[go: up one dir, main page]

CN110685286A - A deep foundation pit support construction technology adjacent to the road under complex geological conditions - Google Patents

A deep foundation pit support construction technology adjacent to the road under complex geological conditions Download PDF

Info

Publication number
CN110685286A
CN110685286A CN201911004456.4A CN201911004456A CN110685286A CN 110685286 A CN110685286 A CN 110685286A CN 201911004456 A CN201911004456 A CN 201911004456A CN 110685286 A CN110685286 A CN 110685286A
Authority
CN
China
Prior art keywords
foundation pit
support
construction
geological conditions
rock
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911004456.4A
Other languages
Chinese (zh)
Inventor
邓利平
冉华
廖荣
胡宗峰
万轶
万昭
李伟
张骏程
李宇
康旆
王贝
廖勇
吴加洋
郭啸天
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 8 Engineering Group Co Ltd
Fourth Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Original Assignee
China Railway No 8 Engineering Group Co Ltd
Fourth Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 8 Engineering Group Co Ltd, Fourth Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd filed Critical China Railway No 8 Engineering Group Co Ltd
Priority to CN201911004456.4A priority Critical patent/CN110685286A/en
Publication of CN110685286A publication Critical patent/CN110685286A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/08Restraining of underground water by employing open ditches arranged below the level of the water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

本发明公开了一种复杂地质条件下临近道路的深基坑支护施工工艺,包括以下步骤:步骤1、在道路旁进行基坑开挖至岩石层,进行放坡施工,形成第一基坑;步骤2、沿第一基坑的坑底边缘打设第一柱桩形成第一斜柱支撑;步骤3、在第一基坑的坑底处开挖岩石层形成第二基坑,进行放坡施工,然后进行锚杆支护;步骤4、沿第二基坑的坑底边缘打设第二柱桩形成第二斜柱支撑。本发明通过采用斜柱支护+锚杆支护+斜柱支护的方式来对深基坑的支护,解决了复杂地质条件下临近道路的深基坑支护难、施工成本高、易出现安全隐患等问题,实现了复杂地质条件下临近道路的深基坑支护施工,为支护施工领域提供了成功的实践经验。

Figure 201911004456

The invention discloses a deep foundation pit support construction process adjacent to a road under complex geological conditions, comprising the following steps: Step 1. Excavate the foundation pit beside the road to the rock layer, carry out grading construction, and form a first foundation pit ; Step 2, drive the first column pile along the edge of the pit bottom of the first foundation pit to form the first inclined column support; Step 3, excavate the rock layer at the pit bottom of the first foundation pit to form the second foundation pit, and carry out placement Slope construction, and then bolt support; step 4, driving a second column pile along the edge of the pit bottom of the second foundation pit to form a second inclined column support. The present invention supports the deep foundation pit by adopting the method of inclined column support + bolt support + inclined column support, so as to solve the difficulty of supporting the deep foundation pit adjacent to the road under complex geological conditions, high construction cost and easy In the event of safety hazards and other problems, the deep foundation pit support construction adjacent to the road under complex geological conditions has been realized, providing a successful practical experience for the field of support construction.

Figure 201911004456

Description

一种复杂地质条件下临近道路的深基坑支护施工工艺A deep foundation pit support construction technology adjacent to the road under complex geological conditions

技术领域technical field

本发明涉及基坑支护施工技术领域,特别涉及一种复杂地质条件下临近道路的深基坑支护施工工艺。The invention relates to the technical field of foundation pit support construction, in particular to a deep foundation pit support construction technique adjacent to a road under complex geological conditions.

背景技术Background technique

基坑支护是为保证地下结构施工及基坑周边环境的安全,对基坑侧壁及周边环境采用的支挡、加固与保护与地下水控制的临时措施,基坑支护工程是个临时工程,设计的安全储备相对较小,但其造价高,开工数量多,技术复杂,是建筑工程中最具有挑战性的技术上的难点,同时也是降低工程造价,确保工程质量的重点。The foundation pit support is a temporary measure of support, reinforcement and protection and groundwater control for the side wall of the foundation pit and the surrounding environment to ensure the safety of the construction of the underground structure and the surrounding environment of the foundation pit. The foundation pit support project is a temporary project. The design safety reserve is relatively small, but its high cost, large number of starts, and complex technology are the most challenging technical difficulties in construction projects, and it is also the focus of reducing project cost and ensuring project quality.

基坑支护的形式主要有排桩支护、水泥挡土墙、土钉墙、地下连续墙支护、逆作拱墙等,一般地,这些基坑支护形式主要根据基坑深度不同而适用不同,然而,对于复杂地质条件下的深基坑支护,其地质条件基本是软硬地质分层出现,一直是施工方的重点和难点,而如何运用这些基坑支护形式,则需要根据深基坑具体复杂地质条件来确定。以申请人所承接的成兰铁路成都至川主寺段CLZF-2标工程为例,在修筑黄胜关及川主寺站房工程时,现场临时场地较狭窄,基坑开挖线距现场临时道路约50cm,基坑深度超过5m,地质条件复杂,地层上部为松散、湿度很高的土层,下部为坚硬紧凑的岩石层,如果采用常规的连续式垂直挡土板支撑(水平挡土板不适宜深度超过5m的基坑),则由于土层只有2-3m和临近道路的原因,垂直挡土板并不能有效起到挡土作用,基坑壁也不适宜做成垂直式,土体在承压下易变形、坍塌,相应地,如果采用现有的排桩支护结构,则由于坚硬岩石层的存在,混凝土灌注桩受到的剪切力较大,也不能形成有效的支护作用。因此,传统单一的支护形式不能形成有效的支护结构,而如果组合使用支护形式,由于没有可以借鉴的实例,根据各个支护形式的特点,技术人员能够想到的是,采用连续式垂直挡土板支撑+排桩支护的方式来解决,然而该方式的主要缺点是,岩石层不是垂直放坡结构,导致岩石层边坡与排桩之间存在较大间隙,需要回填大量土体来填充,施工量大,后期清理麻烦,同时,由于深度较深,需要制作高度较高的灌注桩,施工成本高,并且,当边坡出现溃破和滚石时,排桩拦截剪切力受力过大,易出现安全隐患,因此,该方式也不适用,亟需开发一种适合复杂地质条件下,特别是边坡表面临近道路的情况下,深基坑支护的施工工艺。The forms of foundation pit support mainly include row pile support, cement retaining wall, soil nail wall, underground diaphragm wall support, reverse arch wall, etc. Generally, these foundation pit support forms are mainly based on the depth of the foundation pit. The application is different. However, for the deep foundation pit support under complex geological conditions, the geological conditions are basically the emergence of soft and hard geological layers, which has always been the focus and difficulty of the construction party. How to use these foundation pit support forms requires It is determined according to the specific and complex geological conditions of the deep foundation pit. Taking the CLZF-2 bid project of the Chengdu-Chuanzhusi section of the Chengdu-Lanzhou Railway undertaken by the applicant as an example, during the construction of the Huangshengguan and Chuanzhusi station buildings, the temporary site on site was relatively narrow, and the excavation line of the foundation pit was temporarily away from the site. The road is about 50cm, the depth of the foundation pit is more than 5m, and the geological conditions are complex. The upper part of the stratum is a loose, high-humidity soil layer, and the lower part is a hard and compact rock layer. It is not suitable for foundation pits with a depth of more than 5m), then because the soil layer is only 2-3m and the road is adjacent, the vertical retaining plate cannot effectively retain the soil, and the foundation pit wall is not suitable for vertical type. It is easy to deform and collapse under pressure. Correspondingly, if the existing pile supporting structure is used, due to the existence of the hard rock layer, the concrete cast-in-place pile is subjected to a large shear force and cannot form an effective supporting effect. . Therefore, the traditional single support form cannot form an effective support structure, and if the support form is used in combination, since there are no examples to draw on, according to the characteristics of each support form, the technician can think of using a continuous vertical However, the main disadvantage of this method is that the rock layer is not a vertical grading structure, resulting in a large gap between the rock layer slope and the row of piles, and a large amount of soil needs to be backfilled To fill, the construction volume is large, and the later cleaning is troublesome. At the same time, due to the deep depth, it is necessary to make high-height cast-in-place piles, and the construction cost is high. In addition, when the slope collapses and rolling stones occur, the piles intercept the shear force and are affected. If the force is too large, it is easy to cause potential safety hazards. Therefore, this method is not suitable. It is urgent to develop a construction technology suitable for deep foundation pit support under complex geological conditions, especially when the slope surface is close to the road.

发明内容SUMMARY OF THE INVENTION

本发明的发明目的在于:针对上述存在的问题,提供一种复杂地质条件下临近道路的深基坑支护施工工艺,本发明采用斜柱支护+锚杆支护+斜柱支护的方式来对深基坑的支护,解决了复杂地质条件下临近道路的深基坑支护难、施工成本高、易出现安全隐患等问题。The purpose of the present invention is to: in view of the above-mentioned problems, provide a deep foundation pit support construction technology near the road under complex geological conditions, the present invention adopts the mode of inclined column support + bolt support + inclined column support To support the deep foundation pit, it solves the problems of difficult support, high construction cost, and potential safety hazards for the deep foundation pit adjacent to the road under complex geological conditions.

本发明采用的技术方案如下:一种复杂地质条件下临近道路的深基坑支护施工工艺,其特征在于,包括以下步骤:The technical scheme adopted in the present invention is as follows: a deep foundation pit support construction technology adjacent to a road under complex geological conditions, is characterized in that, comprises the following steps:

步骤1、在道路旁进行基坑开挖,直到基坑底部到达岩石层为止,同时对形成的基坑进行放坡施工,形成第一基坑;Step 1. Carry out foundation pit excavation beside the road until the bottom of the foundation pit reaches the rock layer, and at the same time carry out grading construction on the formed foundation pit to form the first foundation pit;

步骤2、沿第一基坑的坑底边缘打设第一柱桩,在第一柱桩内侧支设挡土板并用第一斜撑支顶,挡土板内侧填土夯实形成第一斜柱支撑;Step 2. Drive a first column pile along the edge of the pit bottom of the first foundation pit, support a retaining plate inside the first column pile and support the top with a first diagonal brace, and fill and compact the inner side of the retaining plate to form a first inclined column support;

步骤3、在第一基坑的坑底处开挖岩石层形成第二基坑,开挖起点距离第一斜柱支撑0.5-2m,开挖深度直至达到设计深度,同时对形成的基坑进行放坡施工,然后按照现有锚杆支护施工标准,对第二基坑的岩石边坡进行锚杆支护;Step 3. Excavate the rock layer at the bottom of the first foundation pit to form the second foundation pit. The excavation starting point is 0.5-2m away from the support of the first inclined column, and the excavation depth reaches the design depth. Grading construction, and then perform bolt support for the rock slope of the second foundation pit according to the existing bolt support construction standards;

步骤4、沿第二基坑的坑底边缘打设第二柱桩,在第二柱桩内侧支设挡石板并用第二斜撑支顶形成第二斜柱支撑。Step 4: Drive a second column pile along the edge of the bottom of the second foundation pit, support a stone block on the inner side of the second column pile, and use a second inclined support to support the top to form a second inclined column support.

在上述方法中,首先,对于具有软硬地质结构的深基坑施工,采用分层开挖基坑的方式来做支护,通过分层支护的方式来解决不同地质条件的问题,由此避免同一支护结构不能适用不同地质条件的缺陷,进一步,通过设计采用斜柱支护+锚杆支护+斜柱支护的方式,在地质最上层采用斜柱支护,为路基提供侧面支撑的同时,避免了路基周围松散的基土在重压和雨水作用下坍塌的问题,减小了基坑对道路路基强度的影响,并且还能防止溃散的基土滚落至第二基坑内而影响施工,为第二基坑形成支护结构提供了良好施工条件,在岩石层(坚硬层)采用锚杆支护,主要是为了防止岩石层崩塌和大块岩石滚落的问题,同时配合第二基坑坑底处的斜柱支护,其不仅解决了第二基坑支护的问题,还避免了采用具有高柱桩结构的排桩支护的方式,大幅减少了回填土量和施工成本,排除了安全隐患,同时,在整体上也解决了组合使用各类支护结构时,各支护结构之间不能形成有效配合的问题,实现了复杂地质条件下临近道路的深基坑支护施工,为支护施工领域提供了成功的实践经验。In the above method, first, for the construction of deep foundation pits with soft and hard geological structures, the method of excavating foundation pits in layers is used for support, and the problems of different geological conditions are solved by the method of layered support. To avoid the defect that the same support structure cannot be applied to different geological conditions, further, through the design of inclined column support + bolt support + inclined column support, inclined column support is used in the uppermost geological layer to provide lateral support for the roadbed At the same time, it avoids the collapse of the loose foundation soil around the subgrade under the action of heavy pressure and rain, reduces the influence of the foundation pit on the strength of the road subgrade, and also prevents the collapsed foundation soil from rolling down into the second foundation pit. Affect the construction and provide good construction conditions for the formation of the supporting structure of the second foundation pit. The rock layer (hard layer) is supported by bolts, mainly to prevent the collapse of the rock layer and the rolling of large rocks. The inclined column support at the bottom of the second foundation pit not only solves the problem of the second foundation pit support, but also avoids the use of row pile support with a high column pile structure, which greatly reduces the amount of backfill and construction cost, eliminates potential safety hazards, at the same time, it also solves the problem that the supporting structures cannot be effectively cooperated when using various supporting structures in combination, and realizes the deep foundation pit support adjacent to the road under complex geological conditions. It provides successful practical experience in the field of support construction.

进一步,考虑到岩石层边坡滚落的碎石会对第二斜柱支撑的柱桩形成冲击,特别是第二柱桩与基坑坑底连接处,其形成的应力集中程度较大,在挡石板与岩石层边坡之间填土夯实形成缓冲土层,以解决碎石冲击第二柱桩造成连接处应力集中的问题。Further, considering that the crushed stone rolled from the rock layer side slope will impact the column pile supported by the second inclined column, especially the connection between the second column pile and the bottom of the foundation pit, the degree of stress concentration formed is relatively large. Fill soil between the stone retaining plate and the rock layer slope to form a buffer soil layer to solve the problem of stress concentration at the connection caused by the impact of the crushed stone on the second column pile.

进一步,考虑到前期夯土回填和后期清场方便的问题,所述缓冲土层的回填高度为所第二述柱桩高度的2/5-3/5之间,在尽可能减少回填夯土量的同时,保证了缓冲土层能够起到的基本作用。Further, considering the problems of rammed earth backfill in the early stage and the convenience of site clearance in the later stage, the backfill height of the buffer soil layer is between 2/5-3/5 of the height of the second column and pile, and the amount of backfill rammed earth should be reduced as much as possible. At the same time, the basic role that the buffer soil layer can play is ensured.

在本发明中,由于属于深基坑支护施工,因此,在岩石层部分,会出现岩石渗水的问题,为了便于排除该部分水,在岩石层边坡和第二基坑的坑底连接处开凿有排水沟,所述排水沟沿该连接处形成环形,排水沟的顶部铺设带通孔或通槽的盖板,所述缓冲土层位于盖板之上。岩石层边坡的渗水通过缓冲土层渗透至排水沟内,然后通过排水沟引流至排水处,解决了岩石渗水对基坑的不利影响。In the present invention, since it belongs to the deep foundation pit support construction, there will be a problem of rock water seepage in the rock layer. A drainage ditch is excavated, the drainage ditch forms an annular shape along the connection, a cover plate with through holes or through grooves is laid on the top of the drainage ditch, and the buffer soil layer is located on the cover plate. The seepage water of the rock layer slope penetrates into the drainage ditch through the buffer soil layer, and then drains to the drainage place through the drainage ditch, which solves the adverse effect of rock seepage on the foundation pit.

进一步,为了更好地进行第二基坑的放坡施工,第二基坑的放坡施工的放坡坡度为1:0.25。Further, in order to better perform the grading construction of the second foundation pit, the grading slope of the grading construction of the second foundation pit is 1:0.25.

进一步,在步骤4中,锚杆施工优选为:在岩石立壁上钻孔至设计深度,孔内放入拉杆,灌入水泥砂浆与岩石结合成抗拉力强的锚杆,锚杆一端固定在岩壁上,另一端锚固在岩石层中,由此形锚杆支护。Further, in step 4, the bolt construction is preferably as follows: drilling a hole on the rock vertical wall to the design depth, putting a tie rod in the hole, pouring cement mortar into the rock to combine with the rock to form a strong tensile bolt, and one end of the bolt is fixed at the On the rock wall, the other end is anchored in the rock layer, and is supported by this shaped bolt.

综上所述,由于采用了上述技术方案,本发明的有益效果是:本发明通过采用斜柱支护+锚杆支护+斜柱支护的方式来对深基坑的支护,解决了复杂地质条件下临近道路的深基坑支护难、施工成本高、易出现安全隐患等问题,实现了复杂地质条件下临近道路的深基坑支护施工,为支护施工领域提供了成功的实践经验。To sum up, due to the adoption of the above technical solutions, the beneficial effects of the present invention are: the present invention supports the deep foundation pit by adopting the method of inclined column support + bolt support + inclined column support, which solves the problem of solving the problem of deep foundation pit support. Under complex geological conditions, the deep foundation pit support near the road is difficult to support, the construction cost is high, and it is prone to potential safety hazards. Experience.

附图说明Description of drawings

图1是本发明的一种复杂地质条件下临近道路的深基坑支护结构示意图。图中标记:1为道路路基,2为第一基坑,3为第二基坑,4为岩石层,5为第一斜柱支撑,501为第一柱桩,502为挡土板,503为第一斜撑,504为木质撑桩,6为回填层,7为斜撑平台,8为锚杆支护,9为第二斜柱支撑,901为第二柱桩,902为挡石板,903为第二斜撑,10为缓冲土层,11为排水沟,12为基土层。FIG. 1 is a schematic diagram of a deep foundation pit supporting structure near a road under complex geological conditions of the present invention. Labels in the figure: 1 is the road subgrade, 2 is the first foundation pit, 3 is the second foundation pit, 4 is the rock layer, 5 is the first inclined column support, 501 is the first column pile, 502 is the retaining plate, 503 is the first diagonal brace, 504 is the wooden support pile, 6 is the backfill layer, 7 is the diagonal bracing platform, 8 is the bolt support, 9 is the second diagonal column support, 901 is the second column pile, 902 is the stone retaining plate, 903 is the second diagonal brace, 10 is the buffer soil layer, 11 is the drainage ditch, and 12 is the base soil layer.

具体实施方式Detailed ways

下面结合附图,对本发明作详细的说明。The present invention will be described in detail below with reference to the accompanying drawings.

为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。In order to make the objectives, technical solutions and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention, but not to limit the present invention.

实施例Example

以申请人承接的成兰铁路成都至川主寺段CLZF-2标工程为例,该工程共包括茂县站、镇江关站、松潘站、川主寺站、黄胜关站共5个站房,其中,在修筑黄胜关及川主寺站房工程时,现场临时场地较狭窄,基坑开挖线距现场临时道路约50cm,基坑深度超过5m,地质条件复杂,地层上部为松散、湿度很高的土层,下部为坚硬紧凑的岩石层,传统支护结构无法适用,本发明为了解决该问题,如图1所示,本发明采用的深基坑支护施工工艺包括以下步骤:Taking the CLZF-2 bid project of the Chengdu-Chuanzhusi section of the Chengdu-Lanzhou Railway undertaken by the applicant as an example, the project includes a total of 5 stations including Maoxian Station, Zhenjiangguan Station, Songpan Station, Chuanzhusi Station and Huangshengguan Station , Among them, during the construction of Huangshengguan and Chuanzhusi station buildings, the temporary site on site was relatively narrow, the excavation line of the foundation pit was about 50cm away from the temporary road on site, the depth of the foundation pit was more than 5m, the geological conditions were complex, and the upper stratum was loose and humid. In a very high soil layer, the lower part is a hard and compact rock layer, and the traditional support structure cannot be applied. In order to solve this problem, the present invention, as shown in Figure 1, adopts the deep foundation pit support construction technology including the following steps:

步骤1、在道路路基1旁进行基坑开挖,直到基坑底部到达岩石层5为止,即先挖2-3m直至挖穿相对柔软的基土层,同时对形成的基坑进行放坡施工,形成第一基坑2,放坡施工根据中的边坡坡度和坡度系数按照原设计要求选取,例如在本实施例中可采用1:0.5;Step 1. Excavate the foundation pit next to the road subgrade 1 until the bottom of the foundation pit reaches the rock layer 5, that is, dig 2-3m first until the relatively soft foundation soil layer is dug through, and at the same time carry out grading construction for the formed foundation pit , the first foundation pit 2 is formed, and the slope and slope coefficient in the grading construction are selected according to the original design requirements, for example, 1:0.5 can be used in this embodiment;

步骤2、沿第一基坑的边缘打设第一柱桩501,在第一柱桩501内侧支设挡土板502并用第一斜撑503支顶,挡土板内侧填土夯实形成第一斜柱支撑5,夯土层形成回填层6;Step 2. Drive a first column pile 501 along the edge of the first foundation pit, support a retaining plate 502 inside the first column pile 501 and support the top with a first diagonal brace 503, and fill the inner side of the retaining plate to form a first The inclined column supports 5, and the rammed earth layer forms the backfill layer 6;

步骤3、在第一基坑2的坑底处开挖岩石层5形成第二基坑3,开挖起点距离第一斜撑0.5-2m(在本实施例中,开挖起点距离1.5m最为合适),形成斜撑平台7,第二基坑3开挖深度达到设计深度3m,在开挖第二基坑3时,需对第二基坑3进行放坡施工,放坡施工的放坡坡度为1:0.25;Step 3. Excavate the rock layer 5 at the bottom of the first foundation pit 2 to form the second foundation pit 3, and the excavation starting point is 0.5-2m away from the first diagonal brace (in this embodiment, the excavation starting point is 1.5m away from the most suitable) to form a diagonal support platform 7, and the excavation depth of the second foundation pit 3 reaches the design depth of 3m. When excavating the second foundation pit 3, it is necessary to carry out grading construction on the second foundation pit 3, and the grading construction of the grading construction The slope is 1:0.25;

步骤4、按照现有锚杆支护施工标准,对第二基坑的岩石立壁进行锚杆支护8,即在岩石立壁上钻孔至设计深度,孔内放入拉杆,灌入水泥砂浆与岩石结合成抗拉力强的钢筋锚杆,钢筋锚杆一端固定在岩壁上,另一端锚固在岩石层中,通过锚杆支护来保护岩石边坡的稳定性(该钢筋锚杆支护为优选例,其也可采用其他锚杆支护结构,例如钢丝绳砂浆锚杆支护或管缝式锚杆支护);Step 4. According to the existing bolt support construction standards, perform bolt support 8 on the rock vertical wall of the second foundation pit, that is, drill holes on the rock vertical wall to the design depth, put a tie rod in the hole, pour cement mortar and The rock is combined into a strong tensile steel anchor, one end of the steel anchor is fixed on the rock wall, and the other end is anchored in the rock layer, and the stability of the rock slope is protected by the anchor support (the steel anchor supports As a preferred example, it can also use other bolt support structures, such as wire rope mortar bolt support or pipe-slot bolt support);

步骤5、沿第二基坑3的坑底边缘打设第二柱桩901,在第二柱桩901内侧支设挡石板902并用第二斜撑903支顶形成第二斜柱支撑9。Step 5: Drive a second column pile 901 along the bottom edge of the second foundation pit 3 , support a stone blocking plate 902 inside the second column pile 901 and use a second diagonal brace 903 to support the top to form a second diagonal column support 9 .

在上述施工工艺中,第一基坑2采用的第一斜柱支撑5为现有常见的斜柱支撑结构,其施工要求和施工操作按照现有标准执行即可,即将挡土板902定在第一柱桩501内侧,第一柱桩501外侧用第一斜撑503支顶,第一斜撑503底端在木质撑桩504上,挡土板502内侧回填土,在此不做详细描述。相应地,在第二基坑3采用的第二斜柱支撑也为现有常见的斜柱支撑结构,其按照现有施工标准执行即可。为了更好的使第二斜柱支撑发挥支撑挡石作用,挡土板502更换为材料强度更大的混凝土制或钢制挡石板902,其无需在挡石板902内侧回填形成回填层6。In the above construction process, the first inclined column support 5 used in the first foundation pit 2 is an existing common inclined column support structure, and its construction requirements and construction operations can be implemented according to the existing standards, that is, the retaining plate 902 is set at the The inner side of the first pillar 501 and the outer side of the first pillar 501 are supported by a first diagonal brace 503, the bottom end of the first diagonal brace 503 is on the wooden brace 504, and the inner side of the retaining plate 502 is backfilled with soil, which will not be described in detail here. . Correspondingly, the second inclined column support used in the second foundation pit 3 is also an existing common inclined column support structure, which can be implemented according to the existing construction standards. In order to better enable the second inclined column support to play the role of supporting the stone, the soil retaining plate 502 is replaced with a concrete or steel stone retaining plate 902 with stronger material strength, which does not need to be backfilled inside the stone retaining plate 902 to form the backfill layer 6 .

进一步地,考虑到岩石层4边坡滚落的碎石会对第二斜柱支撑9的第二柱桩901形成冲击,特别是第二柱桩901与基坑坑底连接处,其形成的应力集中程度较大,如图1所示,在挡石板902与岩石层4边坡之间填土夯实形成缓冲土层10,以解决碎石冲击柱桩造成连接处应力集中的问题。Further, considering that the crushed stones rolled from the side slope of the rock layer 4 will impact the second column pile 901 of the second inclined column support 9, especially the connection between the second column pile 901 and the bottom of the foundation pit, the formed The degree of stress concentration is relatively large. As shown in FIG. 1 , the buffer soil layer 10 is formed by filling and compacting between the stone retaining plate 902 and the slope of the rock layer 4 to solve the problem of stress concentration at the connection caused by the impact of the crushed stone on the column pile.

