081.XA 2022-01-18 2022-01-18 Pile top structure with foundation pit supporting and retaining functions and basement anti-floating function Active CN114622569B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210055081.XA CN114622569B (en) 2022-01-18 2022-01-18 Pile top structure with foundation pit supporting and retaining functions and basement anti-floating function

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210055081.XA CN114622569B (en) 2022-01-18 2022-01-18 Pile top structure with foundation pit supporting and retaining functions and basement anti-floating function

Publications (2)

Publication Number Publication Date
CN114622569A CN114622569A (en) 2022-06-14
CN114622569B true CN114622569B (en) 2023-07-25

Family

ID=81897960

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210055081.XA Active CN114622569B (en) 2022-01-18 2022-01-18 Pile top structure with foundation pit supporting and retaining functions and basement anti-floating function

Country Status (1)

Country Link
CN (1) CN114622569B (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN214832624U (en) * 2021-05-27 2021-11-23 杭州市勘测设计研究院有限公司 Fender pile reinforced structure

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102943492A (en) * 2012-11-26 2013-02-27 中铁第四勘察设计院集团有限公司 Anti-floating structure for open trench tunnel
CN207121926U (en) * 2017-08-09 2018-03-20 江苏华都建设有限公司 Pattern foundation pit supporting structure retaining wall
CN109208654A (en) * 2018-10-26 2019-01-15 中铁第勘察设计院集团有限公司 The anti-floating system and its construction method that corbel type crown beam is combined with oblique type capping beam
CN110106919A (en) * 2019-05-28 2019-08-09 成都市建筑设计研究院 Enclosure structure and construction method of a cover-excavation station
KR102137484B1 (en) * 2020-02-18 2020-07-24 (주)네오크로스구조엔지니어링 Construction methods of aseismatic structure for slurry wall
CN112031026A (en) * 2020-09-29 2020-12-04 广州地铁集团有限公司 Permanent-temporary combined open-cut and smooth-built structure for subway station and construction method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN214832624U (en) * 2021-05-27 2021-11-23 杭州市勘测设计研究院有限公司 Fender pile reinforced structure

Also Published As

Publication number Publication date
CN114622569A (en) 2022-06-14

Similar Documents

Publication Publication Date Title
US9567720B2 (en) Offshore platform for a marine environment
JP5584542B2 (en) Ground deformation prevention method and underground structure construction method using the same
JP2009084919A (en) Ground excavation method
KR101041274B1 (en) Synthetic Grouting Fixture Structure and Construction Method
JP3752560B2 (en) Basic structure for constructing a new building in an existing basement and its construction method
CN114482099A (en) Steel sheet pile cofferdam construction method
KR100360462B1 (en) Method to construct a structure on soft soil and the structure thereof
CN114622569B (en) Pile top structure with foundation pit supporting and retaining functions and basement anti-floating function
CN114622568B (en) Construction method of pile top structure with foundation pit supporting and retaining functions and basement anti-floating function
CN113957880B (en) Construction method of steel-concrete underground continuous wall
CN116122333A (en) A reverse construction method for deep foundation pit basement
CN113882431B (en) Construction method for dismantling cofferdam at end head
KR20110014901A (en) Steel pipe pile provided with excavation wings and filled with concrete, and construction method
CN216194845U (en) Pebble covering layer steel sheet pile cofferdam system
JP5375549B2 (en) How to construct a retaining wall
JP4911242B2 (en) Reinforcement structure of existing gravity quay
CN113323026A (en) Soft soil layer existing building side-excavation deep foundation pit front reinforcing structure and reinforcing method thereof
JP4440799B2 (en) Ground excavation method
KR102149709B1 (en) Deformation prevention method of files for retaining wall of underground
KR200373276Y1 (en) Steel pipe pile of support structure
CN110185295A (en) A kind of the anti-floating underground garage and its construction method of only support pile
CN220150349U (en) Space-limited slope upper filling slope retaining structure
JP3728659B2 (en) Basement extension method
CN214993890U (en) A utility tunnel excavation supporting construction for morals and manners stratum area
JP6800365B1 (en) How to reinforce the existing caisson foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant