CN106638595A - 混凝土预制桩快速沉桩方法 - Google Patents
混凝土预制桩快速沉桩方法 Download PDFInfo
- Publication number
- CN106638595A CN106638595A CN201510711735.XA CN201510711735A CN106638595A CN 106638595 A CN106638595 A CN 106638595A CN 201510711735 A CN201510711735 A CN 201510711735A CN 106638595 A CN106638595 A CN 106638595A
- Authority
- CN
- China
- Prior art keywords
- pile
- sinking
- end plate
- prefabricated tubular
- prefabricated pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/02—Placing by driving
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D13/00—Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/24—Prefabricated piles
- E02D5/30—Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Piles And Underground Anchors (AREA)
Abstract
本发明涉及桩基础施工领域,具体是一种混凝土预制桩快速沉桩方法;其特征是:包括下述步骤,步骤1、用钢筋加工一个环形抱箍,该环形抱箍的内径与预制管桩的桩外径相等;步骤2、将环形抱箍满焊在预制管桩的桩头端板顶部外围;步骤3、确定并复核桩位,进行沉桩施工作业;步骤4、预制管桩首节沉桩完成后,逐节连接并沉桩施工后续各节预制管桩,直至桩头端板达到设计位置,完成沉桩施工。本快速沉桩方法所用材料易于就地取材,成本低廉;加工技术难度低,具有很强的可操作性;且沉桩效果好,能够很好的提高沉桩效率与质量。
Description
技术领域
本发明涉及桩基础施工领域,具体是一种混凝土预制桩快速沉桩方法。
背景技术
桩基础在高层建筑、桥梁及港口工程中应用极为广泛,其具有承载力高、稳定性好、沉降量小而均匀、便于机械化施工、适应性强等突出特点。
预制管桩可以在施工现场或工厂预制,然后运至桩位处,再经锤击方式打入地层设计位置,即沉桩施工。锤击沉桩法优点是设备简单、沉桩速度快、成本低。然而,当土质比较硬、需要贯穿的砂层较厚时,沉桩非常困难,功效降低。目前常采用在桩头位置焊接一个钢板加工的桩尖来解决上述问题,但如沈鼎在《工程技术》(2013年第13期)发表的“浅谈桩基础施工的常见问题及对策”一文指出,当桩沉入深度达不到设计要求时,可采用大吨位桩架并采用重锤低击法沉桩,问题在于功效仍然偏低,且易造成桩头破损。
发明内容
本发明的目的在于,提供一种简单实用、适用于坚硬土层或贯穿砂层等工况的高质量、高功效的沉桩方法。
为了达到上述目的,本发明是这样实现的:
一种混凝土预制桩快速沉桩方法,包括下述步骤,
步骤1、用钢筋加工一个环形抱箍,该环形抱箍的内径与预制管桩的桩外径相等;
步骤2、将环形抱箍满焊在预制管桩的桩头端板顶部外围;
步骤3、确定并复核桩位,进行沉桩施工作业;
步骤4、预制管桩首节沉桩完成后,逐节连接并沉桩施工后续各节预制管桩,直桩头端板达到设计位置,完成沉桩施工。
所述的混凝土预制桩快速沉桩方法,步骤1所用钢筋的直径不小于18mm。
所述的混凝土预制桩快速沉桩方法,预制管桩的桩头端板前加设有桩尖。
本快速沉桩方法所用材料易于就地取材,成本低廉;加工技术难度低,在桩端板外围满焊抱箍后,原先桩体最前端外侧与土体之间的面接触变抱箍与土体之间的线接触,如此大大降低了桩体初段与土体之间的摩擦力,使得桩体在穿入坚硬土层、贯穿砂石土层时所受阻力更小,因而为具有很强的可操作性;且沉桩效果好,能够很好的提高沉桩效率与质量。
附图说明
图1为本沉桩方法中抱箍的位置示意图。
具体实施方式
以下通过具体实施例进一步说明本发明。
如图1所示,一种混凝土预制桩快速沉桩方法,包括下述步骤,
步骤1、用钢筋加工一个环形抱箍1,该环形抱箍1的内径与预制管桩2的桩外径相等;
步骤2、将环形抱箍1满焊在预制管桩2的桩头端板3顶部外围;
步骤3、确定并复核桩位,进行沉桩施工作业;
步骤4、预制管桩2首节沉桩完成后,逐节连接并沉桩施工后续各节预制管桩,直至第一节桩头端板达到设计位置,完成沉桩施工。
所述的混凝土预制桩快速沉桩方法,步骤1所用钢筋的直径不小于18mm。
所述的混凝土预制桩快速沉桩方法,预制管桩2的桩头端板3前加设有桩尖。
本快速沉桩方法所用材料易于就地取材,成本低廉;加工技术难度低,在桩端板外围满焊抱箍后,原先桩体最前端外侧与土体之间的面接触变抱箍与土体之间的线接触,如此大大降低了桩体初段与土体之间的摩擦力,使得桩体在穿入坚硬土层、贯穿砂石土层时所受阻力更小,因而为具有很强的可操作性;且沉桩效果好,能够很好的提高沉桩效率与质量。
Claims (3)
1. 一种混凝土预制桩快速沉桩方法,其特征是:包括下述步骤,
步骤1、用钢筋加工一个环形抱箍,该环形抱箍的内径与预制管桩的桩外径相等;
步骤2、将环形抱箍满焊在预制管桩的桩头端板顶部外围;
步骤3、确定并复核桩位,进行沉桩施工作业;
步骤4、预制管桩首节沉桩完成后,逐节连接并沉桩施工后续各节预制管桩,直至桩头端板达到设计位置,完成沉桩施工。
2.根据权利要求1所述的混凝土预制桩快速沉桩方法,其特征是:步骤1所用钢筋的直径不小于18mm。