进一步地,考虑到前期夯土回填和后期清场方便的问题,所述缓冲土层10的回填高度为所述第二柱桩901高度的2/5-3/5之间,其可以选择2/5、5/10或者3/5,具体值根据实际情况选择,这样的设置方式可以尽可能减少回填夯土量的同时,保证了缓冲土层10能够起到的基本作用。Further, considering the convenience of backfilling with rammed earth in the early stage and site clearance in the later stage, the backfill height of the buffer soil layer 10 is between 2/5 and 3/5 of the height of the second pile 5, 5/10 or 3/5, the specific value is selected according to the actual situation. This setting method can reduce the amount of backfill rammed earth as much as possible, and at the same time ensure the basic role that the buffer soil layer 10 can play.

在本发明中,由于属于深基坑支护施工,因此,在岩石层4部分,会出现岩石渗水的问题,为了便于排除该部分水,在岩石层4边坡和第二基坑3的坑底连接处开凿有排水沟11,所述排水沟11沿该连接处形成环形,排水沟11的顶部铺设带通孔或通槽的盖板(图中未画出),所述缓冲土层10位于盖板之上。岩石层4边坡的渗水通过缓冲土层10渗透至排水沟11内,然后通过排水沟11引流至排水处,解决了岩石渗水对基坑的不利影响。In the present invention, since it belongs to the deep foundation pit support construction, there will be a problem of rock water seepage in the rock layer 4 part. A drainage ditch 11 is excavated at the bottom connection, and the drainage ditch 11 forms a ring shape along the connection. The top of the drainage ditch 11 is laid with a cover plate with a through hole or a through groove (not shown in the figure), and the buffer soil layer 10 on the cover. The seepage water on the slope of the rock layer 4 penetrates into the drainage ditch 11 through the buffer soil layer 10, and then drains to the drainage place through the drainage ditch 11, which solves the adverse effect of the rock seepage on the foundation pit.

在上述施工工艺中,其适用于在挖掘深基坑时存在软硬两种地层结构的深基坑支护施工,即是说,上述实施例中的岩石层换作较硬的土层时,其也是适用的,通过采用斜柱支护+锚杆支护+斜柱支护的方式来实现对深基坑的支护,解决了复杂地质条件下临近道路的深基坑支护难、施工成本高、易出现安全隐患等问题,实现了复杂地质条件下临近道路的深基坑支护施工,为支护施工领域提供了成功的实践经验。In the above-mentioned construction technology, it is suitable for the deep foundation pit support construction in which there are two kinds of stratum structure, soft and hard when excavating the deep foundation pit, that is to say, when the rock layer in the above-mentioned embodiment is replaced with a harder soil layer, It is also applicable. The support of deep foundation pit is realized by adopting inclined column support + bolt support + inclined column support, which solves the difficulty of supporting and constructing deep foundation pit adjacent to roads under complex geological conditions. Due to the high cost and potential safety hazards, the deep foundation pit support construction adjacent to the road under complex geological conditions has been realized, providing a successful practical experience for the field of support construction.

以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present invention shall be included in the protection of the present invention. within the range.

Claims (6)

