CN104099874A - Steel strand inhaul cable tension construction method by taking slip-resistant stud as locking device - Google Patents

Steel strand inhaul cable tension construction method by taking slip-resistant stud as locking device Download PDF

Info

Publication number
CN104099874A
CN104099874A CN201410363165.5A CN201410363165A CN104099874A CN 104099874 A CN104099874 A CN 104099874A CN 201410363165 A CN201410363165 A CN 201410363165A CN 104099874 A CN104099874 A CN 104099874A
Authority
CN
China
Prior art keywords
steel strand
key
skid
cable
force
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410363165.5A
Other languages
Chinese (zh)
Other versions
CN104099874B (en
Inventor
胡方健
黄锦源
陆元春
张晓松
何飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Design Research Institute Group Co Ltd
Original Assignee
Shanghai Urban Construction Design Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Design Research Institute Co ltd filed Critical Shanghai Urban Construction Design Research Institute Co ltd
Priority to CN201410363165.5A priority Critical patent/CN104099874B/en
Publication of CN104099874A publication Critical patent/CN104099874A/en
Application granted granted Critical
Publication of CN104099874B publication Critical patent/CN104099874B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种以抗滑键作为锁定装置的钢绞线拉索的张拉施工方法,在每根钢绞线在有抗滑键侧张拉时,无抗滑键侧也须同时张拉,张拉过程中始终保持无抗滑键侧的张拉力大于有抗滑键侧张拉力,两侧的差值为实测摩阻力的1~2倍之间;当每根钢绞线在有抗滑键侧张拉到监控目标张拉索力fc时,先锚固,然后将无抗滑键侧张拉到超张拉力fk再降到目标张拉索力fc,然后锚固,完成钢绞线拉索的张拉施工。本发明优化了安装方法,使拉索在塔柱两外侧的索力相同、抗滑键与塔柱密贴且具备足够的压力储备,使得每根钢绞线在塔柱两侧的内力相同,提高了整束拉索的安全度,抗滑键锁紧力更加可靠,现场施工方便不容易出错,超张拉力不会对结构整体造成过大影响。

The invention discloses a tensioning construction method of a steel strand cable using an anti-skid key as a locking device. When each steel strand is stretched on the side with the anti-skid key, the side without the anti-skid key must also be tensioned at the same time. During the tensioning process, the tension force on the side without anti-skid keys is always greater than the tension force on the side with anti-skid keys, and the difference between the two sides is between 1 and 2 times the measured frictional resistance; When the anti-skid key is side-tensioned to the monitoring target tension force f c , anchor first, then side-tension without anti-skid key to the super tension force f k and then drop to the target tension force f c , then anchor and complete Tension construction of steel strand cables. The invention optimizes the installation method, so that the cable forces on both sides of the tower column are the same, the anti-skid key is closely attached to the tower column and has sufficient pressure reserve, so that the internal force of each steel strand on both sides of the tower column is the same, The safety of the whole bundle of cables is improved, the locking force of the anti-slip key is more reliable, the on-site construction is convenient and it is not easy to make mistakes, and the overtension tension will not cause excessive impact on the overall structure.

Description

Using the stretch-draw construction method of antiskid key as the guy of twisted steel cable of locking device
Technical field
The present invention relates to cable-stayed bridge cable technical field of construction, relate in particular to a kind of stretch-draw construction method of antiskid key as the guy of twisted steel cable of locking device of usining.
Background technology
Wear tower steel strand stay cable and be mainly used in low-pylon cable-stayed bridge.The Objective Concept Frenchman Jacgues Mathivat of the type bridge proposes, and Japan has built up First low-pylon cable-stayed bridge in the world, and Japan is the country that the type bridge construction is maximum up to now.Domestic since 2000, in succession built up Construction of Wuhu Changjiang River Bridge, Zhangzhou, Fujian war preparedness bridge etc., accumulated certain design experiences.
Saddle (as shown in Figure 1) is the key constructs of low-pylon cable-stayed bridge king-post, and its basic function is to allow skew drag-line and pass through continuously king-post with continual form, and by anchoring structure, drag-line and king-post is locked, and mainly contains two cannula configuration and minute fiber tube structure.
Wherein, be published in < < bridge construction > > 1 interim article < < Stay Cables Design of Zhangzhou War Preparation Bridge > > in 2002 and discussed relevant two cannula configuration (as shown in Figure 2), in application, found deficiency: 1) because distortion after machining deviation and operation makes saddle internal pipeline, be difficult to change; 2) between two sleeve pipes contact surface narrow and small to make to manage lower stress concentration phenomenon serious; 3) thus between two sleeve pipe, the narrow and small mud jacking leakiness that makes in space causes mortar body cracking destruction.For overcoming above deficiency, proposed minute fiber tube saddle scheme (as shown in Figure 3) and be put to practical application, obtained good effect
But above two kinds are configured in the shortcoming that the design initial stage all exists anti-slide performance deficiency, conventionally need be at king-post outer setting anti-slip anchoring tube (as shown in Figure 4) in large bridge is used, anchorage drum is installed conventionally before drag-line bears out-of-balance force effect, to overcome uneven Suo Li.Specifically can bibliography " bridge construction " 4 interim articles " Stay Cables Design of Zhangzhou War Preparation Bridge " in 2012, " bridge construction " 1 interim article " Stay Cables Design of Zhangzhou War Preparation Bridge " in 2002, the article of the 4th phase in 2013 " railway construction journal " " low-pylon cable-stayed bridge spatial analysis research is protected in Tianjin " and " world's bridge " 5 interim articles in 2012 " Lhasa receive golden bridge bridge tower sections full scale model test research ".
Yet anchorage drum also exposes some problems after use: 1) in cylinder, mortar and exposed steel strand are bonded together, and guy system can not carry out the replacing of single steel strand, and economy is not good; 2) anchor slab of anchorage drum by saddle end is passed to king-post by out-of-balance force and makes the local tension in region, king-post top layer, and the anchoring of anchor slab and king-post exists drawing fatigue effect; 3) under variable action, because girder bending-down makes drag-line, at nearly king-post position, occur micro-corner, anchorage drum has limited drag-line and has freely rotated, and the anchoring structure of the joint portion of anchorage drum and anchor slab, anchor slab and king-post is all by Bending fatigue effect.Therefore, have scholar to advise cancelling also needs the way that grouting-type anchorage drum is set with simplified design, construction and later maintenance (can inquire into > > referring to the test of article < < low-pylon cable-stayed bridge cable saddle section model and the design of 2 phase < < Southeast China University's journal (natural science edition) > > in 2007) beyond saddle.
Recent year has been researched and developed the mechanical friction skidding device (as shown in Figure 5) of minute fiber tube saddle and for real bridge (can referring to < < bridge construction > > 6 interim article < < low-pylon cable-stayed bridges in 2012 intersect research and the application > > of antiskid key), adopt the one-sided antiskid key lock of steel strand, the pattern of bidirectional crossed layout realizes the whole antiskid anchoring of drag-line, its simple structure and can realize the replacing of single steel strand, overcome the shortcoming of anchorage drum structure.
But adopt the guy of twisted steel cable of antiskid key still to have problems when mounted, when being configured in construction, this adopts the form compression antiskid key (as shown in Figure 6) that applies super stretching force (super stretch-draw coefficient is less than 3%) in one-sided (nonreactive feather key one side) of single steel strand, the steel strand of half quantity in the whole bundle drag-line of each super stretch-draw of the every side of king-post.This method make every steel strand in king-post both sides the internal force of (saddle is with beyond antiskid key) different, there is different design safety factors in same steel strand.From a certain section (beyond saddle and antiskid key) of whole bundle drag-line, the pulling force of every steel strand is different, and execute-in-place is easily made mistakes, and whether construction monitoring personnel are difficult to define whole Shu Suoli deviation and meet the demands.Therefore, necessary improvement is usingd antiskid key as the method for stretching of the guy of twisted steel cable of locking device, realizes the optimization in design, construction and monitoring.
Summary of the invention
Because the above-mentioned deficiency of prior art, the present invention proposes a kind ofly can to realize that design, construction and monitoring are upper to be optimized, make that the Suo Li of drag-line in king-post outside is identical, antiskid key and king-post closely connected and possess that enough pressure lays in using the stretch-draw construction method of antiskid key as the guy of twisted steel cable of locking device.
For achieving the above object, a kind ofly using the stretch-draw construction method of antiskid key as the guy of twisted steel cable of locking device, on king-post, be equipped with and using the drag-line of antiskid key as locking device, on each root steel strand, be provided with primary antibodie feather key, described antiskid key is crisscross arranged on the both sides of king-post, comprises the following steps:
Step 1, one-sided super stretching force put in nearly king-post side and do not arrange on the drag-line of antiskid key.
The one-sided drag-line of step 2, king-post is at the construction stage steel strand of super half quantity of stretch-draw respectively.
Step 3, every bundle drag-line when stretch-draw should from be positioned at middle part steel strand, then successively outside.
Step 4, remember that every bundle drag-line target stretching rope power is F c, steel strand quantity is N, every steel strand are at the target stretching rope power f of construction stage c=F c/ N.
Step 5, every bundle drag-line were surveyed coefficient of friction resistance μ before stretch-draw: tested steel twisted wire two ends are installed to jack and prepare sensor, one end is made as fixed end, other end stretch-draw is to construction Suo Li, and the rope force rate of calculating fixed end and super stretching end is worth stretch-draw efficiency factor K, by K=e -μ θ, in conjunction with recording the accumulative total steering angle θ of drag-line in king-post inside, can obtain coefficient of friction resistance μ.
Step 6, remember that the super stretching force of every steel strand is f k, f k=f c/ (2K-1).
Step 7, every steel strand are at nonreactive feather key side pretensioning, and its stretching force need be greater than actual measurement frictional resistance, to guarantee that antiskid key is close to cable saddle end face.
Step 8, every steel strand are when having the stretch-draw of antiskid key side, and nonreactive feather key side also must simultaneous tension, remains that the stretching force of nonreactive feather key side has been greater than antiskid key side stretching force in stretching process, between 1~2 times that the difference of both sides is actual measurement frictional resistance.
Step 9, there iing the stretch-draw of antiskid key side to monitoring objective stretching rope power f when every steel strand ctime, first anchoring, then arrives super stretching force f by the stretch-draw of nonreactive feather key side kdrop to again target stretching rope power f c, then anchoring, completes the stretching construction of guy of twisted steel cable.
Preferably, after completing described step 5, carry out before described step 6, also be provided with a coefficient of friction resistance and check step: transposing application of force direction, by fixed end stretch-draw before this, super stretching end is fixed, and oppositely measures and show that coefficient of friction resistance μ ' checks, the error of coefficient of friction resistance μ and μ ' is less than 0.01 and carries out described step 6, otherwise remeasures coefficient of friction resistance μ and μ '.
Preferably, described step 5 is chosen first and second root of every bundle drag-line and the actual measurement coefficient of friction resistance of last root steel strand is noted down.
Target of the present invention is to optimize mounting method, make that the Suo Li of drag-line in king-post outside is identical, antiskid key and king-post closely connected and possess enough pressure deposits.It is calculated to theoretical basis below and key Design method is further discussed in detail:
(1) calculate theoretical basis
When the effect of guy of twisted steel cable out-of-balance force can be passed to mechanical friction skidding device, every steel strand cannot reach balance in saddle, and direction all deviates from out-of-balance force one side, and drag-line relies on mechanical friction skidding device place and bears extruding force and just can reach balance.Get mechanical friction skidding device as slider (as shown in Figure 7), its stress can be explained with following formula:
F a+f m=F be -μθ (1)
In formula, F atarget Suo Li for during Cantilever Construction or one-tenth bridge stage steel strand; f mthe extruding force of bearing for mechanical friction skidding device; F bsuo Li for the super stretching end of steel strand; μ is the coefficient of friction resistance of guy of twisted steel cable in saddle; θ is that drag-line is at the accumulative total steering angle (rad) of king-post inside.
For engineering design, do not wish that the friction skidding device closely connected with anchor slab is drawn out, the standard that is set as follows is to meet design requirement:
f m≥γ dΔf ( 2)
In formula, Δ f is the out-of-balance force effect that drag-line is subject to; γ dfor design pressure deposit safety factor.
Get friction skidding device as slider, with reference to formula (1), can obtain:
F adΔf≤F be -μθ (3)
(2) key Design method
Consider to utilize reverse friction power to eliminate the excessive super stretching force of drag-line revealed section, control to greatest extent the difference of saddle both sides exit Suo Li and guarantee that antiskid key is not drawn out:
1) first will be without the super F that is stretched to of friction skidding device side k, have friction skidding device side to be stretched to pass line power F a(F a<F k), (pressure deposit is a and a>=γ to make friction skidding device (being antiskid key) pressurized dΔ f).
2) will be loaded onto pass line power F without friction skidding device side dumping again b, then anchoring, the reverse friction power while utilizing unloading retains suitable pressure deposit (as shown in Figure 8) at friction skidding device place.With reference to formula (3), theoretical model is expressed as formula (4):
F a+a=F ke -μθ ( 4)
According to calculating target, make saddle export two end cable forces identical, i.e. F b=F aand f=0, suppose that reverse friction when the super stretch-draw side dumping of drag-line is carried is identical with positive frictional resistance, pressure deposit can be expressed as formula (5):
a=F k(1-e -μθ) ( 5)
Bring formula (5) into formula (4) and can obtain formula (6):
F k = F a 2 e - &mu;&theta; - 1 - - - ( 6 )
Formula (5)~(6) can be according to F a, μ, θ solve, so the method that the present invention sets up is feasible.
Now, drag-line is being implemented the elongation L of super stretch-draw side bin available Fig. 8, " curve 2 " surrounds area divided by guy of twisted steel cable elastic modulus E with horizontal axis swith sectional area A sand obtain:
L b = F k E s A s e - &mu;&theta; S 0 - &Integral; 0 S 0 ( F k E s A s e - &mu; s R - F k E s A s e - &mu;&theta; ) ds = 2 &CenterDot; F k E s A s e - &mu;&theta; S 0 - F k E s A s &CenterDot; R &mu; ( 1 - e - &mu; S 0 R ) - - - ( 7 )
Due to friction skidding device closely connected king-post still under live loading (king-post left side), the left side Suo Li F in Fig. 8 acannot surmount F ke -μ θ.And being subject to positive frictional resistance under live loading, super stretch-draw side affects its Suo Li F balso cannot surmount F ke -μ θ.Therefore, the maximum internal force of drag-line in saddle pipeline is F ke -μ θ, be also F a+ a.
It is of the present invention that to using antiskid key as follows as the beneficial effect of the stretch-draw construction method of the guy of twisted steel cable of locking device:
1) the present invention has optimized mounting method, make drag-line in king-post two outsides identical, the antiskid key of the Suo Li of (saddle is with beyond antiskid key) and king-post closely connected and possess enough pressure deposits.
2) internal force of (saddle is with beyond antiskid key) is identical in king-post both sides to the invention enables every steel strand, improved the degree of safety of whole bundle drag-line, antiskid key coupling mechanism force is more reliable, the distortion of drag-line in saddle district is less, drag-line is constant at the maximum internal force in saddle district, does not therefore have fatigue problem.
3) site operation is conveniently not easy to make mistakes, and drag-line is that single steel strand is operated thereby super stretching force can not cause excessive impact to structural entity when implementing super stretch-draw.
4) the design Suo Li of every steel strand of drag-line revealed section is identical, and construction monitoring personnel are convenient to control the Suo Li deviation of whole bundle drag-line.
Below with reference to accompanying drawing, the technique effect of design of the present invention, concrete structure and generation is described further, to understand fully object of the present invention, feature and effect.
Accompanying drawing explanation
Fig. 1 is structure of saddle schematic diagram.
Fig. 2 is two cannula configuration schematic diagrames.
Fig. 3 is a minute fiber tube organigram.
Fig. 4 is anti-slip anchoring tube organigram.
Fig. 5 is antiskid key organigram.
Fig. 6 is usingd the method for stretching schematic diagram of antiskid key as the guy of twisted steel cable of locking device.
Fig. 7 is mechanical friction skidding device slider force analysis figure.
Fig. 8 is the Suo Li distribution map of super stretching end after putting.
Fig. 9 is the one-sided super stretching force applying method schematic diagram of drag-line.
Figure 10 is king-post and saddle total structure schematic diagram.
The specific embodiment
As shown in Figure 9 and Figure 10, the present embodiment a kind of usingd the stretch-draw construction method of antiskid key as the guy of twisted steel cable of locking device, on king-post, be equipped with and using the drag-line of antiskid key as locking device, on each root steel strand, be provided with primary antibodie feather key, described antiskid key is crisscross arranged on the both sides of king-post, comprises the following steps:
Step 1, one-sided super stretching force put in nearly king-post side and do not arrange on the drag-line of antiskid key.
The one-sided drag-line of step 2, king-post is at the construction stage steel strand of super half quantity of stretch-draw respectively.
Step 3, every bundle drag-line when stretch-draw should from be positioned at middle part steel strand, then successively outside.
Step 4, remember that every bundle drag-line target stretching rope power is F c, steel strand quantity is N, every steel strand are at the target stretching rope power f of construction stage c=F c/ N.
Step 5, every bundle drag-line were surveyed coefficient of friction resistance μ before stretch-draw: tested steel twisted wire two ends are installed to jack and prepare sensor, one end is made as fixed end, other end stretch-draw is to construction Suo Li, and the rope force rate of calculating fixed end and super stretching end is worth stretch-draw efficiency factor K, by K=e -μ θ, in conjunction with recording the accumulative total steering angle θ of drag-line in king-post inside, can obtain coefficient of friction resistance μ; Then change application of force direction, by fixed end stretch-draw before this, super stretching end is fixed, and oppositely measures and show that coefficient of friction resistance μ ' checks, the error of coefficient of friction resistance μ and μ ' is less than 0.01 and carries out described step 6, otherwise remeasures coefficient of friction resistance μ and μ '; Wherein, can choose first and second root of every bundle drag-line and the actual measurement coefficient of friction resistance of last root steel strand is noted down.
Step 6, remember that the super stretching force of every steel strand is f k, f k=f c/ (2K-1).
Step 7, every steel strand are at nonreactive feather key side pretensioning, and its stretching force need be greater than actual measurement frictional resistance, to guarantee that antiskid key is close to cable saddle end face.
Step 8, every steel strand are when having the stretch-draw of antiskid key side, and nonreactive feather key side also must simultaneous tension, remains that the stretching force of nonreactive feather key side has been greater than antiskid key side stretching force in stretching process, between 1~2 times that the difference of both sides is actual measurement frictional resistance.
Step 9, there iing the stretch-draw of antiskid key side to monitoring objective stretching rope power f when every steel strand ctime, first anchoring, then arrives super stretching force f by the stretch-draw of nonreactive feather key side kdrop to again target stretching rope power f c, then anchoring, completes the stretching construction of guy of twisted steel cable.
Concrete, design principles according to the present invention is applied the present embodiment and is usingd the stretch-draw construction method of antiskid key as the guy of twisted steel cable of locking device on certain bridge: the guy of twisted steel cable of this bridge has adopted mechanical type friction skidding device (the antiskid key of many steel strand is with respect to king-post center line arranged crosswise), and king-post and saddle total structure are as shown in figure 10.Shown in Fig. 9, the maximal unbalanced force causing with bridge permanent action and variable action act as according to determining drag-line friction skidding device minimum pressure deposit, the maximum (normal) stress that guarantees the inhaul cable operation phase meets standard and designing requirement, by limiting the uneven weight of maximum of during Cantilever Construction, guarantees that drag-line is in the interim antiskid safety in saddle district.Operation phase unbalanced load has adopted full-bridge spatial beam model to load and has solved, and during cantilever construction, maximum permissible unbalance weight solves based on linear superposition theorem by considering the FEM (finite element) model of construction overall process.Adopt method of the present invention to calculate the stress of drag-line in saddle district, according to field measurement coefficient of friction resistance data mu=0.06, obtained the result in table 1.
The stress of the drag-line in certain Bridge Construction stage of table 1 in saddle district gathers
Through calculating, drag-line in king-post both sides identical, the antiskid key of the Suo Li of (saddle is with beyond antiskid key) and king-post closely connected and possess enough pressure deposits, this method has reached predeterminated target.
More than describe preferred embodiment of the present invention in detail.Should be appreciated that those of ordinary skill in the art just can design according to the present invention make many modifications and variations without creative work.Therefore, all technician in the art, all should be in the determined protection domain by claims under this invention's idea on the basis of existing technology by the available technical scheme of logical analysis, reasoning, or a limited experiment.