3.根据权利要求1所述的混凝土预制桩快速沉桩方法,其特征是:预制管桩的桩头端板前加设有桩尖。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510711735.XA CN106638595A (zh) | 2015-10-28 | 2015-10-28 | 混凝土预制桩快速沉桩方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510711735.XA CN106638595A (zh) | 2015-10-28 | 2015-10-28 | 混凝土预制桩快速沉桩方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106638595A true CN106638595A (zh) | 2017-05-10 |
Family
ID=58815964
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510711735.XA Pending CN106638595A (zh) | 2015-10-28 | 2015-10-28 | 混凝土预制桩快速沉桩方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106638595A (zh) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000154540A (ja) * | 1998-09-18 | 2000-06-06 | Sumitomo Metal Ind Ltd | 埋込み杭、その施工方法、施工装置および埋込み杭用既成杭 |
CN202577289U (zh) * | 2012-04-20 | 2012-12-05 | 中交第三航务工程局有限公司 | 易于沉桩的预应力混凝土管桩 |
CN103397632A (zh) * | 2013-08-06 | 2013-11-20 | 中国电力工程顾问集团华东电力设计院 | Phc管桩及其沉桩方法 |
CN104452754A (zh) * | 2014-11-28 | 2015-03-25 | 中铁二十三局集团有限公司 | 预应力混凝土管桩施工方法 |
-
2015
- 2015-10-28 CN CN201510711735.XA patent/CN106638595A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000154540A (ja) * | 1998-09-18 | 2000-06-06 | Sumitomo Metal Ind Ltd | 埋込み杭、その施工方法、施工装置および埋込み杭用既成杭 |
CN202577289U (zh) * | 2012-04-20 | 2012-12-05 | 中交第三航务工程局有限公司 | 易于沉桩的预应力混凝土管桩 |
CN103397632A (zh) * | 2013-08-06 | 2013-11-20 | 中国电力工程顾问集团华东电力设计院 | Phc管桩及其沉桩方法 |
CN104452754A (zh) * | 2014-11-28 | 2015-03-25 | 中铁二十三局集团有限公司 | 预应力混凝土管桩施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102828509B (zh) | 预应力管桩桩底桩侧联合注浆方法 | |
CN102605767A (zh) | 一种预留注浆管预制桩及其成桩工艺 | |
CN111576403A (zh) | 用于实现灌浆连接的套筒端板以及phc管桩 | |
CN110438988A (zh) | 一种预制护壁及桩孔开挖方法 | |
CN201883701U (zh) | 一种外套钢管混凝土加固混凝土柱结构 | |
CN105887808A (zh) | 一种混凝土管桩及其施工方法 | |
CN203284773U (zh) | 管桩连接结构和管桩基础 | |
CN102251521A (zh) | 加固预应力管桩及其施工方法 | |
CN221000974U (zh) | 一种预应力phc管桩可拆卸桩尖连接结构 | |
CN104594343B (zh) | 一种装配式桩及其施工方法 | |
CN110280963A (zh) | 一种环缝不锈钢钢管结构 | |
CN206158226U (zh) | 钢管注浆快速加固柱结构 | |
CN210482760U (zh) | 用于装配式结构的钢筋套筒灌浆连接搭接接头 | |
CN106638595A (zh) | 混凝土预制桩快速沉桩方法 | |
CN208857811U (zh) | 一种钢管桩超大吨位预应力封桩结构 | |
CN103572760A (zh) | 钻孔压灌桩全桩长振捣施工方法及装置 | |
CN107401163A (zh) | 一种用于消减管桩负摩阻力的施工方法 | |
CN104343117A (zh) | 一种混凝土管桩接桩器 | |
CN106223332A (zh) | 复合式混凝土桩 | |
CN205205826U (zh) | 一种管桩底部注浆装置 | |
CN205662920U (zh) | 一种带锚索孔的地下装配式预制桩 | |
CN203741835U (zh) | 一种预制管桩的桩尖结构 | |
CN105421460B (zh) | 一种管桩底部注浆装置及方法 | |
CN204212153U (zh) | 组合式钢护筒 | |
CN108179743A (zh) | 一种同步注浆预应力管桩及施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170510 |