1.一种复杂地质条件下临近道路的深基坑支护施工工艺,其特征在于,包括以下步骤:1. a deep foundation pit support construction technique near road under complex geological conditions, is characterized in that, comprises the following steps: 步骤1、在道路旁进行基坑开挖,直到基坑底部到达岩石层为止,同时对形成的基坑进行放坡施工,形成第一基坑;Step 1. Carry out foundation pit excavation beside the road until the bottom of the foundation pit reaches the rock layer, and at the same time carry out grading construction on the formed foundation pit to form the first foundation pit; 步骤2、沿第一基坑的坑底边缘打设第一柱桩,在第一柱桩内侧支设挡土板并用第一斜撑支顶,挡土板内侧填土夯实形成第一斜柱支撑;Step 2. Drive a first column pile along the edge of the pit bottom of the first foundation pit, support a retaining plate inside the first column pile and support the top with a first diagonal brace, and fill and compact the inner side of the retaining plate to form a first inclined column support; 步骤3、在第一基坑的坑底处开挖岩石层形成第二基坑,开挖起点距离第一斜柱支撑0.5-2m,开挖深度直至达到设计深度,同时对形成的基坑进行放坡施工,然后按照现有锚杆支护施工标准,对第二基坑的岩石边坡进行锚杆支护;Step 3. Excavate the rock layer at the bottom of the first foundation pit to form the second foundation pit. The excavation starting point is 0.5-2m away from the support of the first inclined column, and the excavation depth reaches the design depth. Grading construction, and then perform bolt support for the rock slope of the second foundation pit according to the existing bolt support construction standards; 步骤4、沿第二基坑的坑底边缘打设第二柱桩,在第二柱桩内侧支设挡石板并用第二斜撑支顶形成第二斜柱支撑。Step 4: Drive a second column pile along the edge of the bottom of the second foundation pit, support a stone block on the inner side of the second column pile, and use a second inclined support to support the top to form a second inclined column support. 2.如权利要求1所述的复杂地质条件下临近道路的深基坑支护施工工艺,其特征在于,在挡石板与岩石层边坡之间填土夯实形成缓冲土层。2 . The deep foundation pit support construction process adjacent to the road under complex geological conditions as claimed in claim 1 , wherein the buffer soil layer is formed by filling and compacting between the stone retaining plate and the rock layer side slope. 3 . 3.如权利要求2所述的复杂地质条件下临近道路的深基坑支护施工工艺,其特征在于,所述缓冲土层的回填高度为所第二述柱桩高度的2/5-3/5。3. The deep foundation pit support construction technique near the road under complex geological conditions as claimed in claim 2, wherein the backfill height of the buffer soil layer is 2/5-3 of the height of the second column pile /5. 4.如权利要求1或3所述的复杂地质条件下临近道路的深基坑支护施工工艺,其特征在于,在岩石层边坡和第二基坑的坑底连接处开凿有排水沟,排水沟的顶部铺设带通孔或通槽的盖板,所述缓冲土层位于盖板之上。4. the deep foundation pit support construction technique near road under complex geological conditions as claimed in claim 1 or 3, is characterized in that, a drainage ditch is dug at the junction of the rock layer side slope and the pit bottom of the second foundation pit, A cover plate with through holes or through grooves is laid on the top of the drainage ditch, and the buffer soil layer is located on the cover plate. 5.如权利要求1所述的复杂地质条件下临近道路的深基坑支护施工工艺,其特征在于,第二基坑的放坡施工的放坡坡度为1:0.25。5 . The deep foundation pit support construction technique adjacent to the road under complex geological conditions as claimed in claim 1 , wherein the grading gradient of the grading construction of the second foundation pit is 1:0.25. 6 . 6.如权利要求1所述的复杂地质条件下临近道路的深基坑支护施工工艺,其特征在于,在岩石立壁上钻孔至设计深度,孔内放入拉杆,灌入水泥砂浆与岩石结合成抗拉力强的锚杆,锚杆一端固定在岩壁上,另一端锚固在岩石层中,由此形锚杆支护。6. the construction technique of deep foundation pit support near road under complex geological conditions as claimed in claim 1, is characterized in that, drilling to design depth on rock vertical wall, putting tie rod in hole, pouring cement mortar and rock Combined into a strong tensile strength bolt, one end of the bolt is fixed on the rock wall, and the other end is anchored in the rock layer, so as to be supported by the shaped bolt.
CN201911004456.4A 2019-10-22 2019-10-22 A deep foundation pit support construction technology adjacent to the road under complex geological conditions Pending CN110685286A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911004456.4A CN110685286A (en) 2019-10-22 2019-10-22 A deep foundation pit support construction technology adjacent to the road under complex geological conditions

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911004456.4A CN110685286A (en) 2019-10-22 2019-10-22 A deep foundation pit support construction technology adjacent to the road under complex geological conditions

Publications (1)

Publication Number Publication Date
CN110685286A true CN110685286A (en) 2020-01-14

Family

ID=69113662

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911004456.4A Pending CN110685286A (en) 2019-10-22 2019-10-22 A deep foundation pit support construction technology adjacent to the road under complex geological conditions

Country Status (1)

Country Link
CN (1) CN110685286A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111101524A (en) * 2020-01-17 2020-05-05 龚大娇 Temporary supporting structure for foundation pit construction and temporary supporting construction method
CN111305237A (en) * 2020-03-05 2020-06-19 中煤科工集团重庆设计研究院有限公司 Slope supporting structure and construction method
CN111501782A (en) * 2020-06-02 2020-08-07 湖南科技大学 Foundation pit supporting and construction road integrated structure and construction method
CN112211199A (en) * 2020-04-06 2021-01-12 广东华星建设集团有限公司 Large deep foundation pit supporting construction structure and method thereof
CN112281870A (en) * 2020-11-18 2021-01-29 贵州建工集团第一建筑工程有限责任公司 Foundation pit supporting structure
CN112663622A (en) * 2020-12-16 2021-04-16 深圳市宏源建设工程有限公司 Anti-seepage construction method for anchor cable in deep foundation pit supporting engineering
CN112779917A (en) * 2021-01-25 2021-05-11 福建江夏学院 Good foundation ditch side slope supporting construction of stability
CN112813984A (en) * 2020-12-31 2021-05-18 攀钢集团工程技术有限公司 Deep foundation pit construction method under complex geological condition
CN113668556A (en) * 2021-08-05 2021-11-19 深圳市盛业建筑科技(集团)有限公司 Double-row pile supporting method for adding connecting beams in soil layer
CN116104099A (en) * 2022-09-14 2023-05-12 上海南汇建工建设(集团)有限公司 Reinforcing treatment method for water collecting well part of deep foundation pit