Claims (3)

1.一种以抗滑键作为锁定装置的钢绞线拉索的张拉施工方法,在塔柱上穿设有以抗滑键作为锁定装置的拉索,每一根钢绞线上均设置有一抗滑键,所述抗滑键交错设置在塔柱的两侧上,其特征在于,包括以下步骤:1. A tensioning construction method of a steel strand cable with an anti-slip key as a locking device, a cable with an anti-slip key as a locking device is threaded on the tower column, and each steel strand is provided with a There is an anti-skid key, and the anti-skid key is staggeredly arranged on both sides of the tower column, which is characterized in that it includes the following steps: 步骤一、单侧超张拉力施加于在近塔柱侧未布置抗滑键的拉索上;Step 1. Unilateral hypertension tension is applied to the cables that are not arranged with anti-skid keys on the side near the tower column; 步骤二、塔柱单侧的拉索在施工阶段分别超张拉一半数量的钢绞线;Step 2. The cables on one side of the tower column are respectively over-tensioned by half of the number of steel strands during the construction stage; 步骤三、每束拉索在张拉时应从位于中部的钢绞线开始,然后逐次向外;Step 3. Each bundle of cables should start from the steel strand in the middle when stretching, and then go outward one by one; 步骤四、记每束拉索目标张拉索力为Fc,钢绞线数量为N,则每根钢绞线在施工阶段的目标张拉索力fc=Fc/N;Step 4. Record the target tension force of each cable as F c , and the number of steel strands is N, then the target tension force of each steel strand in the construction stage is f c =F c /N; 步骤五、每束拉索在张拉之前实测摩阻系数μ:将测试钢绞线两端装好千斤顶并配好传感器,一端设为固定端,另一端张拉到施工索力,计算固定端与超张拉端的索力比值得张拉效率系数K,由K=e-μθ,结合测得拉索在塔柱内部的累计转向角度θ,可获取摩阻系数μ;Step 5. Measure the friction coefficient μ of each cable before tensioning: install jacks and sensors at both ends of the test steel strand, set one end as a fixed end, and stretch the other end to the construction cable force, and calculate the fixed end The tension efficiency coefficient K is the ratio of the cable force to the super-tensioned end, and the friction coefficient μ can be obtained by combining the measured cumulative steering angle θ of the cable inside the tower column by K=e -μθ ; 步骤六、记每根钢绞线的超张拉力为fk,则fk=fc/(2K-1);Step 6, record the supertension tension of each steel strand as f k , then f k =f c /(2K-1); 步骤七、每根钢绞线在无抗滑键侧先张拉,其张拉力需大于实测摩阻力,以保证抗滑键紧贴着索鞍端面;Step 7. Each steel strand is first tensioned on the side without the anti-skid key, and the tension force must be greater than the measured frictional resistance to ensure that the anti-skid key is close to the end face of the saddle; 步骤八、每根钢绞线在有抗滑键侧张拉时,无抗滑键侧也须同时张拉,张拉过程中始终保持无抗滑键侧的张拉力大于有抗滑键侧张拉力,两侧的差值为实测摩阻力的1~2倍之间;Step 8. When each steel strand is stretched on the side with anti-skid key, the side without anti-skid key must also be stretched at the same time. During the tensioning process, the tension on the side without anti-skid key is always greater than that on the side with anti-skid key. Pulling force, the difference between the two sides is between 1 and 2 times of the measured frictional resistance; 步骤九、当每根钢绞线在有抗滑键侧张拉到监控目标张拉索力fc时,先锚固,然后将无抗滑键侧张拉到超张拉力fk再降到目标张拉索力fc,然后锚固,完成钢绞线拉索的张拉施工。Step 9. When each steel strand is stretched to the monitoring target tension cable force f c on the side with anti-skid key, anchor it first, and then stretch the side without anti-skid key to the overtension force f k and then lower it to the target The cable force f c is tensioned, and then anchored to complete the tensioning construction of the steel strand cable. 2.如权利要求1所述的以抗滑键作为锁定装置的钢绞线拉索的张拉施工方法,其特征在于:在完成所述步骤五后,进行所述步骤六前,还设置有一摩阻系数校核步骤:调换施力方向,将此前的固定端张拉,超张拉端固定,反向测量并得出摩阻系数μ′进行校核,摩阻系数μ和μ′的误差小于0.01则执行所述步骤六,否则重新测量摩阻系数μ和μ′。2. The tensioning construction method of steel strand cables using anti-skid keys as locking devices as claimed in claim 1, characterized in that: after completing said step 5, before performing said step 6, a Friction coefficient checking steps: change the direction of force, stretch the previous fixed end, fix the over-tensioned end, reverse measurement and get the friction coefficient μ′ for verification, the error of friction coefficient μ and μ′ If it is less than 0.01, execute the sixth step; otherwise, re-measure the friction coefficients μ and μ′. 3.如权利要求1或2所述的以抗滑键作为锁定装置的钢绞线拉索的张拉施工方法,其特征在于:所述步骤五选取每束拉索的第一、二根及最后一根钢绞线的实测摩阻系数作记录。3. as claimed in claim 1 or 2, take the anti-skid key as the tensioning construction method of the steel strand stay cable of locking device, it is characterized in that: described step 5 selects the first, second and second strands of each bunch of stay cables The measured friction coefficient of the last steel strand is recorded.
CN201410363165.5A 2014-07-28 2014-07-28 Tension construction method of steel strand cable with anti-skid key as locking device Active CN104099874B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410363165.5A CN104099874B (en) 2014-07-28 2014-07-28 Tension construction method of steel strand cable with anti-skid key as locking device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410363165.5A CN104099874B (en) 2014-07-28 2014-07-28 Tension construction method of steel strand cable with anti-skid key as locking device