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202323960U (en) * 2011-11-23 2012-07-11 天津住宅集团建设工程总承包有限公司 Shallow foundation pit forming construction structure capable of ensuring slope stability
CN203741848U (en) * 2013-12-25 2014-07-30 深圳市工勘岩土工程有限公司 Steel tube plate type retaining structure
KR20160097486A (en) * 2015-02-09 2016-08-18 한국도로공사 Road drainage facility and construction methods accordingly
CN107419737A (en) * 2017-08-25 2017-12-01 中铁建设集团有限公司 A kind of steel tube for soil-nail slope retaining structure and method
CN108560572A (en) * 2018-04-12 2018-09-21 中铁上海工程局集团有限公司 A kind of construction method of extra-high support system
CN108842784A (en) * 2018-07-04 2018-11-20 上海建工七建集团有限公司 A kind of shallow foundation hole slope protecting device and means of defence excavated for slope
CN208136928U (en) * 2018-04-24 2018-11-23 河南建筑材料研究设计院有限责任公司 A kind of non-metal mine side slope soil-baffling structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202323960U (en) * 2011-11-23 2012-07-11 天津住宅集团建设工程总承包有限公司 Shallow foundation pit forming construction structure capable of ensuring slope stability
CN203741848U (en) * 2013-12-25 2014-07-30 深圳市工勘岩土工程有限公司 Steel tube plate type retaining structure
KR20160097486A (en) * 2015-02-09 2016-08-18 한국도로공사 Road drainage facility and construction methods accordingly
CN107419737A (en) * 2017-08-25 2017-12-01 中铁建设集团有限公司 A kind of steel tube for soil-nail slope retaining structure and method
CN108560572A (en) * 2018-04-12 2018-09-21 中铁上海工程局集团有限公司 A kind of construction method of extra-high support system
CN208136928U (en) * 2018-04-24 2018-11-23 河南建筑材料研究设计院有限责任公司 A kind of non-metal mine side slope soil-baffling structure
CN108842784A (en) * 2018-07-04 2018-11-20 上海建工七建集团有限公司 A kind of shallow foundation hole slope protecting device and means of defence excavated for slope

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张永平等: "《建筑与装饰施工工艺》", 31 August 2018, 北京理工大学出版社, pages: 26 - 27 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111101524A (en) * 2020-01-17 2020-05-05 龚大娇 Temporary supporting structure for foundation pit construction and temporary supporting construction method
CN111305237A (en) * 2020-03-05 2020-06-19 中煤科工集团重庆设计研究院有限公司 Slope supporting structure and construction method
CN112211199A (en) * 2020-04-06 2021-01-12 广东华星建设集团有限公司 Large deep foundation pit supporting construction structure and method thereof
CN111501782A (en) * 2020-06-02 2020-08-07 湖南科技大学 Foundation pit supporting and construction road integrated structure and construction method
CN112281870A (en) * 2020-11-18 2021-01-29 贵州建工集团第一建筑工程有限责任公司 Foundation pit supporting structure
CN112663622A (en) * 2020-12-16 2021-04-16 深圳市宏源建设工程有限公司 Anti-seepage construction method for anchor cable in deep foundation pit supporting engineering
CN112663622B (en) * 2020-12-16 2022-02-08 深圳市宏源建设工程有限公司 Anti-seepage construction method for anchor cable in deep foundation pit supporting engineering
CN112813984A (en) * 2020-12-31 2021-05-18 攀钢集团工程技术有限公司 Deep foundation pit construction method under complex geological condition
CN112813984B (en) * 2020-12-31 2022-07-29 攀钢集团工程技术有限公司 Deep foundation pit construction method under complex geological condition
CN112779917A (en) * 2021-01-25 2021-05-11 福建江夏学院 Good foundation ditch side slope supporting construction of stability
CN113668556A (en) * 2021-08-05 2021-11-19 深圳市盛业建筑科技(集团)有限公司 Double-row pile supporting method for adding connecting beams in soil layer
CN116104099A (en) * 2022-09-14 2023-05-12 上海南汇建工建设(集团)有限公司 Reinforcing treatment method for water collecting well part of deep foundation pit

Similar Documents

Publication Publication Date Title
CN110685286A (en) A deep foundation pit support construction technology adjacent to the road under complex geological conditions
CN107503257B (en) One kind being close to mountain high-filled subgrade stabilization and Deformation control structure and construction method
CN108442382B (en) In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method
US20140026518A1 (en) Construction method for root-type foundation anchorage and bored, root-type cast in-situ pile with anchor bolts
CN104389628B (en) Landslide location tunnel reinforcement device and reinforced construction method
CN103696784B (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN103898916B (en) Mini stake Composite Braced Retaining Structure and construction method
CN108412503B (en) Bias shallow-buried tunnel portal construction protection structure and construction method thereof
CN109750571B (en) Road collapse emergency and permanent retaining integrated structure and construction method
CN111594232A (en) Large-scale filling type karst cave geological tunnel foundation reinforcing structure and construction method thereof
CN110055973B (en) Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method
CN110847207A (en) Structure and construction method for newly-built bridge with subway tunnel passing through existing bridge piles
CN110017149A (en) A kind of underground structure and construction method of underground excavation and construction of arch cover
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
WO2023213117A1 (en) Widening structure and construction method for existing subgrade embankment wall section near river
JP7540678B1 (en) System and method for backfilling narrow excess trenches in a mine with liquefied hardened soil
CN111322087A (en) Construction method for soft soil highway tunnel entrance semi-open semi-hidden tunnel in mountainous area
CN101838957A (en) Integral type T-shaped outer cantilever roads and construction method thereof
CN107653886A (en) A kind of building supporting construction and its implementation applied to foundation ditch landform
CN109811773B (en) Bias tunnel portal excavation protection structure and construction method thereof
CN110130361A (en) A foundation pit support structure and construction method for protecting subway tunnel structures
CN110055982A (en) A kind of novel anchor holding frame lattice miniature steel pipe pile supporting system
CN109024621A (en) The compound retaining wall supporting construction of embankment high slope tubular pole and its construction method
CN102425179B (en) Reinforced soil infiltration ditch structure supported by miniature steel pipe cast-in-place pile
CN105951874A (en) Retaining wall reinforcing structure and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200114