Publications (2)

Publication Number Publication Date
CN104099874A true CN104099874A (en) 2014-10-15
CN104099874B CN104099874B (en) 2016-03-23

Family

ID=51668390

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410363165.5A Active CN104099874B (en) 2014-07-28 2014-07-28 Tension construction method of steel strand cable with anti-skid key as locking device

Country Status (1)

Country Link
CN (1) CN104099874B (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105239507A (en) * 2015-10-28 2016-01-13 上海市城市建设设计研究总院 Steering gear of cable member
CN105445181A (en) * 2015-11-25 2016-03-30 安徽金星预应力工程技术有限公司 Method for measuring friction coefficients of pre-stressed ducts of water-drop-shaped cable saddle of stay cable
CN106012795A (en) * 2016-04-13 2016-10-12 中交第二航务工程局有限公司 Cable-stayed bridge cable bent tower intersection structure with double-oval appearance
CN106948263A (en) * 2017-05-10 2017-07-14 安徽省交通控股集团有限公司 A kind of cable-stayed bridge concrete pylon anchor tie plate
CN107217593A (en) * 2017-06-01 2017-09-29 西南交通大学 A kind of main push-towing rope for the main saddle of suspension bridge is layered anti-skid construction
CN108149928A (en) * 2017-12-21 2018-06-12 中交路桥华南工程有限公司 The tower end installation method of suspension cable
CN108229035A (en) * 2018-01-09 2018-06-29 安徽省交通控股集团有限公司 A kind of design method for cable-stayed bridge sub-wire clamp-type saddle
CN108330812A (en) * 2018-03-27 2018-07-27 安徽省交通控股集团有限公司 Using the cable-stayed bridge of revolution drag-line in the same direction
CN108660907A (en) * 2018-06-14 2018-10-16 中铁贵州旅游文化发展有限公司 A kind of super open of stay cable force puts a structure
CN109883624A (en) * 2019-04-11 2019-06-14 招商局重庆交通科研设计院有限公司 A water tightness test equipment with cylindrical design
CN111455855A (en) * 2020-04-16 2020-07-28 中交一公局第四工程有限公司 Construction process of main bridge of double-tower single-cable-plane short-tower cable-stayed bridge
CN112411376A (en) * 2020-12-07 2021-02-26 柳州市邱姆预应力机械有限公司 Inhaul cable anti-skidding device and installation method thereof
CN114657893A (en) * 2022-04-26 2022-06-24 中交一公局集团有限公司 A Single Synchronous Tensioning Device for Stay Cables Based on Spatial Shape
CN114934451A (en) * 2022-05-10 2022-08-23 柳州欧维姆结构检测技术有限公司 Method for dismantling steel strand stay cable with steering cable saddle
CN115075137A (en) * 2022-06-09 2022-09-20 江阴法尔胜住电新材料有限公司 Stay cable tensioning and locking method based on balance control

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02167906A (en) * 1988-12-20 1990-06-28 Taisei Corp Structure of pc cable at crooked part
CN1253196A (en) * 1998-11-09 2000-05-17 柳州欧维姆建筑机械有限公司 Method for stretching guy of twisted steel cable for cable stayed bridge
JP2012117215A (en) * 2010-11-29 2012-06-21 Ihi Infrastructure Systems Co Ltd Detection device of tension of heavy object supporting cable
US20130140509A1 (en) * 2009-12-24 2013-06-06 Vsl International Ag "method and system for equally tensioning multiple strands"
CN203603025U (en) * 2013-11-25 2014-05-21 中铁第四勘察设计院集团有限公司 Curve extra-dosed cable-stayed bridge for ballastless track railway

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02167906A (en) * 1988-12-20 1990-06-28 Taisei Corp Structure of pc cable at crooked part
CN1253196A (en) * 1998-11-09 2000-05-17 柳州欧维姆建筑机械有限公司 Method for stretching guy of twisted steel cable for cable stayed bridge
US20130140509A1 (en) * 2009-12-24 2013-06-06 Vsl International Ag "method and system for equally tensioning multiple strands"
JP2012117215A (en) * 2010-11-29 2012-06-21 Ihi Infrastructure Systems Co Ltd Detection device of tension of heavy object supporting cable
CN203603025U (en) * 2013-11-25 2014-05-21 中铁第四勘察设计院集团有限公司 Curve extra-dosed cable-stayed bridge for ballastless track railway

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘钊等: "部分斜拉桥索鞍锚固区设计探讨", 《OVM通讯》 *

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105239507A (en) * 2015-10-28 2016-01-13 上海市城市建设设计研究总院 Steering gear of cable member
CN105445181A (en) * 2015-11-25 2016-03-30 安徽金星预应力工程技术有限公司 Method for measuring friction coefficients of pre-stressed ducts of water-drop-shaped cable saddle of stay cable
CN106012795A (en) * 2016-04-13 2016-10-12 中交第二航务工程局有限公司 Cable-stayed bridge cable bent tower intersection structure with double-oval appearance
CN106012795B (en) * 2016-04-13 2017-11-03 中交第二航务工程局有限公司 Bielliptic(al) moulding Cable-stayed Bridge Pylon crosses structure
CN106948263B (en) * 2017-05-10 2019-02-19 安徽省交通控股集团有限公司 A kind of cable-stayed bridge concrete pylon anchor tie plate
CN106948263A (en) * 2017-05-10 2017-07-14 安徽省交通控股集团有限公司 A kind of cable-stayed bridge concrete pylon anchor tie plate
CN107217593A (en) * 2017-06-01 2017-09-29 西南交通大学 A kind of main push-towing rope for the main saddle of suspension bridge is layered anti-skid construction
CN108149928B (en) * 2017-12-21 2020-05-19 中交路桥华南工程有限公司 Tower end installation method of stay cable
CN108149928A (en) * 2017-12-21 2018-06-12 中交路桥华南工程有限公司 The tower end installation method of suspension cable
CN108229035A (en) * 2018-01-09 2018-06-29 安徽省交通控股集团有限公司 A kind of design method for cable-stayed bridge sub-wire clamp-type saddle
CN108229035B (en) * 2018-01-09 2020-11-06 安徽省交通控股集团有限公司 Design method for cable-stayed bridge wire-dividing clamping type saddle
CN108330812A (en) * 2018-03-27 2018-07-27 安徽省交通控股集团有限公司 Using the cable-stayed bridge of revolution drag-line in the same direction
CN108660907B (en) * 2018-06-14 2024-02-23 中铁贵州旅游文化发展有限公司 Stay cable force overstretching structure
CN108660907A (en) * 2018-06-14 2018-10-16 中铁贵州旅游文化发展有限公司 A kind of super open of stay cable force puts a structure
CN109883624A (en) * 2019-04-11 2019-06-14 招商局重庆交通科研设计院有限公司 A water tightness test equipment with cylindrical design
CN109883624B (en) * 2019-04-11 2024-03-15 招商局重庆交通科研设计院有限公司 Water tightness test equipment adopting cylindrical surface design
CN111455855A (en) * 2020-04-16 2020-07-28 中交一公局第四工程有限公司 Construction process of main bridge of double-tower single-cable-plane short-tower cable-stayed bridge
CN111455855B (en) * 2020-04-16 2021-11-12 中交一公局第四工程有限公司 Construction process of main bridge of double-tower single-cable-plane short-tower cable-stayed bridge
CN112411376A (en) * 2020-12-07 2021-02-26 柳州市邱姆预应力机械有限公司 Inhaul cable anti-skidding device and installation method thereof
CN114657893A (en) * 2022-04-26 2022-06-24 中交一公局集团有限公司 A Single Synchronous Tensioning Device for Stay Cables Based on Spatial Shape
CN114657893B (en) * 2022-04-26 2024-06-25 中交一公局集团有限公司 A single synchronous tensioning device for inclined cables based on spatial special shapes
CN114934451A (en) * 2022-05-10 2022-08-23 柳州欧维姆结构检测技术有限公司 Method for dismantling steel strand stay cable with steering cable saddle
CN114934451B (en) * 2022-05-10 2024-05-14 柳州欧维姆结构检测技术有限公司 Dismantling method of steel strand stay cable with steering cable saddle
CN115075137A (en) * 2022-06-09 2022-09-20 江阴法尔胜住电新材料有限公司 Stay cable tensioning and locking method based on balance control

Also Published As

Publication number Publication date
CN104099874B (en) 2016-03-23

Similar Documents

Publication Publication Date Title
CN104099874A (en) Steel strand inhaul cable tension construction method by taking slip-resistant stud as locking device
Qu et al. Investigation and verification on seismic behavior of precast concrete frame piers used in real bridge structures: Experimental and numerical study
CN106442541B (en) A kind of Cable Structure monitoring method based on long gauge length optical fibre grating sensor
Napoli et al. Bond behaviour of Steel Reinforced Polymer strengthening systems
CN108798062A (en) Steel-concrete interface damage monitoring based on marmem and reinforcement means
Grace et al. Flexural behavior of CFRP precast prestressed decked bulb T-beams
CN104020056B (en) The loading method of concrete creep test under the effect of a kind of curved scissors pressure compound stress
CN104931364B (en) Reinforced concrete structure method for testing fatigue and device based on piezomagnetism
Liu et al. Measurement and comparative study on movements of suspenders in long-span suspension bridges
Yanes-Armas et al. System transverse in-plane shear stiffness of pultruded GFRP bridge decks
CN104233942A (en) Method for enhancing overall stress on assembled type heterotropic pre-stress hollow slab beam bridge
CN103837279A (en) Prestress anchoring structure tensioning force detecting system based on single-freedom-degree system
CN203053625U (en) Static inhaul cable force monitoring device
CN105571958A (en) Large-diameter high-strength composite circular tube torsion test device and test method thereof
Jawdhari et al. Bond study on CFRP rod panels externally adhered to concrete
CN110359356A (en) Small arrow degree difference cable way bridge
Qi et al. The first engineering application of 10MN CFRP cables in cable-stayed bridge in China
Al-Hayek et al. Flexural strength of posttensioned timber beams
CN114858436B (en) Slidable steel anchor box combined cable tower model test device
CN204789007U (en) Arch structural test load loading device
CN106149541B (en) Prestressed tensioning prefabricated box type bridge and construction method
Cho et al. Evaluation of Cable Tension Forces Using Vibration Method for a Cable-stayed Bridge under Construction
CN101363762B (en) Pressure dispersion type anchor cable stress state monitoring device based on force transmission plate
CN207114077U (en) A kind of prestressing force measurement apparatus of large-diameter pipeline
CN203960756U (en) A kind of No. 0 interim prestressed strand system of piece case beam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 200011 Tibet South Road, Shanghai, No. 1170, No.

Patentee after: Shanghai urban construction design & Research Institute (Group) Co., Ltd.

Address before: 200011 Tibet South Road, Shanghai, No. 1170, No.

Patentee before: Shanghai Urban Construction Design & Research Institute